Summary

This document contains questions and answers related to project management, risk management, and procurement topics. It includes examples of different types of contracts and risk assessments.

Full Transcript

A project involves implementing a new software system, and one identified risk is a potential delay due to stakeholder unavailability for key workshops. The probability is medium, and the impact is high. What is the best risk response?\ a. Mitigate the risk by scheduling workshops well in advance an...

A project involves implementing a new software system, and one identified risk is a potential delay due to stakeholder unavailability for key workshops. The probability is medium, and the impact is high. What is the best risk response?\ a. Mitigate the risk by scheduling workshops well in advance and providing alternate participation methods.\ b. Transfer the risk by outsourcing the facilitation of workshops to a third party.\ c. Accept the risk and proceed with the current schedule.\ d. Escalate the risk to senior management to manage stakeholder availability.\ Correct Answer: A A project manager discovers that a key resource might be reassigned to another project, potentially delaying the timeline. What is the most effective response?\ a. Escalate the risk to the sponsor and request a decision on resource prioritization.\ b. Avoid the risk by assigning a backup resource immediately.\ c. Accept the risk and adjust the schedule if the resource is reassigned.\ d. Mitigate the risk by cross-training other team members to fill the role.\ Correct Answer: D The risk register includes a threat of regulatory changes that could impact project scope. The probability is low, but the impact is very high. What strategy should the project manager adopt?\ a. Monitor the risk and implement contingent responses if the changes occur.\ b. Transfer the risk by purchasing insurance against compliance penalties.\ c. Avoid the risk by modifying the project scope to exclude regulatory exposure.\ d. Escalate the risk to legal counsel to track potential changes.\ Correct Answer: A The team is conducting a risk analysis using a Probability and Impact Matrix. A risk with a probability of 70% and an impact of \$50,000 is identified. If the risk threshold is set at 4, what should the project manager do?\ a. Prioritize the risk for immediate response planning.\ b. Accept the risk as it falls below the threshold.\ c. Escalate the risk to the sponsor for further evaluation.\ d. Defer action until the risk probability or impact changes.\ Correct Answer: A A previously low-risk item in the risk register now has a much higher probability due to recent project changes. How should the project manager handle this?\ a. Update the risk score and evaluate whether the response strategy needs modification.\ b. Accept the change and proceed with the original response strategy.\ c. Remove the item from the risk register to avoid unnecessary focus.\ d. Escalate the updated risk to the project sponsor for further action.\ Correct Answer: A The project involves procuring specialized equipment. The seller proposes a Cost Plus Percentage Fee (CPPF) contract. How should the project manager handle this?\ a. Negotiate for a Fixed Price or Cost Plus Incentive Fee (CPIF) contract to minimize buyer risk.\ b. Accept the contract as it aligns with the project's procurement strategy.\ c. Request additional guarantees from the seller to mitigate risk.\ d. Decline the contract and seek alternative sellers.\ Correct Answer: A A vendor fails to deliver on time, citing unforeseen supply chain issues. The contract is Fixed Price. What is the project manager's best course of action?\ a. Enforce contract terms and apply penalties for late delivery.\ b. Accept the delay and update the project schedule.\ c. Renegotiate the contract to accommodate the vendor's issues.\ d. Terminate the contract and engage a new vendor immediately.\ Correct Answer: A The team is evaluating proposals from multiple sellers using a Weighted Scoring Model. One seller scores high on technical criteria but offers the highest price. What should the project manager prioritize?\ a. Balance cost and quality by selecting a seller with moderate scores in both areas.\ b. Select the seller with the highest technical score, as quality is critical.\ c. Choose the lowest-cost seller to maintain the budget.\ d. Use Best and Final Offer (BAFO) negotiations to lower the high-scoring seller's price.\ Correct Answer: D A project requires a Time and Materials (T&M) contract for an undefined scope. What should the project manager do to manage cost risks?\ a. Set a price ceiling in the contract to limit financial exposure.\ b. Avoid T&M contracts and insist on a Fixed Price agreement.\ c. Track costs monthly and request additional funds as needed.\ d. Rely on contingency reserves to cover any cost overruns.\ Correct Answer: A The project sponsor prefers to avoid risk in procurement and asks for a contract type that minimizes buyer uncertainty. Which contract type should the project manager recommend?\ a. Firm Fixed Price (FFP) contract.\ b. Cost Plus Fixed Fee (CPFF) contract.\ c. Time and Materials (T&M) contract.\ d. Cost Plus Incentive Fee (CPIF) contract.\ Correct Answer: A During a procurement process, the seller insists on using their own terms and conditions, which include a clause limiting their liability for delays. This poses a significant risk to the project. What is the best course of action?\ a. Negotiate to remove or revise the liability clause to better protect the buyer.\ b. Accept the seller\'s terms and include additional contingency reserves.\ c. Escalate the issue to the project sponsor for resolution.\ d. Reject the seller's proposal and move to the next bidder.\ Correct Answer: A A project manager identifies that a critical deliverable may not meet its deadline due to a subcontractor\'s performance. The contract is a Cost Plus Fixed Fee (CPFF) agreement. What should the project manager prioritize?\ a. Use performance incentives within the contract to motivate the subcontractor.\ b. Enforce penalties for delays as outlined in the contract.\ c. Request additional funds from the sponsor to mitigate the delay.\ d. Assign additional resources to the subcontractor to expedite work.\ Correct Answer: A A project risk assessment reveals a 20% probability of a \$100,000 loss due to a regulatory change. What is the expected monetary value (EMV) of this risk?\ a. \$20,000\ b. \$10,000\ c. \$50,000\ d. \$0 (no action required due to low probability)\ Correct Answer: A (EMV = Probability × Impact = 0.2 × \$100,000 = \$20,000) The team is considering insurance to transfer a high-impact risk related to construction delays. The premium is \$25,000, while the risk impact is \$250,000 with a 10% probability. Should the project manager recommend purchasing insurance?\ a. Yes, as the premium cost is lower than the potential EMV of the risk.\ b. No, because the probability is low, and it can be mitigated internally.\ c. Yes, as transferring the risk eliminates its impact on the project.\ d. No, as the premium exceeds 10% of the risk impact.\ Correct Answer: A (EMV = \$250,000 × 0.1 = \$25,000; the premium matches the EMV, making it a reasonable transfer strategy.) The project team identifies that an essential supplier has limited capacity to fulfill all requirements. What procurement strategy should the project manager use to address this?\ a. Develop a multiple-supplier agreement to diversify risk.\ b. Negotiate higher performance guarantees with the supplier.\ c. Switch to a fixed-price contract to minimize cost overruns.\ d. Allocate additional funds to ensure supplier compliance.\ Correct Answer: A During project execution, the CPI (Cost Performance Index) is 0.85, and the SPI (Schedule Performance Index) is 1.10. A new high-risk procurement is required. What should the project manager prioritize?\ a. Focus on cost management and select a vendor with the most favorable pricing.\ b. Maintain schedule performance by fast-tracking vendor onboarding.\ c. Perform a detailed cost-risk analysis before proceeding with procurement.\ d. Delay procurement until cost performance improves.\ Correct Answer: C The project requires procuring a component critical to the schedule. However, there is a risk of price increases due to market volatility. What should the project manager do?\ a. Lock in the price with a long-term fixed-price contract.\ b. Include an escalation clause in the contract to manage potential price increases.\ c. Procure the component just-in-time to minimize holding costs.\ d. Use a time and materials contract to account for price fluctuations.\ Correct Answer: A A stakeholder raises concerns about a high-risk procurement strategy involving a sole-source vendor. How should the project manager mitigate the risk?\ a. Perform a detailed due diligence process to assess the vendor's reliability.\ b. Include penalty clauses in the contract for non-performance.\ c. Develop a contingency plan to address potential vendor failure.\ d. All of the above.\ Correct Answer: D The team is conducting a quantitative risk analysis and identifies a risk with multiple potential outcomes: a 30% chance of \$50,000 loss, a 50% chance of no impact, and a 20% chance of \$80,000 gain. What is the EMV of the risk?\ a. \$11,000\ b. -\$5,000\ c. \$8,000\ d. \$13,000\ Correct Answer: A (EMV = (0.3 × -\$50,000) + (0.5 × \$0) + (0.2 × \$80,000) = -\$15,000 + \$0 + \$16,000 = \$11,000) The project manager identifies a new opportunity that could significantly enhance project value but would require reallocating contingency reserves. What is the best way to proceed?\ a. Conduct a cost-benefit analysis to evaluate the opportunity before reallocating reserves.\ b. Reallocate reserves immediately to seize the opportunity.\ c. Avoid reallocating contingency reserves to preserve risk management resources.\ d. Escalate the opportunity to the sponsor for approval without further analysis.\ Correct Answer: A A supplier offers a lower price in exchange for partial upfront payment, but this increases the project's financial risk. What should the project manager do?\ a. Negotiate for a smaller upfront payment to balance cost savings and risk.\ b. Accept the supplier's terms to maximize cost efficiency.\ c. Decline the offer to avoid increasing project risk.\ d. Use management reserves to cover the upfront payment.\ Correct Answer: A A project sponsor insists on accelerating a procurement process to meet an early delivery date. What should the project manager prioritize to mitigate risks?\ a. Perform a thorough vendor prequalification to ensure reliability under time constraints.\ b. Reduce the scope of the procurement to simplify vendor selection.\ c. Use sole-sourcing to expedite the procurement timeline.\ d. Escalate the sponsor's request to the procurement team for guidance.\ Correct Answer: A The project requires specialized training for vendor personnel. This was not included in the original contract. How should the project manager handle this?\ a. Issue a change order to formally add the training to the contract.\ b. Absorb the training cost within the project's contingency reserve.\ c. Negotiate with the vendor to provide training at no additional cost.\ d. Assign the training responsibility to internal team members.\ Correct Answer: A A project manager is monitoring a vendor contract with performance-based payments. The vendor delivers earlier than expected, but the quality is subpar. What is the best response?\ a. Enforce quality standards and withhold payments until the deliverable meets requirements.\ b. Accept the deliverable to maintain the schedule and address quality issues later.\ c. Provide partial payment to incentivize the vendor to correct quality issues.\ d. Terminate the contract and engage a new vendor.\ Correct Answer: A A project team identifies a risk with a high probability but low impact. The sponsor asks why no contingency reserve was allocated. What should the project manager explain?\ a. The risk falls below the threshold for contingency reserve allocation.\ b. Contingency reserves are reserved for high-impact risks only.\ c. The risk is being monitored and managed without additional funds.\ d. Reserves were used for higher-priority risks.\ Correct Answer: A A contractor on a Fixed Price Incentive Fee (FPIF) contract has met their milestone early but requests an additional incentive for exceeding the schedule. What is the best way for the project manager to handle this?\ a. Review the contract terms to determine if early delivery qualifies for additional incentives.\ b. Negotiate an additional incentive to maintain a positive contractor relationship.\ c. Deny the request and adhere strictly to the contract terms.\ d. Escalate the request to the sponsor for further decision-making.\ Correct Answer: A A project team identifies a risk related to potential delays in material delivery. The supplier offers an expedited delivery option at a premium cost. What should the project manager do?\ a. Conduct a cost-benefit analysis to determine if the premium cost justifies mitigating the delay risk.\ b. Approve the expedited delivery immediately to avoid project delays.\ c. Decline the expedited delivery to remain within budget.\ d. Request contingency funds to cover the premium cost.\ Correct Answer: A During a procurement audit, it is discovered that one vendor has been consistently underperforming. The vendor is under a Time and Materials (T&M) contract. What is the project manager's best course of action?\ a. Negotiate performance penalties into the existing contract.\ b. Switch to a Fixed Price contract to mitigate further risks.\ c. Terminate the contract and engage an alternative vendor.\ d. Implement stricter monitoring and review processes for the vendor's work.\ Correct Answer: D A quantitative risk analysis reveals that mitigating a high-risk event will cost \$20,000, but the EMV of the risk is only \$15,000. How should the project manager proceed?\ a. Accept the risk because the mitigation cost exceeds the EMV.\ b. Mitigate the risk to ensure it does not impact the project.\ c. Transfer the risk to a third party to avoid both mitigation and impact costs.\ d. Escalate the decision to the project sponsor.\ Correct Answer: A A project manager must choose between two suppliers. Supplier A has a proven track record but a higher cost, while Supplier B offers lower pricing but has limited experience. What is the best decision-making approach?\ a. Use a weighted scoring model to evaluate both suppliers based on cost and reliability criteria.\ b. Select Supplier A to ensure quality despite the higher cost.\ c. Choose Supplier B to remain within budget and allocate contingency for risks.\ d. Split the procurement between both suppliers to balance cost and quality.\ Correct Answer: A A project's risk register identifies a threat with high probability but low impact. The project sponsor questions why no mitigation plan is in place. What should the project manager do?\ a. Explain that monitoring the risk is sufficient given its low impact.\ b. Develop a mitigation plan immediately to address the sponsor's concern.\ c. Reallocate contingency reserves to fund a response plan for the risk.\ d. Escalate the issue to the risk management committee.\ Correct Answer: A The procurement team is considering a multi-year contract for recurring services. Market trends indicate potential cost reductions over time. What is the best procurement strategy?\ a. Include price adjustment clauses in the contract to leverage future cost reductions.\ b. Lock in the current rates with a long-term Fixed Price contract.\ c. Use a Time and Materials (T&M) contract to adjust costs as needed.\ d. Negotiate annual renewals instead of a multi-year agreement.\ Correct Answer: A A vendor under a Fixed Price contract submits a change request for additional payment due to unexpected labor costs. How should the project manager respond?\ a. Deny the change request, as the vendor is responsible for managing costs under the Fixed Price contract.\ b. Approve the request to maintain the vendor relationship.\ c. Negotiate a cost-sharing agreement for the additional expenses.\ d. Escalate the issue to the procurement team for resolution.\ Correct Answer: A A critical task requires a procurement item that is not available from any current vendors. The procurement team suggests developing a custom solution, which will significantly increase costs. What should the project manager prioritize?\ a. Perform a cost-benefit analysis to evaluate the feasibility of a custom solution.\ b. Approve the custom solution to avoid delays.\ c. Delay the task until a vendor offers a standard solution.\ d. Escalate the issue to the project sponsor for additional funding.\ Correct Answer: A The project sponsor insists on a rapid procurement process for critical materials, but the team is concerned about quality risks. What is the best way to address this?\ a. Implement a prequalification process to ensure vendors meet quality standards before procurement.\ b. Use sole-source procurement to expedite the process.\ c. Focus on cost reduction to balance quality risks.\ d. Escalate the sponsor's demand to the procurement team for resolution.\ Correct Answer: A The team identifies a risk that could delay project delivery. The mitigation plan involves reallocating resources from another critical task. What should the project manager do?\ a. Assess the overall project impact and consult stakeholders before reallocating resources.\ b. Proceed with resource reallocation to address the delay risk.\ c. Use contingency reserves to hire additional resources.\ d. Delay mitigation until more resources become available.\ Correct Answer: A A project manager receives a request from a vendor to renegotiate payment terms due to cash flow issues. The vendor is critical to project success. What should the project manager do?\ a. Review the request and negotiate terms that align with project goals and constraints.\ b. Deny the request to enforce the original contract terms.\ c. Provide a temporary advance payment to alleviate the vendor's cash flow issues.\ d. Replace the vendor to ensure continuity.\ Correct Answer: A The procurement team is evaluating a proposal from a vendor with limited industry experience. The vendor offers significant cost savings. What is the best decision-making approach?\ a. Use a weighted scoring model to evaluate the proposal against technical and cost criteria.\ b. Select the vendor to maximize cost savings and allocate contingency for risks.\ c. Decline the proposal due to the vendor's lack of experience.\ d. Engage the vendor for non-critical tasks to assess their capabilities.\ Correct Answer: A A quantitative risk analysis shows a risk with an EMV of \$50,000. The cost of mitigation is \$40,000, but it reduces the risk's impact by 80%. What is the best course of action?\ a. Proceed with the mitigation plan, as it provides a cost-effective risk reduction.\ b. Accept the risk, as the mitigation cost is close to the EMV.\ c. Transfer the risk to a third party to avoid direct costs.\ d. Delay mitigation until the risk materializes.\ Correct Answer: A A project team identifies a procurement risk involving vendor performance variability. The vendor proposes a Cost Plus Incentive Fee (CPIF) contract. How should the project manager proceed?\ a. Negotiate performance incentives tied to specific milestones to manage variability.\ b. Decline the CPIF contract and propose a Fixed Price contract.\ c. Accept the CPIF contract without modification to maintain vendor collaboration.\ d. Escalate the contract negotiation to the procurement team.\ Correct Answer: A A vendor offers a discount for bulk purchases, but this would require exceeding the allocated procurement budget. The discount could lead to long-term savings for future phases. What should the project manager prioritize?\ a. Evaluate the long-term cost-benefit of the bulk purchase and present a case for exceeding the budget.\ b. Decline the bulk purchase to stay within the current budget.\ c. Allocate contingency reserves to fund the bulk purchase.\ d. Postpone the decision until more budget is available.\ **Correct Answer**: A A vendor is under a Fixed Price contract but requests additional funds due to inflationary pressures. The request is not covered by contract terms. How should the project manager handle this?\ a. Enforce the original terms of the contract and deny the request.\ b. Escalate the issue to senior management to negotiate additional funding.\ c. Negotiate a contract amendment to share the cost burden of inflation.\ d. Terminate the vendor contract and engage a new supplier.\ **Correct Answer**: A A project involves high-cost procurement, and the sponsor requests monthly updates on procurement progress. What is the best way to manage this?\ a. Use Earned Value Management (EVM) to track procurement costs and provide detailed updates.\ b. Provide high-level updates and focus on minimizing procurement delays.\ c. Deliver updates only at key procurement milestones to reduce reporting workload.\ d. Assign a team member to create customized reports for the sponsor.\ **Correct Answer**: A During contract execution, a vendor consistently delivers late. The contract includes performance penalties, but enforcing them may strain the relationship. What should the project manager do?\ a. Enforce penalties while opening discussions to improve performance.\ b. Waive the penalties to maintain a positive relationship with the vendor.\ c. Terminate the contract to find a more reliable vendor.\ d. Escalate the issue to the procurement team for resolution.\ **Correct Answer**: A A project manager identifies a low-probability, high-impact risk related to vendor bankruptcy. The team suggests purchasing insurance, but the cost is significant. What is the best way to proceed?\ a. Evaluate the cost of insurance against the EMV of the risk and decide based on value.\ b. Purchase the insurance to eliminate the financial impact of the risk.\ c. Accept the risk due to its low probability and monitor the vendor's financial health.\ d. Transfer the risk to another vendor to avoid direct exposure.\ **Correct Answer**: A The team identifies a potential opportunity to reduce costs by using a less expensive supplier. However, the supplier has not been prequalified. What is the project manager's best response?\ a. Perform a thorough prequalification process before engaging the supplier.\ b. Engage the supplier for a trial period to evaluate their performance.\ c. Use the supplier for non-critical tasks to mitigate risk.\ d. Decline the supplier and stick with prequalified vendors.\ **Correct Answer**: A A key deliverable is delayed because the vendor's internal processes require additional time. The contract does not include time penalties. How should the project manager address this?\ a. Negotiate a timeline adjustment with the vendor to avoid further delays.\ b. Add penalties for future delays through a contract amendment.\ c. Escalate the delay to senior management for resolution.\ d. Accept the delay and update the project schedule.\ **Correct Answer**: A A project manager is conducting a procurement risk review and discovers a potential cost overrun due to fluctuating raw material prices. What is the best mitigation strategy?\ a. Negotiate price stabilization clauses into the vendor contract.\ b. Accept the risk and monitor market conditions for fluctuations.\ c. Add contingency reserves to cover potential price increases.\ d. Delay procurement until prices stabilize.\ **Correct Answer**: A A sponsor requests a sole-source procurement for a critical component due to time constraints. The procurement team raises concerns about cost and reliability. How should the project manager respond?\ a. Conduct a risk assessment of the sole-source procurement and present findings to the sponsor.\ b. Proceed with the sole-source procurement to meet the sponsor's timeline.\ c. Suggest a competitive bidding process to identify a reliable and cost-effective vendor.\ d. Use contingency reserves to offset potential risks associated with sole sourcing.\ **Correct Answer**: A The project involves a multi-year contract, and the vendor's initial performance is satisfactory. The sponsor suggests locking in the contract for an extended period. What should the project manager do?\ a. Review vendor performance trends and market conditions before committing to a longer term.\ b. Agree to the extended contract to secure favorable terms.\ c. Decline the extension and renegotiate annually for flexibility.\ d. Add penalties for underperformance to the extended contract.\ **Correct Answer**: A

Use Quizgecko on...
Browser
Browser