Module 10 - Chat GBT PDF
Document Details
Uploaded by FasterMistletoe
Tags
Summary
This document is a collection of project management practice questions covering topics such as earned value management, variance analysis, and change requests.
Full Transcript
A project has an Earned Value (EV) of \$500,000, Planned Value (PV) of \$600,000, and Actual Cost (AC) of \$450,000. What is the status of the project?\ a. The project is under budget and ahead of schedule.\ b. The project is under budget but behind schedule.\ c. The project is over budget and ahead...
A project has an Earned Value (EV) of \$500,000, Planned Value (PV) of \$600,000, and Actual Cost (AC) of \$450,000. What is the status of the project?\ a. The project is under budget and ahead of schedule.\ b. The project is under budget but behind schedule.\ c. The project is over budget and ahead of schedule.\ d. The project is over budget and behind schedule.\ Correct Answer: B A project with a BAC of \$1,200,000 has a Cost Performance Index (CPI) of 0.8. What is the Estimate at Completion (EAC) if current trends continue?\ a. \$1,000,000\ b. \$1,500,000\ c. \$960,000\ d. \$1,200,000\ Correct Answer: B (EAC = BAC / CPI = \$1,200,000 / 0.8 = \$1,500,000) If a project's SPI (Schedule Performance Index) is 0.95 and its CPI is 1.10, what does this indicate?\ a. The project is ahead of schedule and under budget.\ b. The project is behind schedule but under budget.\ c. The project is on schedule but over budget.\ d. The project is ahead of schedule but over budget.\ Correct Answer: B A project manager is reviewing variance results. The Schedule Variance (SV) is -\$15,000, and the Cost Variance (CV) is \$10,000. What does this mean?\ a. The project is over budget and behind schedule.\ b. The project is under budget and behind schedule.\ c. The project is over budget and ahead of schedule.\ d. The project is under budget and ahead of schedule.\ Correct Answer: B A project manager calculates the EAC using the formula EAC=AC+(BAC−EV)EAC = AC + (BAC - EV). When is this formula appropriate?\ a. When current variances are considered atypical.\ b. When current variances are expected to continue.\ c. When CPI and SPI are both trending positively.\ d. When CPI and SPI trends diverge.\ Correct Answer: A A progress report shows a CPI of 0.9 and an SPI of 1.2. How should the project manager interpret this?\ a. Focus on reducing costs as the project is over budget.\ b. Increase the pace of work as the project is behind schedule.\ c. Reallocate resources to balance cost and schedule performance.\ d. Maintain the current trajectory as both metrics are acceptable.\ Correct Answer: A A burndown chart shows the actual work line consistently above the ideal work line. What does this indicate?\ a. The project is ahead of schedule.\ b. The project is behind schedule.\ c. The project is over budget.\ d. The project is under budget.\ Correct Answer: B The team uses a burnup chart to track progress. The completed line is below the ideal trajectory, but the total scope line remains unchanged. What is the best course of action?\ a. Increase team velocity to match the ideal trajectory.\ b. Decrease scope to align with current progress.\ c. Reassess story points to ensure they are realistic.\ d. Communicate delays to stakeholders and adjust expectations.\ Correct Answer: D A project dashboard shows a negative cost variance but a positive schedule variance. What should the project manager prioritize?\ a. Improving cost efficiency.\ b. Maintaining the current schedule.\ c. Increasing the project's scope.\ d. Allocating more resources to critical tasks.\ Correct Answer: A A project manager includes variance analysis in monthly status reports. What is the primary benefit of this practice?\ a. It ensures stakeholder engagement in cost and schedule decisions.\ b. It provides real-time updates on project deliverables.\ c. It highlights trends and potential risks to project performance.\ d. It simplifies reporting by focusing on high-level metrics only.\ Correct Answer: C A key stakeholder submits a change request to add a new feature. The project manager identifies that it will delay the schedule by two weeks and increase costs by \$10,000. What should the project manager do first?\ a. Evaluate the change request's alignment with project objectives.\ b. Approve the change to maintain stakeholder satisfaction.\ c. Reject the change to avoid impacting the project baseline.\ d. Implement the change and inform stakeholders of the impact.\ Correct Answer: A The project team discovers scope creep due to undocumented changes. What is the best way to manage this?\ a. Implement a formal change control process to evaluate and document all changes.\ b. Revert to the original scope and reject all undocumented changes.\ c. Allocate contingency reserves to address the additional scope.\ d. Include the undocumented changes in future iterations.\ Correct Answer: A A project sponsor insists on implementing a regulatory change mid-project. This requires re-baselining the schedule and budget. What is the project manager's next step?\ a. Analyze the impact of the change and submit a change request.\ b. Approve the change immediately to ensure compliance.\ c. Request additional funding to accommodate the change.\ d. Escalate the issue to the Change Control Board (CCB).\ Correct Answer: A During a change control meeting, the Change Control Board (CCB) approves a request to defer a new feature. What should the project manager do next?\ a. Update the change log to reflect the deferred status.\ b. Communicate the decision to the team and stakeholders.\ c. Adjust the project schedule to exclude the feature.\ d. All of the above.\ Correct Answer: D The project manager identifies an increase in the number of change requests. What should they focus on to manage this trend?\ a. Improve the clarity of initial project requirements.\ b. Reject non-critical changes to reduce project scope.\ c. Allocate more resources to manage change requests.\ d. Increase stakeholder communication to avoid further changes.\ Correct Answer: A A stakeholder requests a detailed change impact analysis for a new feature. The project team estimates that preparing this analysis will take considerable time and delay other tasks. What should the project manager prioritize?\ a. Perform the analysis to provide stakeholders with informed data for decision-making.\ b. Reject the request to avoid further delays.\ c. Provide a high-level analysis to minimize time spent.\ d. Approve the feature without analysis to save time.\ Correct Answer: A A project team implements a new reporting tool, but stakeholders find the dashboards difficult to interpret. What should the project manager do to address this issue?\ a. Provide training to stakeholders on how to use and interpret the dashboards.\ b. Switch back to the old reporting method to avoid confusion.\ c. Customize dashboards for each stakeholder based on their specific needs.\ d. Reduce the level of detail in dashboards to simplify their use.\ Correct Answer: A A project manager identifies a discrepancy between the planned and actual progress on the burndown chart. The team explains that unanticipated issues slowed progress. What should the project manager do?\ a. Identify the root cause of delays and update the project plan accordingly.\ b. Increase the team's workload to accelerate progress.\ c. Ignore the discrepancy and monitor the next reporting cycle.\ d. Add additional contingency to account for future delays.\ Correct Answer: A The project's Earned Value Management (EVM) analysis reveals that the Cost Variance (CV) is -\$20,000 and the Schedule Variance (SV) is +\$15,000. How should the project manager proceed?\ a. Focus on cost control measures to bring the project back within budget.\ b. Increase team resources to maintain schedule performance.\ c. Reduce the project scope to offset the cost overrun.\ d. Use contingency reserves to balance cost performance.\ Correct Answer: A A project's SPI (Schedule Performance Index) is 0.85, and CPI (Cost Performance Index) is 1.05. What does this indicate, and what action should the project manager take?\ a. The project is ahead of budget but behind schedule; prioritize schedule acceleration.\ b. The project is on track; no action is needed.\ c. The project is over budget; reduce costs to improve performance.\ d. The project is delayed; increase resources to accelerate progress.\ Correct Answer: A The sponsor requests a weekly status report, but team members find preparing it time-consuming and prefer focusing on deliverables. How should the project manager balance these needs?\ a. Automate report generation using project management software.\ b. Reduce the frequency of reports to biweekly updates.\ c. Assign a dedicated team member to handle reporting tasks.\ d. Request the sponsor to accept high-level verbal updates instead.\ Correct Answer: A A progress report indicates that the actual progress is significantly below planned progress. However, the team argues that quality control tasks are taking longer than expected. How should the project manager respond?\ a. Reassess quality control processes to ensure efficiency without compromising standards.\ b. Reduce time allocated to quality control tasks to meet the planned schedule.\ c. Remove non-critical tasks from the schedule to compensate for the delays.\ d. Ignore the variance and continue monitoring progress.\ Correct Answer: A A stakeholder has requested metrics on the project's environmental sustainability, which was not part of the original reporting plan. What should the project manager do?\ a. Evaluate the feasibility of gathering the data and update the reporting plan if necessary.\ b. Decline the request to stay aligned with the original scope.\ c. Provide high-level estimates rather than actual metrics.\ d. Escalate the request to the sponsor for approval.\ Correct Answer: A The project manager identifies that reporting metrics are inconsistent across departments due to varying calculation methods. What is the best way to address this?\ a. Standardize the calculation methods and provide training to all departments.\ b. Use department-specific metrics but align them to a common reporting format.\ c. Focus on high-level metrics to avoid inconsistencies.\ d. Assign a team member to manually reconcile the differences.\ Correct Answer: A The project sponsor requests that all reports include risk metrics in addition to performance metrics. The team argues that this will slow reporting processes. What is the best approach?\ a. Automate risk reporting to integrate it into the existing process.\ b. Focus on performance metrics and exclude risk metrics for now.\ c. Delay reporting deadlines to accommodate the new requirement.\ d. Provide high-level risk summaries instead of detailed metrics.\ Correct Answer: A A team member reports a significant variance between planned and actual resource utilization. The project manager suspects inefficient allocation. What should they prioritize?\ a. Conduct a resource utilization audit and reallocate resources based on findings.\ b. Increase the team size to address resource shortages.\ c. Focus on completing high-priority tasks to offset the inefficiency.\ d. Reduce the project scope to align with current resource levels.\ Correct Answer: A The team is using KPIs (Key Performance Indicators) to track progress, but one of the KPIs consistently shows poor performance. How should the project manager handle this?\ a. Investigate the root cause of poor performance and implement corrective actions.\ b. Replace the KPI with one that better reflects project progress.\ c. Ignore the KPI and focus on other performance metrics.\ d. Adjust the baseline to align with current performance levels.\ Correct Answer: A A project report shows that planned milestones are being achieved, but costs are significantly higher than expected. What is the best course of action?\ a. Analyze cost drivers and identify areas for efficiency improvements.\ b. Increase contingency reserves to cover additional costs.\ c. Reallocate resources to reduce spending.\ d. Focus on maintaining the schedule and address costs later.\ Correct Answer: A A stakeholder requests that reports include predictive analytics to forecast project outcomes. The team lacks experience in this area. What should the project manager do?\ a. Train the team on predictive analytics and integrate it into reports.\ b. Decline the request due to the team's lack of expertise.\ c. Use historical data to provide basic projections instead.\ d. Outsource the analytics to a third party.\ Correct Answer: A A project manager finds that reports are often delayed because data collection is not centralized. What is the best way to address this issue?\ a. Implement a centralized reporting system to streamline data collection.\ b. Assign specific team members to handle reporting tasks manually.\ c. Reduce the frequency of reports to allow more time for data collection.\ d. Focus on gathering high-level data to simplify the process.\ Correct Answer: A A stakeholder complains that the reports are overly technical and difficult to understand. How should the project manager address this?\ a. Simplify the reports by including executive summaries with non-technical language.\ b. Provide additional training to stakeholders on interpreting technical data.\ c. Continue using the current report format and offer one-on-one explanations.\ d. Focus on delivering detailed reports only to the project team.\ **Correct Answer**: A A variance analysis report shows consistent underperformance in a specific task area. The task leads attribute this to unforeseen technical challenges. What should the project manager do?\ a. Collaborate with task leads to develop solutions and allocate additional resources if necessary.\ b. Adjust the project baseline to accommodate the challenges.\ c. Escalate the issue to the sponsor and request additional funding.\ d. Ignore the variance and focus on other tasks to balance performance.\ **Correct Answer**: A A sponsor requests a new dashboard to track project progress, but the team is already overloaded with reporting tasks. What is the best approach?\ a. Automate the dashboard updates to minimize the team's workload.\ b. Delay the implementation of the dashboard until the team's workload decreases.\ c. Refuse the request and focus on existing reporting methods.\ d. Assign an external resource to create and manage the dashboard.\ **Correct Answer**: A The team uses a RAG (Red-Amber-Green) status report, and a stakeholder questions why one task is marked as \"Amber.\" What should the project manager prioritize?\ a. Provide a detailed explanation of the risks or issues contributing to the \"Amber\" status.\ b. Change the status to \"Green\" if the task is expected to improve soon.\ c. Remove the RAG status from reports to avoid stakeholder concerns.\ d. Focus on addressing other areas of the project and revisit the status later.\ **Correct Answer**: A The project team's progress reports show a steady decline in velocity. Stakeholders express concern about deliverable timelines. What is the best way to address this?\ a. Analyze the root cause of the velocity decline and implement corrective actions.\ b. Reallocate resources to accelerate progress.\ c. Reduce the project scope to align with the current velocity.\ d. Increase the reporting frequency to monitor velocity more closely.\ **Correct Answer**: A The project sponsor requests that the next report include benchmarks comparing the project's performance to similar past projects. The team has no historical data available. What should the project manager do?\ a. Collect and analyze data from external sources or industry standards for benchmarking.\ b. Decline the request due to the lack of historical data.\ c. Provide performance metrics without comparisons to avoid delays.\ d. Use estimates based on team input to create benchmarks.\ **Correct Answer**: A A mid-project report indicates that key milestones have been delayed, but the overall project timeline is unchanged. Stakeholders demand clarity. What should the project manager do?\ a. Explain how the delays were absorbed into the project timeline and update the schedule as needed.\ b. Provide a high-level summary without addressing individual milestone delays.\ c. Focus on future milestones to assure stakeholders that the timeline is achievable.\ d. Escalate the issue to the Change Control Board for resolution.\ **Correct Answer**: A A stakeholder reports that they are not receiving reports promptly due to time zone differences. How should the project manager resolve this?\ a. Use automated scheduling tools to ensure reports are delivered at the stakeholder\'s preferred time.\ b. Assign a team member to manually send reports to stakeholders in different time zones.\ c. Standardize the reporting time and ask stakeholders to adjust their schedules.\ d. Reduce the frequency of reports to avoid delivery delays.\ **Correct Answer**: A A project report shows that CPI (Cost Performance Index) and SPI (Schedule Performance Index) are both below 1.0. The team suggests re-baselining the project. What is the project manager's next step?\ a. Evaluate the root causes of poor performance and determine if re-baselining is justified.\ b. Approve the re-baseline request immediately to reset expectations.\ c. Decline the request and focus on improving performance without re-baselining.\ d. Escalate the issue to the project sponsor for a decision.\ **Correct Answer**: A The project team is using visual dashboards to report metrics, but stakeholders request raw data instead. What is the best way to address this?\ a. Provide raw data as a supplement to the visual dashboards.\ b. Eliminate dashboards and provide only raw data going forward.\ c. Focus on visual dashboards to simplify reporting.\ d. Assign a team member to manually prepare raw data reports.\ **Correct Answer**: A A team member reports inconsistent data between different reports. The project manager suspects issues with data sources. What should they do?\ a. Audit data sources to ensure consistency and standardize reporting processes.\ b. Focus on high-priority reports and resolve inconsistencies later.\ c. Use the most recent data and ignore older discrepancies.\ d. Escalate the issue to the sponsor for additional resources.\ **Correct Answer**: A The sponsor requests that reports include predictive cost metrics. However, the team is unfamiliar with cost forecasting techniques. What should the project manager do?\ a. Train the team on cost forecasting methods and incorporate them into reports.\ b. Decline the request and focus on existing cost metrics.\ c. Use contingency funds to outsource cost forecasting to an external expert.\ d. Provide basic cost estimates until the team is trained.\ **Correct Answer**: A A report highlights that planned and actual progress are diverging. The sponsor requests recommendations for corrective actions. What is the best approach?\ a. Analyze the root causes of the divergence and propose targeted corrective measures.\ b. Re-baseline the project to align planned and actual progress.\ c. Focus on future progress and avoid revisiting past performance.\ d. Delay action until the next reporting cycle to gather more data.\ **Correct Answer**: A The project team reports a sudden drop in productivity after implementing a new reporting system. What should the project manager prioritize?\ a. Investigate whether the new reporting system is causing inefficiencies and resolve them.\ b. Remove the reporting system to restore productivity.\ c. Focus on delivering project outcomes and address reporting issues later.\ d. Assign additional resources to manage reporting tasks.\ **Correct Answer**: A A status report shows that risk mitigation efforts have been successful, but the sponsor suggests reducing the risk management budget. How should the project manager respond?\ a. Explain that continued investment in risk management is necessary to sustain success.\ b. Agree to reduce the budget and focus on other project areas.\ c. Reallocate the risk management budget to contingency reserves.\ d. Use the budget only for high-priority risks going forward.\ **Correct Answer**: A Stakeholders request that variance reports include visual representations of data. What is the best way to implement this?\ a. Use graphs and charts to visually present variances alongside numerical data.\ b. Provide detailed numerical data and let stakeholders interpret it.\ c. Focus on verbal updates to supplement variance reports.\ d. Use text-based explanations to describe variances instead of visuals.\ **Correct Answer**: A A stakeholder requests that reports highlight lessons learned during the project. The team argues that this should be included only in the final report. What should the project manager do?\ a. Include lessons learned in ongoing reports to ensure continuous improvement.\ b. Decline the request and focus on delivering the final report.\ c. Provide a separate lessons-learned document for stakeholders.\ d. Add lessons learned only for completed phases of the project.\ **Correct Answer**: A A project report shows an unexplained increase in costs. The sponsor demands an explanation, but the data is incomplete. What should the project manager prioritize?\ a. Investigate cost discrepancies and provide an interim report to the sponsor.\ b. Delay reporting until complete data is available.\ c. Use contingency reserves to address cost increases and avoid sponsor concerns.\ d. Focus on completing the next phase and address costs later.\ **Correct Answer**: A The team implements an Earned Value Management (EVM) system mid-project, but stakeholders are unfamiliar with EVM metrics. How should the project manager address this?\ a. Provide training to stakeholders on interpreting EVM metrics.\ b. Focus on traditional reporting metrics to avoid confusion.\ c. Use EVM internally and exclude it from stakeholder reports.\ d. Gradually introduce EVM metrics alongside familiar ones.\ **Correct Answer**: A A project manager uses trend analysis to track performance. A negative trend in schedule performance is identified, but the team believes it is temporary. What is the best way to proceed?\ a. Monitor the trend closely and prepare corrective actions if it persists.\ b. Ignore the trend and focus on future progress.\ c. Re-baseline the schedule to accommodate temporary delays.\ d. Increase team resources to offset the negative trend.\ **Correct Answer**: A