How to find slack time in project management?

Understand the Problem

The question is asking for methods or techniques to determine slack time in project management, which refers to the amount of time that a task can be delayed without affecting the subsequent tasks or the overall project timeline.

Answer

Subtract Early Start from Late Start, or Early Finish from Late Finish to find slack time.

To calculate slack time, subtract the Early Start Time from the Late Start Time, or the Early Finish Time from the Late Finish Time.

Answer for screen readers

To calculate slack time, subtract the Early Start Time from the Late Start Time, or the Early Finish Time from the Late Finish Time.

More Information

Slack time, also known as float, helps project managers identify how much a task can be delayed without affecting the entire project schedule.

Tips

Common mistakes include confusing earliest and latest times, and not correctly identifying critical path activities where slack time is zero.