API-1169 Pipeline Construction Inspector Exam PDF
Document Details

Uploaded by RoomierRutherfordium
Lone Star College System
Tags
Summary
This document contains questions and answers for the API-1169 Pipeline Construction Inspector Exam. The practice questions cover various topics including regulations, safety, construction phases, and terminology related to pipeline inspection. The questions are in a multiple-choice format and include a mix of definitions, regulations, and practical applications.
Full Transcript
API API-1169 Pipeline Construction Inspector Exam Questions and Answers (PDF) For More Information - Visit: https://www.certkillers.net Visit us athttps://www.certschief.com/api-1169/ Total Questions: 459 Latest V...
API API-1169 Pipeline Construction Inspector Exam Questions and Answers (PDF) For More Information - Visit: https://www.certkillers.net Visit us athttps://www.certschief.com/api-1169/ Total Questions: 459 Latest Version: 7.0 Question: 1 FERC A. Interstate Commerce Commission B. Department Of Energy C. Federal Energy Regulatory Commission D. Osha Answer: C Question: 2 NPDES A. National Pollution Discharge Elimination System B. Clean Water Act C. Storm Water Pollution Plan D. Resource Conservation and Recovery Act Answer: A Question: 3 Maintain a safe distance of at least ___ from edge of excavation or use a retaining device sufficient to stop migration of material or equipment into the excavation. A. 10' B. 6, 18, 2, 3 C. 20' D. 2' Answer: D Question: 4 Visit us athttps://www.certschief.com/api-1169/ 49 CFR Part 192 A. Standard Gas Transmission and Distribution Piping Systems B. Regulation Transportation of Natural and Other Gas by Pipeline C. Class 1 liquids having a flash point below 100 deg F. Gasoline. D. Regulation Transportation of Hazardous Liquids by Pipeline Answer: A Question: 5 Blue A. Blackwater B. Potable Water C. Reclaimed Water D. Safe Water Answer: B Question: 6 Plan devised between the Owner and crossing party to specify the details and provisions under which the crossing construction shall occur A. Storm water pollution plan B. Potable water C. Crossing plan D. Safety Answer: C Question: 7 Phases of Pipeline Construction A. Regulates how wastes should be managed to avoid potential threats to human health and environment B. 1. Survey 2. Clearing and grading 3. Stockpiling and stringing 4. Field bending 5. Ditching and excavation 6. Welding 7. Coating 8. Lowering In. 9. Backfilling 10. Cathodic Protection 11. Hydrostatic testing 12. Clean up and restoration Visit us athttps://www.certschief.com/api-1169/ C. To remedy threats to human health and the environment from unexpected releases and historical mistakes in hazardous waste management D. Noise level exceeds 85 dba over an 8 hour period. INGAA states during pressure testing to keep under 80 dba's Answer: B Question: 8 Rejectable damage A. protractor, measuring tape, center finder, straight edge. B. as close to perpendicular as possible C. gouges, buckles, wrinkles, ripples or ovality's D. communication, alarm or signal lines Answer: C Question: 9 BMP A. Leak Response Plan B. Ada Standards For Recapture Devices C. Epa Air Quality Standards D. Best Management Practices Answer: D Question: 10 CERCLA purpose A. Noise level exceeds 85 dba over an 8 hour period. INGAA states during pressure testing to keep under 80 dba's B. To remedy threats to human health and the environment from unexpected releases and historical mistakes in hazardous waste management C. Regulation Transportation of Natural and Other Gas by Pipeline D. Area within 24" of facilities or the distance mandated by state law, whichever is greater. NOTE: CGA & INGAA says 18". Visit us athttps://www.certschief.com/api-1169/ Answer: B Question: 11 49 CFR Part 195 A. Regulates how wastes should be managed to avoid potential threats to human health and environment B. Code of Federal Regulations C. Pipeline Hazardous Materials and Safety Administration D. Regulation Transportation of Hazardous Liquids by Pipeline Answer: D Question: 12 OSHA A. American Society for Testing and Materials B. Occupational Safety and Hazard Administration C. Energy Star D. Proposed Excavation Answer: B Question: 13 EPA A. Environmental Protection Act B. Wildlife And Countryside Act C. Clean Air Act D. Air Quality Act Answer: A Question: 14 INGAA states that crossing company shall not permit soil disturbance within ____ of the centerline of existing pipeline facilities without an owners rep being present. Visit us athttps://www.certschief.com/api-1169/ A. 15' B. 25' C. 20' D. 10' Answer: B Question: 15 Purple A. Blackwater B. Reclaimed Water C. Potable Water D. Process Water Answer: B Question: 16 MTF A. Material receiving reports B. Material receiving reports C. Root cause analysis D. Material transfer form Answer: D Question: 17 Flammable Liquids A. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement B. Minimum specified distance from welds and ends. Bending increments are distributed along length of bend. C. gouges, buckles, wrinkles, ripples or ovality's D. Class 1 liquids having a flash point below 100 deg F. Gasoline. Answer: D Visit us athttps://www.certschief.com/api-1169/ Question: 18 Hearing protection required in areas ____________ A. Rock=90 deg. or vertical 2. Type A=3/4:1 or 53 deg. 3. Type B=1.1 or 45 de. 4. Type C= 1 1/2:1 or 34 deg. B. Area where the edge of the disturbance is within 25' of centerline of existing facilities C. Noise level exceeds 85 dba over an 8 hour period. INGAA states during pressure testing to keep under 80 dba's D. To remedy threats to human health and the environment from unexpected releases and historical mistakes in hazardous waste management Answer: C Question: 19 RCA A. Root Cause Analysis B. Resolved C. Process Management D. Material Transfer Form Answer: A Question: 20 Top soil should be removed ___ to ___ inches and seperated ___ to __ feet. A. 18" B. 4' 19.5% - 23.5% C. 6, 18, 2, 3 D. 6, 18, 10, 3 Answer: C Question: 21 Encroachment Area Visit us athttps://www.certschief.com/api-1169/ A. Minimum specified distance from welds and ends. Bending increments are distributed along length of bend. B. Area where the edge of the disturbance is within 25' of centerline of existing facilities C. Area within 24" of facilities or the distance mandated by state law, whichever is greater. NOTE: CGA & INGAA says 18". D. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement Answer: D Question: 22 4 instruments used to inspect field bends A. Crossing plan B. Gouges, buckles, wrinkles, ripples or ovality's C. Protractor, Measuring tape, Center Finder, Straight edge. D. Grading Answer: C Question: 23 CFR A. Research Agenda B. Code of Federal Regulations C. United States Code D. Code Enforcement and Sprinklers Answer: B Question: 24 NORM A. Outer space B. Storm water pollution plan C. Naturally occurring radioactive materials D. Earth crust Visit us athttps://www.certschief.com/api-1169/ Answer: C Question: 25 MUTCD A. Manual of Uniform Traffic Devices B. Material transfer form C. Spill Prevention Control and Containment D. Maximum operating pressure Answer: A Question: 26 Excavation Tolerance Zone A. Protractor, Measuring tape, Center Finder, Straight edge. B. Area within 24" of facilities or the distance mandated by state law, whichever is greater. NOTE: CGA & INGAA says 18". C. 1. Rock=90 deg. or vertical 2. Type A=3/4:1 or 53 deg. 3. Type B=1.1 or 45 de. 4. Type C= 1 1/2:1 or 34 deg. D. Minimum specified distance from welds and ends. Bending increments are distributed along length of bend. Answer: B Question: 27 INGAA A. Interstate Natural Gas Association of America B. Regulation Transportation of Hazardous Liquids by Pipeline C. Communication, Alarm or Signal Lines D. Pipeline Hazardous Materials and Safety Administration Answer: A Question: 28 Visit us athttps://www.certschief.com/api-1169/ MRR A. Maximum operating pressure B. Material transfer form C. Temporary survey markings D. Material receiving reports Answer: D Question: 29 Combustible Liquids A. Regulation Transportation of Natural and Other Gas by Pipeline B. gouges, buckles, wrinkles, ripples or ovality's C. Regulates how wastes should be managed to avoid potential threats to human health and environment D. Class 2 liquids having a flash point above 100 deg F. Diesel, jet fuel motor oil Answer: D Question: 30 HDD A. Transporting to location B. Hydrostatic testing C. Root cause analysis D. Horizontal directional drilling Answer: D Question: 31 PHMSA A. Occupational Safety and Hazard Administration B. Pipeline Hazardous Materials and Safety Administration C. Comprehensive Environmental Response, Compensation and Liability Act also known as Superfund D. Interstate Natural Gas Association of America Visit us athttps://www.certschief.com/api-1169/ Answer: B Question: 32 Yellow A. Gas, Oil, Steam, Petroleum or Gaseous Materials B. gouges, buckles, wrinkles, ripples or ovality's C. Electric Power Lines, Cables, Conduit and Lighting Cables D. Sewers and Drain Lines Answer: A Question: 33 ASTM A. International building code B. Standard gas transmission and distribution piping systems C. Uniform commercial code D. American society for testing materials Answer: D Question: 34 Removal of stumps and roots A. 10' B. Gouges, buckles, wrinkles, ripples or ovality's C. Grubbing (Not allowed in wet lands) D. 18" Answer: C Question: 35 ACI A. American Concrete Institute Visit us athttps://www.certschief.com/api-1169/ B. Concrete Reinforcing Steel Institute C. Horizontal Directional Drilling D. Common Ground Alliance Answer: A Question: 36 Crossing angle A. Gouges, buckles, wrinkles, ripples or ovality's B. As close to perpendicular as possible C. Grubbing (not allowed in wet lands) D. Grading Answer: B Question: 37 Trenches _____ depth or Confined Spaces must be monitored before entry. Safe oxygen levels are ________ A. 4' 19.5% - 23.5% B. 0' 19.5% - 23.5% C. standard gas transmission and distribution piping systems D. gas, oil, steam, petroleum or gaseous materials Answer: A Question: 38 When an excavation is within _____ of a pipeline facility an OQ qualified representative shall be continuously present during all excavation and backfilling activities to ensure that criteria is being met. A. 15' B. 25' C. 20' D. 10' Answer: D Visit us athttps://www.certschief.com/api-1169/ Question: 39 CGA A. Resource Conservation And Recovery Act B. Common Ground Alliance C. Maximum operating pressure D. Material transfer form Answer: B Question: 40 29 CFR Part 1926 A. Federal Water Pollution and Control Act B. Pipeline Hazardous Materials and Safety Administration C. Regulation Safety and Health Regulations for Construction D. Regulation Transportation of Natural and Other Gas by Pipeline Answer: C Question: 41 4 soil types and sloping A. 1. Rock=90 deg. or vertical 2. Type A=3/4:1 or 53 deg. 3. Type B=1.1 or 45 de. 4. Type C= 1 1/2:1 or 34 deg. B. Minimum specified distance from welds and ends. Bending increments are distributed along length of bend. C. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement D. Area within 24" of facilities or the distance mandated by state law, whichever is greater. NOTE: CGA & INGAA says 18". Answer: A Question: 42 SWP3 Visit us athttps://www.certschief.com/api-1169/ A. Federal Water Pollution And Control Act B. Reclaimed Water C. Storm Water Pollution Plan D. Strategic Plan Answer: C Question: 43 Active Excavation Area A. Area where the edge of the disturbance is within 25' of centerline of existing facilities B. Area within 24" of facilities or the distance mandated by state law, whichever is greater. NOTE: CGA & INGAA says 18". C. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement D. Regulates how wastes should be managed to avoid potential threats to human health and environment Answer: A Question: 44 FWPCA A. Storm Water Pollution Plan B. Resource Conservation and Recovery Act C. Spill Prevention Control and Containment D. Federal Water Pollution and Control Act Answer: D Question: 45 Green A. Sewers and drain lines B. Potable water C. Proposed excavation D. Communication, alarm or signal lines Answer: A Visit us athttps://www.certschief.com/api-1169/ Question: 46 29 CFR Part 1910 A. Naturally occurring radioactive materials B. Spill Prevention Control and Containment C. Regulation Occupational Safety and Health Standards D. Class 1 liquids having a flash point below 100 deg F. Gasoline. Answer: C Question: 47 Trench Boxes must extend ____above outside soil level A. 25' B. 24" C. 18" D. 12" Answer: C Question: 48 In 29 CFR 1910 subpart ___ covers excavations A. 100' B. P C. 4 hrs @ 125% Max Operating Pressure for above ground pipe. 8 hrs @ 110% MOP. D. 25' Answer: B Question: 49 RCRA A. Toxic Substances Control Act B. Resource Conservation and Recovery Act Visit us athttps://www.certschief.com/api-1169/ C. Comprehensive Environmental Response, Compensation, and Liability Act D. Clean Water Act Answer: B Question: 50 Red A. Electrical B. Grading C. Thermal D. Mechanical Answer: A Question: 51 Valve locations per CFR 195 A. Area within 24" of facilities or the distance mandated by state law, whichever is greater. NOTE: CGA & INGAA says 18". B. To remedy threats to human health and the environment from unexpected releases and historical mistakes in hazardous waste management C. Each side of a water crossing that is more than 100' wide from high water mark to high water mark. Unless the Administrator finds they are not justified. D. 1. Survey 2. Clearing and grading 3. Stockpiling and stringing 4. Field bending 5. Ditching and excavation 6. Welding 7. Coating 8. Lowering In. 9. Backfilling 10. Cathodic Protection 11. Hydrostatic testing 12. Clean up and restoration Answer: D Question: 52 Orange A. Occupational Safety and Hazard Administration B. Potable Water C. Sewers and Drain Lines D. Communication, Alarm or Signal Lines Visit us athttps://www.certschief.com/api-1169/ Answer: D Question: 53 SPCC A. Federal Water Pollution and Control Act B. Spill Prevention Control and Containment C. Federal Energy Regulatory Commission D. Pipeline Hazardous Materials and Safety Administration Answer: B Question: 54 When an excavation is within ____ of a pipeline facility an OQ qualifies representative shall be continuously present during all backfilling and A. 25' B. 10' C. 20' D. 15' Answer: B Question: 55 If pipe has a longitudinal weld the bend must be located in the ___________ A. Neutral axis B. Negative deformation C. Structural frame D. Horizontal directional drilling Answer: A Question: 56 White Visit us athttps://www.certschief.com/api-1169/ A. Water B. Potable Water C. Proposed Excavation D. Crossing Plan Answer: C Question: 57 Leveling the pipeline ROW so construction can proceed smoothly A. Testing B. Pulverizing C. Easement D. Grading Answer: D Question: 58 Hydro test parameters per 49 CFR 195 A. 4 hrs @ 125% Max Operating Pressure for above ground pipe. 8 hrs @ 110% MOP. B. Protractor, Measuring tape, Center Finder, Straight edge. C. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement D. Noise level exceeds 85 dba over an 8 hour period. INGAA states during pressure testing to keep under 80 dba's Answer: A Question: 59 ASME B31.8 A. Standard Gas Transmission and Distribution Piping Systems B. Federal Water Pollution and Control Act C. Regulation Transportation of Hazardous Liquids by Pipeline D. Standard Pipeline Transportation Systems for Liquids and Slurries Answer: A Visit us athttps://www.certschief.com/api-1169/ Question: 60 Trenches _____ deep or greater require a protective system which can be sloping, benching, trench boxes A. 4' 19.5% - 23.5% B. 10' C. 5' D. 100' Answer: C Question: 61 Remain _______ from any pipe being hydro-tested A. 500' B. 20' C. 25' D. 100' Answer: D Question: 62 RCRA Purpose A. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement B. Regulation Transportation of Natural and Other Gas by Pipeline C. Regulates how wastes should be managed to avoid potential threats to human health and environment D. Regulation Transportation of Hazardous Liquids by Pipeline Answer: C Question: 63 Trenches _____ deep or greater require a protective system designed by a PE A. 100' Visit us athttps://www.certschief.com/api-1169/ B. 20' C. 10' D. 25' Answer: B Question: 64 SMYS A. Material transfer form B. Standard tensile and strength yield C. Standard minimum yield stress level D. Specified minimum yield strength Answer: D Question: 65 ROW is established thru a written document known as the A. Sewers And Drain Lines B. Encroachment C. Easement D. Variance Answer: C Question: 66 Inspect bends for A. Standard Pipeline Transportation Systems for Liquids and Slurries B. Area within 24" of facilities or the distance mandated by state law, whichever is greater. NOTE: CGA & INGAA says 18". C. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement D. Minimum specified distance from welds and ends. Bending increments are distributed along length of bend. Answer: D Visit us athttps://www.certschief.com/api-1169/ Question: 67 CERCLA A. To remedy threats to human health and the environment from unexpected releases and historical mistakes in hazardous waste management B. Area where the ground disturbance occurs within 50' of centerline of ROW, facility or easement C. Comprehensive Environmental Response, Compensation and Liability Act also known as Superfund D. Area where the edge of the disturbance is within 25' of centerline of existing facilities Answer: C Question: 68 MOP A. Maximum operating pressure B. Common ground alliance C. Design pressure D. Specified minimum yield strength Answer: A Question: 69 Call ____ Before surveying A. 411 B. 311 C. 811 D. 806 Answer: C Question: 70 Pink A. Temporary Survey Markings B. Potable Water Visit us athttps://www.certschief.com/api-1169/ C. Reinforced Concrete D. Proposed Excavation Answer: A Question: 71 ASME B31.4 A. Standard Gas Transmission and Distribution Piping Systems B. Class 1 liquids having a flash point below 100 deg F. Gasoline. C. Standard Pipeline Transportation Systems for Liquids and Slurries D. Area where the edge of the disturbance is within 25' of centerline of existing facilities Answer: C Question: 72 Station numbers for 100, 10,000 and 5000 A. 25' B. 1+00, 100+00, 50+00 C. 4' 19.5% - 23.5% D. 6, 18, 2, 3 Answer: B Question: 73 In the event that an inspector notices a sheen on a navigable river, the inspector should immediately? A. The owner B. Notify the owner (API 1169, 6.7) C. Notify the owner (api 1174, 6.7) D. Notify the owner (api 1169, 6.3) Answer: B Question: 74 Visit us athttps://www.certschief.com/api-1169/ Prior to hydrostatic testing the owner/operator shall notify? A. Residence within proximity of the facility being tested, state and local enforcement agencies. (CS-S-9 4.5) B. Management with regard to quality, can include establishing quality policies in quality objectives and processes to achieve these quality objectives through quality planning quality assurance quality control and quality improvement (ISO 9000 3.3.4) C. Have the longitude a weld as near as practical to the neutral axis of the band (49 CFR 192.313) D. Within 2 feet of the existing facilities or the distance mandated by state law which ever is greater (INGAA CROSSING guide 11 K) Answer: A Question: 75 Work Permits for Isolation of hazardous energy sources would be found under what OSHA standard? A. A spike test, strength test and/or a leak test (API 1110, 4.1.3 a) B. OSHA 1910.147 (29 CFR 1910) occupational safety and health standard C. Within 24 hours of each 0.50 inch of rainfall (FERC Upland 11.B.13) D. A right of way (INGaA Crossing Guideline 11 M) Answer: B Question: 76 Define objective evidence in terms related to data, information in document. A. Confirmation, through the provisions of objective evidence, that the requirements for a specific intended use or application have been fulfilled. (The objective evidence needed for a validation is the result of a test or other form of determination such as performing alternative calculations or reviewing documents) (ISO 9000 3.8.13) B. Data supporting the existence of verity of something (Objective evidence can be obtained through observation measurement test or by other means) (ISO 9000 3.8.3) C. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) Visit us athttps://www.certschief.com/api-1169/ D. Liquids having a flashpoint at or above 100°F are known as class 11 liquids the most common or diesel fuel, class III liquids include jet fuel and motor oil Answer: C Question: 77 The owner Well cause it's facilities within the encroachment area to be marked using appropriate line locating message that will ensure the accurate placement of the markers. Markers will be placed at a maximum spacing not exceeding? A. 30' B. 20' C. 50' D. 100' Answer: C Question: 78 Key areas to verify certification and qualification include? a) office personal b) heavy equipment mechanics c) welders, blasting personal d) management A. c) welders, blasting personal (API 1169 7.2.3) B. Spike test (API 1110 4.1.7.2) C. Manufacturing acceptance criteria (API Spec Q1 3.1.15 D. A right of way (INGaA Crossing Guideline 11 M) Answer: A Question: 79 Define Contractor; Visit us athttps://www.certschief.com/api-1169/ A. terrain features; landowner issues; road, railroad, or waterway crossing; environmental features; cultural features and protected resources (i.e. drinking water and proximity to occupied facilities) B. An entity that includes the primary organization and any subcontractors engaged in pipeline construction covered by ARPI 1169 3.1.1 C. Process of establishing, documenting, implementing, maintaining and continually improving a quality management system. (ISO 9000 3.4.3) D. Liquids having a flashpoint at or above 100°F are known as class 11 liquids the most common or diesel fuel, class III liquids include jet fuel and motor oil Answer: B Question: 80 Define quality management system realization in terms to process A. d) welding she will not be done we're floors are combustible (ANDI Z49.1 6.1) B. Process of establishing, documenting, implementing, maintaining and continually improving a quality management system. (ISO 9000 3.4.3) C. A part of quality management Focused on the ability to fulfil quality requirements. The quality requirements can be related to any aspect such as effectiveness efficiency or traceability. D. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) Answer: B Question: 81 For natural gas pipe lines, each feel band in steel pipe must? A. Latitude/longitude coordinates (CGA Best Practice 6.2) B. Have the longitude a weld as near as practical to the neutral axis of the band (49 CFR 192.313) C. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) D. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) Answer: B Visit us athttps://www.certschief.com/api-1169/ Question: 82 Work Permits for Confined Space Entry would be found under which OSHA standard? A. OSHA 1910.119 (k) (29 CFR 1910) occupational safety and health standard B. OSHA 1910.146 (29 CFR 1910) occupational safety and health standard C. Within a set of written process safety information controls (29 CFR 1910.119, general knowledge) D. A spike test, strength test and/or a leak test (API 1110, 4.1.3 a) Answer: B Question: 83 Examples of information discussed and exchange between Designated contacts include? A. Management with regard to quality, can include establishing quality policies in quality objectives and processes to achieve these quality objectives through quality planning quality assurance quality control and quality improvement (ISO 9000 3.3.4) B. Document stating requirements (example quality manual, quality plan, technical drawing, procedure document, work instruction.) (ISO 9000 3.8.7) C. Is the entity that intends to install, operate, maintain a new pipeline that crosses existing pipeline facilities. The Crossing company may designate a third-party or parties to perform the task necessary to accomplish a Crossing but remains responsible for the work performed by such third parties. D. Placement of the ROW, Location of the existing of proposed pipelines within the ROW, the types of easement (exclusive, or open and undefined), construction methods and practices, unique landscape, terrain, or environmental situations, separation distances, restrictions on type in location of heavy equipment crossings, any potential pipeline integrity concerns, responsibility for cathodic protection after installation, the ground disturbance timing. Answer: D Question: 84 Definition for Crossing agreement Visit us athttps://www.certschief.com/api-1169/ A. Is the agreement entered into between the owner of the existing facility and the crossing company installing the new facility to specify the rights and obligations of the parties during the crossing Construciton. B. The quality policy (ISO 9000 3.5.8) C. Federal water pollution control act, a.k.a. clean water act D. Person or group of people who directs and controls an organization at the highest level (ISO 9000 3.1.1) Answer: A Question: 85 Define Owners/Operators Representative A. Is the singular point of contact identified within the company of the crossing company and the owner who has the responsibility to communicate about the safely managed crossing. There will be a cross and Company designated contact and an owner designated contact. B. An individual qualified to monitor, assess, evaluate, verify, discuss, decide, resolve, report, and document pipeline construction activities to ensure the requirements of the design, drawings, specifications, regulations, and Industry practises are being met safely, effectively, and in an environmentally sound manner. C. Inspectors are expected to function at all times as a representative of the pipeline company owning and or managing the project. In most cases the inspector works for or represents a pipeline company, with strict procedures and war contract provisions are in place that spell out the expectations and obligations of the inspectors performance. D. Is the entity that intends to install, operate, maintain a new pipeline that crosses existing pipeline facilities. The Crossing company may designate a third-party or parties to perform the task necessary to accomplish a Crossing but remains responsible for the work performed by such third parties. Answer: C Question: 86 The crossing company will not excavate unless there's visual confirmation of the existing pipelines? A. Encroachment Area B. Creation C. Infection D. Location Answer: D Visit us athttps://www.certschief.com/api-1169/ Question: 87 Define SPCC A. Operator qualification B. Spill prevention, control, and containment C. National pollutant discharge elimination systems D. Resource conservative in recovery act Answer: B Question: 88 Define quality planning in terms related to activity. A. Action to illuminate the cause of a non-conformity in to prevent recurrence. (correct of action is taken to prevent recurrence where as preventative action is taken to prevent occurrence) (ISO 9000 3.12.2) B. Data supporting the existence of verity of something (Objective evidence can be obtained through observation measurement test or by other means) (ISO 9000 3.8.3) C. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives (ISO 9000 3.3.5) D. Document stating requirements (example quality manual, quality plan, technical drawing, procedure document, work instruction.) (ISO 9000 3.8.7) Answer: C Question: 89 Define management system in terms related to system. A. The contractor (API 1169 5.2.3) B. Management system set of interrelated or interacting elements of an organization to establish policies and objectives and processes to achieve those objectives. (ISO 9000 3.5.4) C. The company ( API 1104 7.5) Visit us athttps://www.certschief.com/api-1169/ D. Is the agreement entered into between the owner of the existing facility and the crossing company installing the new facility to specify the rights and obligations of the parties during the crossing Construciton. Answer: B Question: 90 Define Quality Assurance, and who is expected to be the principal means of assuring work and material quality during field construction? A. The company ( API 1104 7.5) B. Quality assurance includes sales activities focused on providing confidence that quality requirements are consistently fulfilled. Inspectors are expected to be the principal means. C. The contractor (API 1169 5.2.3) D. The crossing company Answer: B Question: 91 What type of test is used to verify the structural integrity of a pipeline with time dependent anomalies? A. Spike test (API 1110 4.1.7.2) B. Acceptance criteria (api spec q1 3.1.1) C. Rework (api 1104 3.1.25) D. Strength, spike, and leak (api 1110 4.1.7) Answer: A Question: 92 What tests must be completed on a performance qualification made on a butt weld? A. Tensile, band, Nick break, visual (AP 1104 6.4, 6.5.2) Visit us athttps://www.certschief.com/api-1169/ B. c) welders, blasting personal (API 1169 7.2.3) C. Latitude/longitude coordinates (CGA Best Practice 6.2) D. Were bending is not required (CEPA Table 57) Answer: A Question: 93 It is who's responsible to gain access for the purpose of conducting a survey of facilities within the Encroachment Area? A. Crossing company B. Positive response C. Location D. Spike test (api 1110 4.1.7.2) Answer: A Question: 94 The total amount of residual air in the test section should not exceed ___________ of the volume of the test section? A. Encroachment Area B. 475+69 (API 1169 7.3.4) C. 50% (API 1104 7.3) D. 5% (API 1110 5.3) Answer: C Question: 95 Define Combustible liquids A. Document stating requirements Visit us athttps://www.certschief.com/api-1169/ (example quality manual, quality plan, technical drawing, procedure document, work instruction.) (ISO 9000 3.8.7) B. Liquids having a flashpoint below 100°F are Known as class 1 liquids. The most common is gasoline C. Action to illuminate the cause of a non-conformity in to prevent recurrence. (correct of action is taken to prevent recurrence where as preventative action is taken to prevent occurrence) (ISO 9000 3.12.2) D. Liquids having a flashpoint at or above 100°F are known as class 11 liquids the most common or diesel fuel, class III liquids include jet fuel and motor oil Answer: D Question: 96 Define Due Diligence Corridor A. Is the entity that intends to install, operate, maintain a new pipeline that crosses existing pipeline facilities. The Crossing company may designate a third-party or parties to perform the task necessary to accomplish a Crossing but remains responsible for the work performed by such third parties. B. Is the entity that owns our operates the existing pipeline facilities. The owner may designate a third- party or parties to perform the tasks necessary to enable a safe crossing of its facilities by crossing company but remains responsible for the work performed by such third-party. C. Is the distance equal to the width of the proposed survey Corredor +50 feet on each side of the crossing construction involving a survey Corredor. The survey Corredor is the quarter width typically use for biological surveys, for example. D. Is the area in which soil must be removed by non-mechanical means such as (hand digging, pot- holing, or hydro-Vac) rather than mechanical means. It is an area within 2 feet of the existing facilities or the distance mandated by state law where applicable, whichever is greater. Answer: C Question: 97 Pipeline stationing for the dimensions 47,568 feet would be expressed as? A. 475+69 (API 1169 7.3.4) B. a diffuser (general knowledge) C. the contractor (api 1169 5.2.3) D. 50% (api 1104 7.3) Visit us athttps://www.certschief.com/api-1169/ Answer: A Question: 98 Facility, Commissioning, and Pre-start-up Review, inspectors should understand owner/operator MOT requirements and why adherence to them can prevent incidents. In the case of construction MOC concepts do what? A. They shall be accepted as meeting the requirements provided they break at not less than 95% of the tensile strength of the material (API 1104 5.3) B. Management with regard to quality, can include establishing quality policies in quality objectives and processes to achieve these quality objectives through quality planning quality assurance quality control and quality improvement (ISO 9000 3.3.4) C. Recognize, document, and communicate such factors as change and personnel, organizational make up, physical configuration/layouts, equipment, site conditions, materials, and procedures if required. D. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation. (Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence) (ISO 9000 3.12.1) Answer: C Question: 99 Repairs to steel pipe in a natural gas pipeline that occurs arc burns, or dead, may be repaired by? A. Grinding (49 Cfr 192.1545) B. 50% (api 1104 7.3) C. Discing (ferc Upland v.c.2) D. Grinding (49 CFR 192.309) Answer: D Question: 100 Where would a worker look to find information on proper PPE for coding repairs? A. Discing (ferc upland v.c.2) Visit us athttps://www.certschief.com/api-1169/ B. MSDS (general knowledge) C. Rework (api 1104 3.1.25) D. Safety concerns (general knowledge) Answer: B Question: 101 Internal and external corrosion threats are typically managed by what type of pressure test? A. A spike test, strength test and/or a leak test (API 1110, 4.1.3 a) B. Within a set of written process safety information controls (29 CFR 1910.119, general knowledge) C. A right of way (INGaA Crossing Guideline 11 M) D. That the trench is adequately sloped, and access/egress ladders are installed. (CEPA TABLE 74) Answer: A Question: 102 Define Crossing Construction A. Management with regard to quality, can include establishing quality policies in quality objectives and processes to achieve these quality objectives through quality planning quality assurance quality control and quality improvement (ISO 9000 3.3.4) B. Is the construction of a new natural gas pipeline facility by Crossing company that will cross owners existing natural gas pipeline(s). The extent of the crossing area is established by the beginning and ending of the encroachment area. Crossing construction begins with the first disturbance of soil in the encroachment area and ends when the ROW has been restored. C. Is the entity that owns our operates the existing pipeline facilities. The owner may designate a third- party or parties to perform the tasks necessary to enable a safe crossing of its facilities by crossing company but remains responsible for the work performed by such third-party. D. Confirmation, through the provisions of objective evidence, that specified requirements have been fulfilled. (The objective evidence needed for a fair if Acacian can be the result of an inspection or of other forms of determination such as performing alternative calculations or reviewing documents) (ISO 9000 3.8.12) Visit us athttps://www.certschief.com/api-1169/ Answer: B Question: 103 Define Crossing Company A. Is the singular point of contact identified within the company of the crossing company and the owner who has the responsibility to communicate about the safely managed crossing. There will be a cross and Company designated contact and an owner designated contact. B. Is the entity that intends to install, operate, maintain a new pipeline that crosses existing pipeline facilities. The Crossing company may designate a third-party or parties to perform the task necessary to accomplish a Crossing but remains responsible for the work performed by such third parties. C. Is the construction of a new natural gas pipeline facility by Crossing company that will cross owners existing natural gas pipeline(s). The extent of the crossing area is established by the beginning and ending of the encroachment area. Crossing construction begins with the first disturbance of soil in the encroachment area and ends when the ROW has been restored. D. Is the property in which a pipeline company and a landowner both have legal interest. The ROW is usually established through a written document known as an easement. The easement provides that each entity has the right to be there although each is permitted different uses of the land. Pipeline companies are typically granted permission to install operate and maintain a buried pipeline and sometimes, with surface apparatuses across a certain portion of land without interference with its rights to do so. Answer: B Question: 104 Define validation in terms related related to data, information and document. A. Document stating requirements (example quality manual, quality plan, technical drawing, procedure document, work instruction.) (ISO 9000 3.8.7) B. Is the entity that intends to install, operate, maintain a new pipeline that crosses existing pipeline facilities. The Crossing company may designate a third-party or parties to perform the task necessary to accomplish a Crossing but remains responsible for the work performed by such third parties. C. Confirmation, through the provisions of objective evidence, that the requirements for a specific intended use or application have been fulfilled. (The objective evidence needed for a validation is the result of a test or other form of determination such as performing alternative calculations or reviewing documents) (ISO 9000 3.8.13) D. Confirmation, through the provisions of objective evidence, that specified requirements have been fulfilled. Visit us athttps://www.certschief.com/api-1169/ (The objective evidence needed for a fair if Acacian can be the result of an inspection or of other forms of determination such as performing alternative calculations or reviewing documents) (ISO 9000 3.8.12) Answer: C Question: 105 Define Designated Contact A. Is the area in which soil must be removed by non-mechanical means such as (hand digging, pot- holing, or hydro-Vac) rather than mechanical means. It is an area within 2 feet of the existing facilities or the distance mandated by state law where applicable, whichever is greater. B. Is the distance equal to the width of the proposed survey Corredor +50 feet on each side of the crossing construction involving a survey Corredor. The survey Corredor is the quarter width typically use for biological surveys, for example. C. Is the area where the ground disturbance occurs within 50 feet of the centerline of the existing facility or within the existing facilities ROW or easement, whichever is greater. Additional distance may be required for the constructions such as topography side-hill lays, catholic operating equipment, and topography. D. Is the singular point of contact identified within the company of the crossing company and the owner who has the responsibility to communicate about the safely managed crossing. There will be a cross and Company designated contact and an owner designated contact. Answer: D Question: 106 Define Excavation Tolerance Zone A. Is the singular point of contact identified within the company of the crossing company and the owner who has the responsibility to communicate about the safely managed crossing. There will be a cross and Company designated contact and an owner designated contact. B. Is the area where the edge of the disturbance is within 25 feet of the centreline of the existing facilities. C. Is the vertical separation between the existing pipeline and facilities and where the new pipeline is being installed. The recommended crossing clearance distance between the new pipeline and the existing facilities is two feet (24"). The minimum distance is one foot (12"). The new pipeline should be installed at a level depth across the ROW, if practicable. D. Is the area in which soil must be removed by non-mechanical means such as (hand digging, pot- holing, or hydro-Vac) rather than mechanical means. It is an area within 2 feet of the existing facilities or the distance mandated by state law where applicable, whichever is greater. Visit us athttps://www.certschief.com/api-1169/ Answer: D Question: 107 The cross company will identify areas where blasting will be used along the route within how many feet of the existing facilities to be crossed? A. Is the vertical separation between the existing pipeline and facilities and where the new pipeline is being installed. The recommended crossing clearance distance between the new pipeline and the existing facilities is two feet (24"). The minimum distance is one foot (12"). The new pipeline should be installed at a level depth across the ROW, if practicable. B. 300' (the members recognize this guideline differs from the one contained in the API's "Guidelines for Property Development" that specifies a hosting plan is required when blasting will occur within a (1/4) mile of existing facilities. C. Efforts to notify the excavator by phone, email, or using a contact card on a string, or other comparable method, on the door handle, or steering wheel, of the subject equipment. D. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation. (Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence) (ISO 9000 3.12.1) Answer: B Question: 108 And Inspector has noticed that a single steak marker for an excavation site is being used. What must be on the steak indicating the Excavation area? A. The steak is white in color, and shell display the excavators company identifier and radius of the excavation in black letters (CGA Best Practices App. B) B. That there is no water, rocks, hard clods, roots or debris in the ditch and that padding of rock shield is in place (API 1169 7.14.2) C. 300' (the members recognize this guideline differs from the one contained in the API's "Guidelines for Property Development" that specifies a hosting plan is required when blasting will occur within a (1/4) mile of existing facilities. D. Document stating requirements (example quality manual, quality plan, technical drawing, procedure document, work instruction.) (ISO 9000 3.8.7) Answer: A Visit us athttps://www.certschief.com/api-1169/ Question: 109 Who is responsible for all safe work on the worksite? A. The contractor (API 1169 5.2.3) B. The company ( api 1104 7.5) C. A diffuser (general knowledge) D. 475+69 (api 1169 7.3.4) Answer: A Question: 110 Defined quality manual in terms related to data, information and document A. Resource conservative in recovery act B. Federal water pollution control act, a.k.a. clean water act C. The quality policy (ISO 9000 3.5.8) D. Specification for the quality management system of an organization. (ISO 9000 3.8.8) Answer: D Question: 111 Which of the following would the inspector not have to ensure? a) confirm that the specified depth of cover will be measured from the top of the pipe to the graded ROW profile b) where buoyancy control is to be used, confirm that the depth of cover will be from the top of the buoyancy control measure c) confirmed the trench will be deep enough to provide the required cover in all conditions, including sand padding and sandbag or foam pillow supports d) Monitor for locations were available workspace is insufficient to allow compliance with safety environmental requirements, escalate and referred to the environmental inspector when identified A. d) Monitor for locations were available workspace is insufficient to allow compliance with safety and environmental requirements, escalate and refer to the environmental. Visit us athttps://www.certschief.com/api-1169/ (CEPA Table 74) B. Document stating requirements (example quality manual, quality plan, technical drawing, procedure document, work instruction.) (ISO 9000 3.8.7) C. Lifting/hoisting pipe and equipment, excavation your pipe lines or other utilities, marking/labeling, and other programs to increase awareness D. Oxygen and acetylene (welding/cutting operations) Nitrogen (purging) LPG (heating/drying) Compressed air (pneumatic tools, grit blasting, tire inflation, painting) Answer: A Question: 112 During stringing, triple jointed pipes shall be placed? A. Acceptance criteria (API Spec Q1 3.1.1) B. Were bending is not required (CEPA Table 57) C. Tensile, band, Nick break, visual (AP 1104 6.4, 6.5.2) D. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) Answer: B Question: 113 The overall intentions and direction of an organization related to quality as formally express by top management is? A. The quality policy (iso 9000 3.5.7) B. The quality policy (iso 9000 6.5.8) C. The quality policy (ISO 9000 3.5.8) D. The quality policy (iso 9000 7.5.8) Answer: C Question: 114 Visit us athttps://www.certschief.com/api-1169/ During construction of the ROW the prime consideration shall be? A. Safety to the public (ASME B31.4 443.2, API 1169 7.3.1) B. Action to illuminate the cause of a non-conformity in to prevent recurrence. (correct of action is taken to prevent recurrence where as preventative action is taken to prevent occurrence) (ISO 9000 3.12.2) C. Were bending is not required (CEPA Table 57) D. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) Answer: A Question: 115 What are some examples of loss prevention systems that the inspector should be familiar with? A. Data supporting the existence of verity of something (Objective evidence can be obtained through observation measurement test or by other means) (ISO 9000 3.8.3) B. Within 24 hours of each 0.50 inch of rainfall (FERC Upland 11.B.13) C. Lifting/hoisting pipe and equipment, excavation your pipe lines or other utilities, marking/labeling, and other programs to increase awareness D. Strength, spike, and leak (API 1110 4.1.7) Answer: C Question: 116 Operator Qualification (OQ), inspectors should understand the concepts including but not limited to covered tasks and evaluation of qualifications. What would be examples of covered tasks? a) an operator digging a trench for excavation of foreign utilities b) crew vans bringing personal to the job site on time c) review of realignment before being issued IFC d) management meetings A. A spike test, strength test and/or a leak test (API 1110, 4.1.3 a) B. OSHA 1910.147 (29 CFR 1910) occupational safety and health standard Visit us athttps://www.certschief.com/api-1169/ C. OSHA 1910.146 (29 CFR 1910) occupational safety and health standard D. a) an operator digging a trench for excavation of foreign utilities Answer: D Question: 117 Surface equipment crossing the existing facilities only do so when dictated by? A. The contractor B. The architect C. The owner D. The engineer Answer: C Question: 118 During welding procedure qualification in accordance with API 1104, if the required tensile specimens break outside the world and heat affected zone they shall be? A. Efforts to notify the excavator by phone, email, or using a contact card on a string, or other comparable method, on the door handle, or steering wheel, of the subject equipment. B. Manufacturing acceptance criteria (API Spec Q1 3.1.15 C. OSHA 1926.650 and 1926.651, (29 CFR 1926) safety and health regulations for construction D. They shall be accepted as meeting the requirements provided they break at not less than 95% of the tensile strength of the material (API 1104 5.3) Answer: D Question: 119 Cathodic protection test stations are typically installed every? A. rework (api 1104 3.1.25) B. 98 to 3 kilometres (cepa 16.1) C. 12 inches (api 1169 7.15) Visit us athttps://www.certschief.com/api-1169/ D. 2 to 3 kilometres (CEPA 16.1) Answer: D Question: 120 Define preventative action in terms related to action. A. Inspectors are expected to function at all times as a representative of the pipeline company owning and or managing the project. In most cases the inspector works for or represents a pipeline company, with strict procedures and war contract provisions are in place that spell out the expectations and obligations of the inspectors performance. B. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation. (Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence) (ISO 9000 3.12.1) C. An individual qualified to monitor, assess, evaluate, verify, discuss, decide, resolve, report, and document pipeline construction activities to ensure the requirements of the design, drawings, specifications, regulations, and Industry practises are being met safely, effectively, and in an environmentally sound manner. D. Is the entity that owns our operates the existing pipeline facilities. The owner may designate a third- party or parties to perform the tasks necessary to enable a safe crossing of its facilities by crossing company but remains responsible for the work performed by such third-party. Answer: B Question: 121 If the owner observed excavation equipment in the encroachment area and is unaware of planned activities, the owner will undertake reasonable efforts to alert the excavator of the presence of any unknown pipeline in the are a. This could include? A. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives (ISO 9000 3.3.5) B. 300' (the members recognize this guideline differs from the one contained in the API's "Guidelines for Property Development" that specifies a hosting plan is required when blasting will occur within a (1/4) mile of existing facilities. C. Data supporting the existence of verity of something (Objective evidence can be obtained through observation measurement test or by other means) (ISO 9000 3.8.3) D. Efforts to notify the excavator by phone, email, or using a contact card on a string, or other comparable method, on the door handle, or steering wheel, of the subject equipment. Visit us athttps://www.certschief.com/api-1169/ Answer: D Question: 122 Define quality plan in terms related to Data, information and document. A. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) B. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) C. Specification of the procedures and associated resources to be applied when and by whom to a specified object. (these procedures generally include those referring to quality management processes and the product and services realization processes) (ISO 9000 3.8.9) D. Process of establishing, documenting, implementing, maintaining and continually improving a quality management system. (ISO 9000 3.4.3) Answer: C Question: 123 Which of the following is not true regarding welding and cutting near combustibles? a) no welding or cutting she'll be done unless the atmosphere is non-flammable and combustibles are moved away or protected from fire and hazards. b) where it is practical, the welding or cutting work she'll be moved to a designated safe location. c) where the work and fire hazards are not movable, safeguards she'll be used to protect the immovable fire hazards and nearby personnel. d) welding should not be done with floors are combustible. A. d) Monitor for locations were available workspace is insufficient to allow compliance with safety and environmental requirements, escalate and refer to the environmental. (CEPA Table 74) B. d) welding she will not be done we're floors are combustible (ANDI Z49.1 6.1) C. A spike test, strength test and/or a leak test (API 1110, 4.1.3 a) D. terrain features; landowner issues; road, railroad, or waterway crossing; environmental features; cultural features and protected resources (i.e. drinking water and proximity to occupied facilities) Visit us athttps://www.certschief.com/api-1169/ Answer: B Question: 124 To eliminate potential confusion caused by lack of a response to a one call, the owners designated contact will notify the cross companies designed with a ? indicating either that there is no conflict or the line will be marked. A. Crossing Company B. Cognitive Learning C. Positive Response D. Classical Condition Answer: C Question: 125 Inspections of excavation she'll be conducted by competent person a) Prior to the start of work b) prior to the start of work and as needed throughout the shift and after every rainstorm that has an excess of 1 inch of rainfall or hazard increasing occurrence c) prior to the start of work and as needed throughout the shift and after every rainstorm that has in accidents of.5 inch of rain full or hazard increasing occurrence d) prior to the start of work and as needed throughout the shift and after every frame storm or hazard increasing occurrence A. They shall be accepted as meeting the requirements provided they break at not less than 95% of the tensile strength of the material (API 1104 5.3) B. Owner operator C. d) prior to the start of work and as needed throughout the shift and after every frame storm or hazard increasing occurrence (29 CFR 1926.651 (k) (I)) D. A part of quality management Focused on the ability to fulfil quality requirements. The quality requirements can be related to any aspect such as effectiveness efficiency or traceability. Answer: C Question: 126 Typical gases used in new pipeline construction are? Visit us athttps://www.certschief.com/api-1169/ A. Within 2 feet of the existing facilities or the distance mandated by state law which ever is greater (INGAA CROSSING guide 11 K) B. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives (ISO 9000 3.3.5) C. Oxygen and acetylene (welding/cutting operations) Nitrogen (purging) LPG (heating/drying) Compressed air (pneumatic tools, grit blasting, tire inflation, painting) D. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) Answer: C Question: 127 Methods of addressing so compaction in agricultural areas include? A. discing (FERC Upland V.C.2) B. 50' C. the company ( api 1104 7.5) D. rework (api 1104 3.1.25) Answer: A Question: 128 Define specification in terms related to data information and document A. Data supporting the existence of verity of something (Objective evidence can be obtained through observation measurement test or by other means) (ISO 9000 3.8.3) B. Within 2 feet of the existing facilities or the distance mandated by state law which ever is greater (INGAA CROSSING guide 11 K) C. Document stating requirements (example quality manual, quality plan, technical drawing, procedure document, work instruction.) (ISO 9000 3.8.7) D. Lifting/hoisting pipe and equipment, excavation your pipe lines or other utilities, marking/labeling, and other programs to increase awareness Answer: C Visit us athttps://www.certschief.com/api-1169/ Question: 129 Define quality improvement in terms related to activity. A. Action to illuminate the cause of a non-conformity in to prevent recurrence. (correct of action is taken to prevent recurrence where as preventative action is taken to prevent occurrence) (ISO 9000 3.12.2) B. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives (ISO 9000 3.3.5) C. A part of quality management Focused on the ability to fulfil quality requirements. The quality requirements can be related to any aspect such as effectiveness efficiency or traceability. D. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) Answer: C Question: 130 List Attached C, drawing illustration Guidelines found in INGAA Foundation A. Residence within proximity of the facility being tested, state and local enforcement agencies. (CS-S-9 4.5) B. Within 24 hours of each 0.50 inch of rainfall (FERC Upland 11.B.13) C. Strength, spike, and leak (API 1110 4.1.7 Answer: C Question: 131 The quality management system documentation shall include? A. Process of establishing, documenting, implementing, maintaining and continually improving a quality management system. (ISO 9000 3.4.3) B. Person or group of people who directs and controls an organization at the highest level (ISO 9000 3.1.1) Visit us athttps://www.certschief.com/api-1169/ C. Management system set of interrelated or interacting elements of an organization to establish policies and objectives and processes to achieve those objectives. (ISO 9000 3.5.4) D. Statements of policy and objectives (API Spec Q1 4.4.1) Answer: D Question: 132 Define top management as related to a person or people A. Person or group of people who directs and controls an organization at the highest level (ISO 9000 3.1.1) B. Is the plan devise between the owner and crossing party to specify the details and provisions under which the crossing construction show occur. Depending on the size the nature of the crossing across and plan should be simple as an exchange of the mechanical requirements and an email agreement to follow these requirements. The more complex jobs the crossing plan should include topics such as cathodic protection requirements, a blasting plan (if any), support and backfill requirements, and erosion control. C. Management system set of interrelated or interacting elements of an organization to establish policies and objectives and processes to achieve those objectives. (ISO 9000 3.5.4) D. Resource conservative in recovery act Answer: A Question: 133 The inspector should check and ensure that soft earth padding at least ____________ thick is in place in Rocky train in accordance with job specifications. A. 475+69 (api 1169 7.3.4) B. 50% (api 1104 7.3) C. 12 inches (API 1169 7.15) D. rework (api 1104 3.1.25) Answer: C Visit us athttps://www.certschief.com/api-1169/ Question: 134 Which of the following would not be an essential variable for welding procedure qualification? A) change in base material B) change in the joint design C) change in electrode size D) increase in the time between passess A. Within 24 hours of each 0.50 inch of rainfall (FERC Upland 11.B.13) B. C) change in electrode size (API 1104 5.4) C. Were bending is not required (CEPA Table 57) D. Safety concerns (general knowledge) Answer: B Question: 135 Temporary trench plugs may consist of? A. Is the area where the edge of the disturbance is within 25 feet of the centreline of the existing facilities. B. I excavated portions of the trench (FERC Upland IV.F.2.a) C. Were bending is not required (CEPA Table 57) D. Latitude/longitude coordinates (CGA Best Practice 6.2) Answer: B Question: 136 Where should emergency information for chemicals in substances be located? A. Lifting/hoisting pipe and equipment, excavation your pipe lines or other utilities, marking/labeling, and other programs to increase awareness B. OSHA 1926.650 and 1926.651, (29 CFR 1926) safety and health regulations for construction C. Within a set of written process safety information controls Visit us athttps://www.certschief.com/api-1169/ (29 CFR 1910.119, general knowledge) D. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) Answer: C Question: 137 Specific limits of acceptability apply to the process of product characteristics is the definition of? A. Manufacturing acceptance criteria (api spec q1 3.1.15 B. Latitude/longitude coordinates (cga Best Practice 6.2) C. Spike test (api 1110 4.1.7.2) D. Acceptance criteria (API Spec Q1 3.1.1) Answer: D Question: 138 During storage of received pipe the inspector will ensure that placement of timber and chokers are in compliance with? A. Owner specifications ( CEPA Table 55) B. The third-party owner (cepa Table 130) C. Rework (api 1104 3.1.25) D. Grinding (49 cfr 192.309) Answer: A Question: 139 The owner will ensure that all points of inflection (PI's) within what area are clearly marked and maintained during the crossing Construciton? A. Active Excavation Area B. Protected Area Visit us athttps://www.certschief.com/api-1169/ C. Encroachment Area D. Operation Area Answer: C Question: 140 Define Encroachment Area A. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) B. A part of quality management Focused on the ability to fulfil quality requirements. The quality requirements can be related to any aspect such as effectiveness efficiency or traceability. C. Is the area where the ground disturbance occurs within 50 feet of the centerline of the existing facility or within the existing facilities ROW or easement, whichever is greater. Additional distance may be required for the constructions such as topography side-hill lays, catholic operating equipment, and topography. D. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) Answer: C Question: 141 Define TWIC A. Transportation worker identification card B. Operator qualification C. National pollutant discharge elimination systems D. Resource conservative in recovery act Answer: A Question: 142 What are the three basic types of hydrostatic pressure tests? A. Spike test (api 1110 4.1.7.2) B. Strength, spike, and leak (api 1110 4.1.8) C. The company Visit us athttps://www.certschief.com/api-1169/ ( api 1104 7.5) D. Strength, spike, and leak (API 1110 4.1.7) Answer: D Question: 143 Inspector should strive to prevent any type of environmental contamination. In the event of an instant inspector should immediately report the event to? A. The owner B. Owner operator C. Broker D. Operator qualification Answer: B Question: 144 Define CFR A. Called a federal regulations B. Transportation worker identification card C. Operator qualification D. Resource conservative in recovery act Answer: A Question: 145 Define NPDES A. Transportation worker identification card B. Spill prevention, control, and containment C. National pollutant discharge elimination systems D. Operator qualification Answer: C Visit us athttps://www.certschief.com/api-1169/ Question: 146 Define quality control in terms related to activity. A. Have the longitude a weld as near as practical to the neutral axis of the band (49 CFR 192.313) B. Is the area where the edge of the disturbance is within 25 feet of the centreline of the existing facilities. C. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) D. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation. (Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence) (ISO 9000 3.12.1) Answer: C Question: 147 Define BMP A. Group selection harvesting B. Sustainable agriculture C. Best management practices D. Better managed pollution Answer: C Question: 148 Define Crossing clearance distance A. Is the area in which soil must be removed by non-mechanical means such as (hand digging, pot- holing, or hydro-Vac) rather than mechanical means. It is an area within 2 feet of the existing facilities or the distance mandated by state law where applicable, whichever is greater. B. Is the vertical separation between the existing pipeline and facilities and where the new pipeline is being installed. The recommended crossing clearance distance between the new pipeline and the existing facilities is two feet (24"). The minimum distance is one foot (12"). The new pipeline should be installed at a level depth across the ROW, if practicable. C. Inspectors are expected to function at all times as a representative of the pipeline company owning and or managing the project. In most cases the inspector works for or represents a pipeline company, Visit us athttps://www.certschief.com/api-1169/ with strict procedures and war contract provisions are in place that spell out the expectations and obligations of the inspectors performance. D. Liquids having a flashpoint at or above 100°F are known as class 11 liquids the most common or diesel fuel, class III liquids include jet fuel and motor oil Answer: B Question: 149 Define OQ A. Resource conservative in recovery act B. National pollutant discharge elimination systems C. Transportation worker identification card D. Operator qualification Answer: D Question: 150 Define crossing plan A. Is the agreement entered into between the owner of the existing facility and the crossing company installing the new facility to specify the rights and obligations of the parties during the crossing Construciton. B. Federal water pollution control act, a.k.a. clean water act C. Is the plan devise between the owner and crossing party to specify the details and provisions under which the crossing construction show occur. Depending on the size the nature of the crossing across and plan should be simple as an exchange of the mechanical requirements and an email agreement to follow these requirements. The more complex jobs the crossing plan should include topics such as cathodic protection requirements, a blasting plan (if any), support and backfill requirements, and erosion control. D. The company ( API 1104 7.5) Answer: C Question: 151 The land base and data base for one call shall use? A. Latitude/longitude coordinates (CGA Best Practice 6.2) Visit us athttps://www.certschief.com/api-1169/ B. Latitude/longitude coordinates (cga Best Practice 6.102) C. Latitude/longitude coordinates (cga Best Practice 7.2) D. Latitude/longitude coordinates (cga Best Practice 6.4) Answer: A Question: 152 What would an inspector look for at the end of a dewatering line? A. The contractor (api 1169 5.2.3) B. A diffuser (general knowledge) C. Notify the owner (api 1169, 6.7) D. The quality policy (iso 9000 3.5.8) Answer: A Question: 153 After daylighting a third-party Pipeline, and damage to the existing facility is noted, the inspector shall contact? A. The third-party owner (CEPA Table 130) B. The owner C. Notify the owner (api 1169, 6.7) D. Owner specifications ( cepa Table 55) Answer: A Question: 154 Define FWPCA A. Specification for the quality management system of an organization. (ISO 9000 3.8.8) B. The quality policy (ISO 9000 3.5.8) Visit us athttps://www.certschief.com/api-1169/ C. Federal water pollution control act, a.k.a. clean water act D. Is the plan devise between the owner and crossing party to specify the details and provisions under which the crossing construction show occur. Depending on the size the nature of the crossing across and plan should be simple as an exchange of the mechanical requirements and an email agreement to follow these requirements. The more complex jobs the crossing plan should include topics such as cathodic protection requirements, a blasting plan (if any), support and backfill requirements, and erosion control. Answer: C Question: 155 During the welding or after the world has been completed, but before visual or non-destructive testing is carried out, the grinding or removal of an imperfection is referred to as? A. Spike test (api 1110 4.1.7.2) B. Rework (API 1104 3.1.25) C. 50% (api 1104 7.3) D. Rework (api 1099 3.1.25) Answer: B Question: 156 Name the uniform color code colours and what they mean. A. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives (ISO 9000 3.3.5) B. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) C. terrain features; landowner issues; road, railroad, or waterway crossing; environmental features; cultural features and protected resources (i.e. drinking water and proximity to occupied facilities) Answer: A Question: 157 A property in which a pipeline company and the landowner both have a legal interest is? A. A right of way Visit us athttps://www.certschief.com/api-1169/ (INGaA Crossing Guideline 11 M) B. Tensile, band, Nick break, visual (AP 1104 6.4, 6.5.2) C. Strength, spike, and leak (API 1110 4.1.7) D. c) welders, blasting personal (API 1169 7.2.3) Answer: A Question: 158 Work Permits for Hot Work would be found under what OSHA standard? A. Tensile, band, Nick break, visual (AP 1104 6.4, 6.5.2) B. Have the longitude a weld as near as practical to the neutral axis of the band (49 CFR 192.313) C. OSHA 1910.119 (k) (29 CFR 1910) occupational safety and health standard D. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) Answer: C Question: 159 Define Right of way ROW A. Is the vertical separation between the existing pipeline and facilities and where the new pipeline is being installed. The recommended crossing clearance distance between the new pipeline and the existing facilities is two feet (24"). The minimum distance is one foot (12"). The new pipeline should be installed at a level depth across the ROW, if practicable. B. Is the construction of a new natural gas pipeline facility by Crossing company that will cross owners existing natural gas pipeline(s). The extent of the crossing area is established by the beginning and ending of the encroachment area. Crossing construction begins with the first disturbance of soil in the encroachment area and ends when the ROW has been restored. C. Is the area where the ground disturbance occurs within 50 feet of the centerline of the existing facility or within the existing facilities ROW or easement, whichever is greater. Additional distance may be required for the constructions such as topography side-hill lays, catholic operating equipment, and topography. D. Is the property in which a pipeline company and a landowner both have legal interest. The ROW is usually established through a written document known as an easement. The easement provides that each entity has the right to be there although each is permitted different uses of the land. Pipeline companies are typically granted permission to install operate and maintain a buried pipeline and Visit us athttps://www.certschief.com/api-1169/ sometimes, with surface apparatuses across a certain portion of land without interference with its rights to do so. Answer: D Question: 160 Root bead segments used in connection with external clamps should be uniformly spaced around the circumference of the pipe and shall have an aggregate length of at least ____________ of the pipe circumference before the clamp is removed? A. 50% (API 1104 7.3) B. notify the owner (api 1169, 6.7) C. 50% (api 1094 7.3) D. rework (api 1104 3.1.25) Answer: A Question: 161 Define CERCLA A. National pollutant discharge elimination systems B. Comprehensive environmental response, comprehensive and liability act C. Resource conservative in recovery act D. Operator qualification Answer: B Question: 162 Who is responsible for all damages, repairs and rehabilitation caused by its construction activities, as well as restoration of the disturbed portions of the existing facilities ROW, to the satisfaction of all parties? A. The crossing company B. Owner operator C. Encroachment area Visit us athttps://www.certschief.com/api-1169/ D. Location Answer: A Question: 163 Define limits placed on characteristics of materials, products, and services established by the organization to achieve conformity to the manufacturing or service requirements is the definition of? A. Rework (api 1104 3.1.25) B. Acceptance criteria (api spec q1 3.1.1) C. Strength, spike, and leak (api 1110 4.1.7) D. Manufacturing acceptance criteria (API Spec Q1 3.1.15 Answer: D Question: 164 Define RCRA A. Resource conservative in recovery act B. Operator qualification C. Specification for the quality management system of an organization. (ISO 9000 3.8.8) D. Comprehensive environmental response, comprehensive and liability act Answer: A Question: 165 Definition for Active Excavation Area A. Is the area where the edge of the disturbance is within 25 feet of the centreline of the existing facilities. B. That there is no water, rocks, hard clods, roots or debris in the ditch and that padding of rock shield is in place (API 1169 7.14.2) C. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) Visit us athttps://www.certschief.com/api-1169/ D. Is the distance equal to the width of the proposed survey Corredor +50 feet on each side of the crossing construction involving a survey Corredor. The survey Corredor is the quarter width typically use for biological surveys, for example. Answer: A Question: 166 What is the primary issue that must be addressed with Crossing navigable waters with a natural gas pipeline? A. Msds (general knowledge) B. A diffuser (general knowledge) C. Safety concerns (general knowledge) D. The quality policy (iso 9000 3.5.8) Answer: C Question: 167 What would be a discovered or potential pipeline route selection deficiencies or obstruction? A. An entity that includes the primary organization and any subcontractors engaged in pipeline construction covered by ARPI 1169 3.1.1 B. terrain features; landowner issues; road, railroad, or waterway crossing; environmental features; cultural features and protected resources (i.e. drinking water and proximity to occupied facilities) C. Hearing protection is used when the work environment noise level exceeds 85 dbA over an 8-hour period D. A diffuser (general knowledge) Answer: B Question: 168 Define quality assurance in terms related to activity. A. Liquids having a flashpoint below 100°F are Known as class 1 liquids. The most common is gasoline B. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation. Visit us athttps://www.certschief.com/api-1169/ (Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence) (ISO 9000 3.12.1) C. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) D. A part of quality management Focused on the ability to fulfil quality requirements. The quality requirements can be related to any aspect such as effectiveness efficiency or traceability. Answer: C Question: 169 Define verification in terms related to data, information and document. A. Confirmation, through the provisions of objective evidence, that the requirements for a specific intended use or application have been fulfilled. (The objective evidence needed for a validation is the result of a test or other form of determination such as performing alternative calculations or reviewing documents) (ISO 9000 3.8.13) B. Confirmation, through the provisions of objective evidence, that specified requirements have been fulfilled. (The objective evidence needed for a fair if Acacian can be the result of an inspection or of other forms of determination such as performing alternative calculations or reviewing documents) (ISO 9000 3.8.12) C. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation. (Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence) (ISO 9000 3.12.1) D. Placement of the ROW, Location of the existing of proposed pipelines within the ROW, the types of easement (exclusive, or open and undefined), construction methods and practices, unique landscape, terrain, or environmental situations, separation distances, restrictions on type in location of heavy equipment crossings, any potential pipeline integrity concerns, responsibility for cathodic protection after installation, the ground disturbance timing. Answer: B Question: 170 A Hazardous Atmosphere has what condition and are classified as Follows? A. Flammable gas, vapor, mist, or dust in excess of LFL - oxygen efficient/excess environments were auction levels are below 19.5% or above 23.5% - PEL Visit us athttps://www.certschief.com/api-1169/ - other atmospheric conditions are concentrations of toxic contaminants that may be IDLH B. A part of quality management Focused on the ability to fulfil quality requirements. The quality requirements can be related to any aspect such as effectiveness efficiency or traceability. C. Within a set of written process safety information controls (29 CFR 1910.119, general knowledge) D. Lifting/hoisting pipe and equipment, excavation your pipe lines or other utilities, marking/labeling, and other programs to increase awareness Answer: A Question: 171 Inspector should ensure prior to lowering in that? A. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) B. That there is no water, rocks, hard clods, roots or debris in the ditch and that padding of rock shield is in place (API 1169 7.14.2) C. Is the area where the edge of the disturbance is within 25 feet of the centreline of the existing facilities. D. Have the longitude a weld as near as practical to the neutral axis of the band (49 CFR 192.313) Answer: B Question: 172 Work Permits for excavation would be found under what OSHA standard? A. OSHA 1910.109 and OSHA 1926.900 to 1926.914 B. Part of quality management focused on fulfilling quality requirements (ISO 9000 3.3.7) C. OSHA 1926.650 and 1926.651, (29 CFR 1926) safety and health regulations for construction D. Have the longitude a weld as near as practical to the neutral axis of the band (49 CFR 192.313) Answer: C Question: 173 Visit us athttps://www.certschief.com/api-1169/ Define correct of action in terms related to action. A. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation. (Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence) (ISO 9000 3.12.1) B. Action to illuminate the cause of a non-conformity in to prevent recurrence. (correct of action is taken to prevent recurrence where as preventative action is taken to prevent occurrence) (ISO 9000 3.12.2) C. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) D. Is the singular point of contact identified within the company of the crossing company and the owner who has the responsibility to communicate about the safely managed crossing. There will be a cross and Company designated contact and an owner designated contact. Answer: B Question: 174 How often are inspectors required to inspect temporary Rosian control measures? A. 2 to 3 kilometres (CEPA 16.1) B. a) an operator digging a trench for excavation of foreign utilities C. Within 24 hours of each 0.50 inch of rainfall (FERC Upland 11.B.13) D. Barred or curled Answer: C Question: 175 Define process in terms related to process. A. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) B. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives (ISO 9000 3.3.5) C. Hearing protection is used when the work environment noise level exceeds 85 dbA over an 8-hour period Visit us athttps://www.certschief.com/api-1169/ D. Is the area where the edge of the disturbance is within 25 feet of the centreline of the existing facilities. Answer: A Question: 176 Permits for explosive blasting would be found under what OSHA standard? A. The owner B. Location C. Crossing company D. OSHA 1910.109 and OSHA 1926.900 to 1926.914 Answer: D Question: 177 A hazardous atmosphere means? A. Is the area where the edge of the disturbance is within 25 feet of the centreline of the existing facilities. B. Have the longitude a weld as near as practical to the neutral axis of the band (49 CFR 192.313) C. And atmosphere that may be immediately danger to life and health (IDLH) or exceed permissible exposure limits (PEl's) D. Is the distance equal to the width of the proposed survey Corredor +50 feet on each side of the crossing construction involving a survey Corredor. The survey Corredor is the quarter width typically use for biological surveys, for example. Answer: C Question: 178 Who is responsible for determining if weather conditions are suitable for welding? A. The company ( API 1104 7.5) B. The company ( Api 1104 2.5) C. Rework (api 1104 3.1.25) D. Discing Visit us athttps://www.certschief.com/api-1169/ (ferc upland v.c.2) Answer: A Question: 179 Define quality management in terms related to activity. A. Confirmation, through the provisions of objective evidence, that the requirements for a specific intended use or application have been fulfilled. (The objective evidence needed for a validation is the result of a test or other form of determination such as performing alternative calculations or reviewing documents) (ISO 9000 3.8.13) B. Set of interrelated activities that use inputs to deliver an intended result (ISO 9000 3.4.1) C. Oxygen and acetylene (welding/cutting operations) Nitrogen (purging) LPG (heating/drying) Compressed air (pneumatic tools, grit blasting, tire inflation, painting) D. Management with regard to quality, can include establishing quality policies in quality objectives and processes to achieve these quality objectives through quality planning quality assurance quality control and quality improvement (ISO 9000 3.3.4) Answer: D Question: 180 Backhoe teeth shall be ? each time the bucket approaches the existing facility. A. The owner B. Owner operator C. Barred or curled D. Msds (general knowledge) Answer: C Question: 181 Define Flammable liquids A. Comprehensive environmental response, comprehensive and liability act Visit us athttps://www.certschief.com/api-1169/ B. Liquids having a flashpoint below 100°F are Known as class 1 liquids. The most common is gasoline C. Part of quality management focussed on providing confidence that quality requirements will be fulfilled. (ISO 9000 3.3.6) D. Is the distance equal to the width of the proposed survey Corredor +50 feet on each side of the crossing construction involving a survey Corredor. Th