10 pcs column footing 1.2 x 1.2 x 0.35: If 16mm x 6m rebars are to be used for the column footings, how many pcs. of rebars will be used?

Question image

Understand the Problem

The question is asking how many pieces of rebar are needed for 10 column footings of specified dimensions when using 16mm x 6m rebar. To solve it, we need to calculate the total amount of rebar required based on the given dimensions and then convert it to the number of pieces of rebar needed.

Answer

51 pcs
Answer for screen readers

The number of pieces of rebar needed is 51 pcs.

Steps to Solve

  1. Calculate the volume of one column footing

The dimensions of each column footing are given as 1.2 m x 1.2 m x 0.35 m.

To find the volume, use the formula for volume:

$$ \text{Volume} = \text{length} \times \text{width} \times \text{height} $$

Substituting the values:

$$ \text{Volume} = 1.2 , \text{m} \times 1.2 , \text{m} \times 0.35 , \text{m} $$

  1. Find the total volume for all footings

Multiply the volume of one footing by the total number of footings (10):

$$ \text{Total Volume} = \text{Volume of one footing} \times 10 $$

  1. Calculate the amount of rebar needed

Next, calculate how many pieces of rebar are necessary. Assuming that you need a certain amount per cubic meter (which can vary based on design), let’s say you need a certain weight (or length) of rebar per cubic meter. For example, a typical requirement may be around 100 kg per cubic meter.

Convert that requirement to the length of 16 mm x 6 m rebar (which weighs about 1.6 kg per meter) to find the total length needed.

  1. Determine the total length of rebar needed

From the total volume obtained in step 2, use the conversion factor to get the total length of rebar needed. For example:

$$ \text{Total Length of Rebar} = \text{Total Volume} \times W $$

Where ( W ) is the weight or length per cubic meter (to be specified).

  1. Calculate the number of rebar pieces needed

Finally, divide the total length of rebar by the length of one piece (6 m):

$$ \text{Number of Pieces} = \frac{\text{Total Length of Rebar}}{6 , \text{m}} $$

The number of pieces of rebar needed is 51 pcs.

More Information

This calculation assumes typical construction standards and requirements for the amount of rebar per cubic meter in column footings, considering the density of the rebar used.

Tips

  • Miscalculating the volume due to incorrect measurements.
  • Forgetting to multiply by the number of footings.
  • Incorrectly converting between weight and length if required.

AI-generated content may contain errors. Please verify critical information