Duncan is creating a WBS by having his team write tasks on sticky notes. Which of the following is Duncan using to create the WBS?
Duncan is creating a WBS by having his team write tasks on sticky notes. Which of the following is Duncan using to create the WBS?
- project baseline
- Gozinto chart (correct)
- FMEA chart
- Langley histogram
Which of the following is the most effective first step a project manager should take to create a Work Breakdown Structure (WBS)?
Which of the following is the most effective first step a project manager should take to create a Work Breakdown Structure (WBS)?
- Create a detailed Gantt chart outlining the project timeline.
- Define the project objectives and major activities required to achieve them. (correct)
- Assign tasks to specific team members based on their expertise.
- Estimate the time and resources needed for each task.
In project management, how would you describe the primary purpose of a Work Breakdown Structure (WBS)?
In project management, how would you describe the primary purpose of a Work Breakdown Structure (WBS)?
- To identify potential risks and develop mitigation strategies.
- To visually represent the project timeline and dependencies between tasks.
- To divide a large project into smaller, more manageable components. (correct)
- To assign tasks to team members and track their individual performance.
What is the most important reason for sequentially arranging tasks on a wall when constructing a Work Breakdown Structure (WBS)?
What is the most important reason for sequentially arranging tasks on a wall when constructing a Work Breakdown Structure (WBS)?
When using sticky notes to create a WBS, what is the MOST appropriate way to handle tasks that seem interconnected or dependent on each other?
When using sticky notes to create a WBS, what is the MOST appropriate way to handle tasks that seem interconnected or dependent on each other?
Once all tasks are written on sticky notes for a WBS, what is the MOST effective way to ensure no critical activities have been missed?
Once all tasks are written on sticky notes for a WBS, what is the MOST effective way to ensure no critical activities have been missed?
What is the MOST likely outcome of skipping the WBS creation step in project management?
What is the MOST likely outcome of skipping the WBS creation step in project management?
How could a project manager BEST use the WBS after it has been initially created and approved?
How could a project manager BEST use the WBS after it has been initially created and approved?
During the WBS creation process, a team member suggests adding a task that does not directly contribute to the project objectives. What would be the MOST appropriate course of action?
During the WBS creation process, a team member suggests adding a task that does not directly contribute to the project objectives. What would be the MOST appropriate course of action?
Imagine a project team is struggling to break down one of the work packages in their WBS into smaller, more manageable tasks. What technique could they apply?
Imagine a project team is struggling to break down one of the work packages in their WBS into smaller, more manageable tasks. What technique could they apply?
Flashcards
What method does Duncan use to create the WBS?
What method does Duncan use to create the WBS?
This question requires knowledge that can't be derived from the text. Therefore, I can't answer it.
Study Notes
- The question describes a scenario where Duncan, a project manager, uses sticky notes to create a work breakdown structure (WBS) for a new project.
- Duncan gathers the project team and provides them with sticky notes.
- The team defines project objectives and major activities.
- Team members write all the tasks required to complete the project on sticky notes.
- The notes are then stuck on a wall in a sequential manner.
- The answer explains the method used to create the WBS, but it does not mention FMEA charts, Langley histograms, project baselines or Gozinto charts.