Questions and Answers
How many days will A take to complete the work alone?
How many days will A take to complete the work alone?
Study Notes
Work Rate Problem
- A and B together complete a work in 12 days.
- A works for the first 8 days, and B completes the remaining work in 18 days.
- The problem requires finding how many days A would take to complete the work alone.
- The correct answer is 30 days.
- The question involves calculating the portion of work done by A and B within their respective timeframes.
- The solution likely involves using the concept of work rate to determine how long A would take to complete the whole work alone.