Untitled Quiz
29 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the difference between duration and effort in project management?

  • Duration includes time worked and elapsed time, while effort is the workdays required. (correct)
  • Duration refers only to the workdays while effort includes total time.
  • Duration is the total time taken to complete a task, while effort is the work hours needed.
  • Effort equals duration in all cases of project timelines.

What are the components involved in a three-point estimate?

  • Optimistic, most likely, and pessimistic estimates. (correct)
  • Projected, historical, and current estimates.
  • Best, worst, and expected estimates.
  • Minimum, average, and maximum estimates.

Which of the following tools is NOT commonly used in schedule development?

  • Gantt charts
  • Resource allocation matrix (correct)
  • Critical path analysis
  • PERT analysis

What is the purpose of a Gantt chart in project management?

<p>To display project activities and their schedules visually. (A)</p> Signup and view all the answers

Who should ideally participate in creating estimates for project activities?

<p>The people doing the work, with review by an expert. (C)</p> Signup and view all the answers

What is primarily responsible for conflicts during the second half of a project?

<p>Schedule issues (A)</p> Signup and view all the answers

Which process involves identifying the specific activities needed to meet project deliverables?

<p>Defining activities (A)</p> Signup and view all the answers

What does the Work Breakdown Structure (WBS) help to define and organize?

<p>Total project scope (D)</p> Signup and view all the answers

Which of the following is NOT part of the project time management processes?

<p>Creating project charter (D)</p> Signup and view all the answers

What is involved in developing a project schedule?

<p>Analyzing activity sequences (B)</p> Signup and view all the answers

Which process focuses on determining necessary resources for project activities?

<p>Estimating activity resources (C)</p> Signup and view all the answers

Why is time considered to have the least amount of flexibility in project management?

<p>It passes regardless of project events (A)</p> Signup and view all the answers

What is the main purpose of sequencing activities in project time management?

<p>To document relationships between activities (A)</p> Signup and view all the answers

What is a key component of a schedule management plan that dictates how project activities are measured for accuracy?

<p>Level of accuracy and units of measure (A)</p> Signup and view all the answers

Which of the following is true about mandatory dependencies?

<p>They are inherent in the nature of the work being performed. (D)</p> Signup and view all the answers

How does an activity list primarily help in project scheduling?

<p>It tabulates activities to be included in the project schedule. (D)</p> Signup and view all the answers

What does the term 'sequencing activities' refer to in project management?

<p>Determining dependencies between activities. (B)</p> Signup and view all the answers

Which type of dependency is based on good practices rather than necessity?

<p>Discretionary dependency (B)</p> Signup and view all the answers

What is defined by the control thresholds established in a schedule management plan?

<p>The variance allowed for monitoring schedule performance. (D)</p> Signup and view all the answers

Which of the following attributes provide additional information about project activities?

<p>Resource requirements and constraints (B)</p> Signup and view all the answers

What is an example of an external dependency?

<p>Installation of software dependent on new hardware delivery. (A)</p> Signup and view all the answers

What do nodes or circles represent in an Arrow Diagramming Method (ADM)?

<p>The start and end points of activities (A)</p> Signup and view all the answers

Which type of relationships can the Arrow Diagramming Method (ADM) display?

<p>Finish-to-start dependencies (C)</p> Signup and view all the answers

What is a 'burst' in the context of network diagrams?

<p>A point where multiple activities start from different nodes (B)</p> Signup and view all the answers

What do arrows represent in a Precedence Diagramming Method (PDM)?

<p>The sequence and relationships between activities (A)</p> Signup and view all the answers

When estimating activity resources, which question is crucial to ask regarding resource availability?

<p>Are the required resources available? (D)</p> Signup and view all the answers

Which method is more popular for displaying project activity dependencies?

<p>Precedence Diagramming Method (PDM) (D)</p> Signup and view all the answers

What does the term 'merge' refer to in network diagrams?

<p>When two nodes transition into a single node (D)</p> Signup and view all the answers

Which of the following does NOT represent a consideration for estimating activity resources?

<p>The marketing strategy for the project (C)</p> Signup and view all the answers

Flashcards

Project Schedule Importance

Delivering projects on time is a major challenge for managers, as time constraints have little flexibility.

WBS (Work Breakdown Structure)

A hierarchical tree structure used to define and organize the full scope of a project.

Project Time Management Processes

A series of steps involved in planning, controlling, and executing the project schedule.

Planning Schedule

Establishing policies, procedures, and documentation for managing the project schedule.

Signup and view all the flashcards

Defining Activities

Identifying specific tasks that project team members and stakeholders need to complete.

Signup and view all the flashcards

Sequencing Activities

Determining the order and relationship between project tasks.

Signup and view all the flashcards

Estimating Activity Resources

Estimating the amount of resources required to complete a project task.

Signup and view all the flashcards

Estimating Activity Durations

Predicting the time needed to complete individual tasks.

Signup and view all the flashcards

Schedule Management Plan

A document that outlines how the project schedule will be planned, controlled, and managed.

Signup and view all the flashcards

Project Schedule Mode

Contains project activities, their durations, dependencies, and other planning information used to create a project schedule.

Signup and view all the flashcards

Control Thresholds

Pre-defined limits for acceptable schedule variance, often expressed as percentages.

Signup and view all the flashcards

Activity List

A table listing all project activities, including their names, unique identifiers, and brief descriptions.

Signup and view all the flashcards

Mandatory Dependencies

Dependencies inherent in the nature of the work, where one task cannot start before another is completed.

Signup and view all the flashcards

Discretionary Dependencies

Dependencies defined by the project team for efficiency, based on best practices, not strict requirements.

Signup and view all the flashcards

External Dependencies

Dependencies on activities outside of the project, involving interactions with external stakeholders.

Signup and view all the flashcards

Activity Attributes

Additional information about activities, such as predecessors, successors, logical relationships, resource requirements, constraints, and assumptions.

Signup and view all the flashcards

Network Diagram

A visual representation of the dependencies and sequence of project activities. It helps in understanding the project flow and identifying critical paths.

Signup and view all the flashcards

Arrow Diagramming Method (ADM)

A method for creating network diagrams where activities are represented by arrows and nodes indicate start and end points. Limited to finish-to-start dependencies.

Signup and view all the flashcards

Activity-on-Arrow (AOA)

A specific type of network diagram using arrows to represent project activities.

Signup and view all the flashcards

Precedence Diagramming Method (PDM)

A network diagram approach where activities are represented by boxes, and arrows show the relationships between activities. Better for showing different types of dependencies.

Signup and view all the flashcards

What are bursts?

In AOA diagrams, a single node followed by two or more activities. This signifies that the first task must finish before multiple subsequent tasks can start.

Signup and view all the flashcards

Merge

In AOA diagrams, where two or more nodes precede a single node, indicating two or more activities must finish before the next activity can begin.

Signup and view all the flashcards

Resource Estimation

Evaluating the resources (people, equipment, and materials) required for each project activity. This helps determine if resources are sufficient, available, and suitable.

Signup and view all the flashcards

What factors influence resource estimation?

Factors such as the complexity of the task, organizational history, resource availability, and resource capabilities all influence resource estimation.

Signup and view all the flashcards

Effort vs. Duration

Effort is the number of workdays or hours needed for a task, while duration is the actual time spent including breaks and delays.

Signup and view all the flashcards

Three-Point Estimate

A three-point estimate uses an optimistic, most likely, and pessimistic estimate to account for uncertainty in activity duration.

Signup and view all the flashcards

Gantt Chart

A Gantt chart visually represents project tasks, their start and finish dates, and dependencies between them.

Signup and view all the flashcards

Dependencies between Tasks

Dependencies show the relationships between tasks, like 'Task B can't start until Task A is finished'.

Signup and view all the flashcards

Study Notes

Lecture 4, Chapter 6: Project Time Management - Part 1

  • Project managers often cite delivering projects on time as one of their biggest challenges.
  • Time has the least amount of flexibility; it passes regardless of project events.
  • Schedule issues are the primary cause of conflicts in projects, particularly during the latter stages.

Work Breakdown Structure (WBS)

  • A WBS is a fundamental project management technique.
  • It defines and organizes the total scope of a project.
  • It uses a hierarchical tree structure.

Building House WBS Example

  • Shows a breakdown of tasks for building a house, from project management to landscaping.
  • It lists specific tasks, materials, and activities (e.g., laying foundation, constructing walls, designing interiors, etc.).

Project Time Management Processes

  • Various processes are used to manage time effectively in a project.
  • Processes include planning, controlling, developing the schedule, defining activities, sequencing activities, estimating activity durations, and estimating activity resources.

Project Time Management - Processes Breakdown

  • Planning schedule: Includes determining policies, procedures, and documentation for planning, executing, and controlling project schedules.
  • Defining activities: Identifying specific activities needed to deliver project deliverables from stakeholders and the project team.
  • Sequencing activities: Identifying and documenting relationships between project activities.
  • Estimating activity resources: Estimating the quantity of resources (people, equipment, and materials).
  • Estimating activity durations: Assessing work periods needed to complete activities.
  • Developing the schedule: Analyzing activity sequences, resource estimates, and duration estimates to develop the project schedule.
  • Controlling the schedule: Managing and controlling changes to the project schedule.

Schedule Management Plan

  • Project schedule mode: Contains project activities with estimated durations, dependencies, and planning information to create project schedules.
  • Level of accuracy and units of measure: Defining the accuracy requirements and time units (hours, days, etc.) for estimates.
  • Control thresholds: Establishing variance thresholds (e.g., ±10%) for monitoring schedule performance.
  • Rules of performance measurement: Specifying how team members track work completion percentages.
  • Reporting formats: Defining the format and frequency of schedule reports.
  • Process descriptions: Describing how all schedule management processes will be carried out.

Defining Activities

  • An activity or task is an element of work within a project's work breakdown structure (WBS).
  • Defining activities involves detailed WBS explanations to establish realistic cost and duration estimations.
  • These activities need resources, expected duration, and costs.

Activity Lists and Attributes

  • Activity lists tabulate activities to be included in project schedules.
  • Attributes include the activity name, identifier, description, predecessors, successors, logical relationships, leads/lags, resource requirements, constraints, dates, and assumptions related to the activity.

Sequencing Activities

  • Sequencing activities involves reviewing activities and dependencies.
  • A dependency or relationship sequences project activities or tasks.
  • Understanding dependencies is vital for critical path analysis.

Types of Dependencies

  • Mandatory dependencies: Inherent in the nature of the work, can't be performed until a prior step is complete (e.g., writing code before testing).
  • Discretionary dependencies: Defined by the project team based on good practices.
  • External dependencies: Involve relationships between the project and non-project activities, often involving external suppliers.

Task Dependency Types

  • Finish-to-Start (FS): Task B begins after Task A is finished.
  • Start-to-Start (SS): Task B begins simultaneously with Task A.
  • Finish-to-Finish (FF): Task B ends when Task A ends.
  • Start-to-Finish (SF): Task B ends after Task A has started.

Network Diagrams

  • Network diagrams graphically illustrate logical project activity relationships.
  • The preferred method of illustrating project activity sequencing.

Arrow Diagramming Method (ADM)

  • Also known as Activity-on-Arrow (AOA) network diagrams.
  • Activities are represented by arrows, and nodes represent starting/ending points.
  • ADM diagrams can only showcase finish-to-start dependencies.
  • An example of an AOA Network Diagram shows activities with durations, and node connections, illustrating activities and dependencies within a project.

Creating AOA Diagrams

  • Construct the diagram by identifying activities starting at node 1.
  • Indicate dependencies with arrows and include activity names/duration estimates.
  • Analyze for "bursts" (single node leading to multiple activities) and "merges" (multiple nodes uniting into a single activity).

Precedence Diagramming Method (PDM)

  • Activities shown as boxes.
  • Relationships shown via arrows connecting activities (predecessors, successors, etc.).
  • PDM is more popular than ADM. Preferred for illustrating various dependencies.

PDM Network Diagram

  • Visual example of how the precedence diagram method is represented for project activities, including task-names, and durations.

Estimating Activity Resources

  • Understanding resource quantities and types is crucial before duration estimations.
  • Crucial questions include activity difficulty, organizational history, material/resource availability, and potential needs for additional resources.

Estimating Activity Durations

  • Duration considers both work time and elapsed time.
  • Effort differentiates itself from duration and is measured in work days or hours.
  • Estimates created by those directly involved in activities should be reviewed by an expert.

Three-Point Estimates

  • This approach offers optimistic, most likely, and pessimistic estimates for a more nuanced understanding of task durations that is needed for PERT (Program Evaluation and Review Technique).

Schedule Development

  • Schedule development uses results from time management processes to determine project start and end dates.
  • The goal is to construct a realistic schedule that monitors progress.
  • Important tools include Gantt charts, critical path analysis, critical chain scheduling, and PERT analysis.

Gantt Charts

  • Standardized format for displaying project schedules, representing tasks and their start and finish dates in a calendar-based format.
  • Arrows indicate dependencies between tasks.
  • A Gantt chart example is provided, illustrating how tasks are linked and scheduled.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Untitled Quiz
6 questions

Untitled Quiz

AdoredHealing avatar
AdoredHealing
Untitled Quiz
37 questions

Untitled Quiz

WellReceivedSquirrel7948 avatar
WellReceivedSquirrel7948
Untitled Quiz
55 questions

Untitled Quiz

StatuesquePrimrose avatar
StatuesquePrimrose
Untitled Quiz
50 questions

Untitled Quiz

JoyousSulfur avatar
JoyousSulfur
Use Quizgecko on...
Browser
Browser