3 Questions
Based on the given information, if 36 men can do a piece of work in 25 hours, how many men would be needed to do the same work in 15 hours?
18 men
If 15 men can do a piece of work in 25 hours, how many men would be needed to do the same work in 50 hours?
14 men
If 36 men can do a piece of work in 25 hours, how many hours would it take for 18 men to do the same work?
15 hours
Test your problem-solving skills with this quiz on work and time. Learn how to calculate the number of men needed to complete a task in a given time frame or determine the time required for a specific number of men to finish the work. Challenge yourself with different scenarios and improve your mathematical abilities.