Podcast
Questions and Answers
What is the minimum rail section required for turnouts on running loops?
What is the minimum rail section required for turnouts on running loops?
- 45 kg/m
- 60 kg/m
- 52 kg/m (correct)
- 40 kg/m
What is the sleeper density required on running loops?
What is the sleeper density required on running loops?
- 1700 Nos.per km
- 1540 Nos.per km (correct)
- 1400 Nos.per km
- 1200 Nos.per km
What is the permissible speed for 1 in 12 curved switch?
What is the permissible speed for 1 in 12 curved switch?
- 20 Kmph
- 30 Kmph
- 40 Kmph
- 50 Kmph (correct)
What type of switch is required on turnouts on running loops?
What type of switch is required on turnouts on running loops?
What is the minimum sleeper spacing required on turn-in curves?
What is the minimum sleeper spacing required on turn-in curves?
What is the purpose of providing extra shoulder ballast on the outside of the turn-in curve?
What is the purpose of providing extra shoulder ballast on the outside of the turn-in curve?
What is the purpose of welding rail joints on turnouts?
What is the purpose of welding rail joints on turnouts?
What is the minimum permissible speed on turnouts laid on PSC sleepers?
What is the minimum permissible speed on turnouts laid on PSC sleepers?
What is the purpose of the curve board provided at the tangent point of a curve?
What is the purpose of the curve board provided at the tangent point of a curve?
What is the purpose of the rail posts on the inside of the curve?
What is the purpose of the rail posts on the inside of the curve?
What is the special case of Super-elevation run out that may be approved?
What is the special case of Super-elevation run out that may be approved?
What is the typical color scheme used for the rail posts?
What is the typical color scheme used for the rail posts?
Where is the curve board typically placed?
Where is the curve board typically placed?
What information does the curve board provide?
What information does the curve board provide?
What is the purpose of the rail posts on the tangent track and on the circular curve?
What is the purpose of the rail posts on the tangent track and on the circular curve?
What type of curve is referred to when rail posts are erected on the tangent track and on the circular curve?
What type of curve is referred to when rail posts are erected on the tangent track and on the circular curve?
What is the cumulative spacing from SRJ at point 1?
What is the cumulative spacing from SRJ at point 1?
What is the spacing at point 20?
What is the spacing at point 20?
At which point does the spacing change from 600 to 550?
At which point does the spacing change from 600 to 550?
What is the cumulative spacing at point 15?
What is the cumulative spacing at point 15?
What is the spacing at point 10?
What is the spacing at point 10?
At which point does the cumulative spacing exceed 15000?
At which point does the cumulative spacing exceed 15000?
What is the cumulative spacing at point 5?
What is the cumulative spacing at point 5?
What is the spacing at point 2?
What is the spacing at point 2?
What is the purpose of keeping the original rail face as the base until the change is certain?
What is the purpose of keeping the original rail face as the base until the change is certain?
What should be recorded at every station where there are two or more lines?
What should be recorded at every station where there are two or more lines?
What is the basic principle of string lining which states that the sum total of the existing versines should be equal to the sum total of the proposed versines?
What is the basic principle of string lining which states that the sum total of the existing versines should be equal to the sum total of the proposed versines?
What is the effect of a slew in any direction at a station on the versine values at the adjacent stations?
What is the effect of a slew in any direction at a station on the versine values at the adjacent stations?
What does the second summation of versine difference between proposed versine and existing versine represent?
What does the second summation of versine difference between proposed versine and existing versine represent?
What should be the slew at the first and at the last station?
What should be the slew at the first and at the last station?
What is the purpose of selecting proposed versines in a certain way?
What is the purpose of selecting proposed versines in a certain way?
What should be calculated to obtain a realignment solution?
What should be calculated to obtain a realignment solution?
Why must the outer track be raised in a cross over road?
Why must the outer track be raised in a cross over road?
What is the minimum distance on either side of the diamond crossing where the cant should be uniformly run-out?
What is the minimum distance on either side of the diamond crossing where the cant should be uniformly run-out?
Why are speed restrictions imposed on the approach curve?
Why are speed restrictions imposed on the approach curve?
What is the minimum straight length required between the curve and the heel of acute crossing of diamond?
What is the minimum straight length required between the curve and the heel of acute crossing of diamond?
What is the purpose of providing extra clearance on curves?
What is the purpose of providing extra clearance on curves?
Why is compensation for curvature necessary?
Why is compensation for curvature necessary?
What is the maximum permissible speed over the diamond crossing?
What is the maximum permissible speed over the diamond crossing?
Who decides the speed restrictions on the approach curve?
Who decides the speed restrictions on the approach curve?
Study Notes
Up-gradation of Speeds on Turnouts and Loops to 30 Kmph
- Up-gradation of speeds on turnouts should cover a number of contiguous stations at a time to derive a perceptible advantage of the higher speed in train operation.
- Works described should cover all the running loops on the stretch of line taken up.
- Turnouts on the running loops should be laid with curved switches, with a minimum rail section of 52 kg/m.
- All rail joints on these turnouts should also be welded to the extent possible.
- Permissible speeds for different types of curved switches are:
- 1 in 8½ curved switch: 15 Kmph
- 1 in 8½ symmetrical split with curved switches: 30 Kmph
- 1 in 12 curved switch: 30 Kmph (50 Kmph for TWS)
- The minimum track structure on the running loops should be 52 kg/m rails laid as Short Welded Panels, sleeper density 1540 Nos. per km, and 150 mm clean ballast cushion.
- Proper drainage of the area should also be ensured.
Turn-in Curves
- Turn-in curves should be laid with the same rail section as on the turnout with PSC sleepers.
- Sleeper spacing should be 65 cm centre to centre (maximum).
- Turn-in curve should conform to Para 408(2) and especially so in respect of curvature of the lead curve.
- Extra shoulder ballast of 150 mm should be provided on outside of the turn-in curve.
Indicators/Boards Provided in Curves
- Each approach of a curve should be provided with a curve board at the tangent point fixed on the outside of the curve.
- The board should indicate the radius of the curve, the length of the curve, length of transition in metres, and the maximum cant provided on the circular portion of curve in millimetres.
- Rail posts indicating tangent points should be erected on each approach of the curve, to indicate the positions of the beginning and end of transition curves.
Curves with Diamond Crossing
- Straight diamond crossings should not be provided in curves as these produce kinks in the curve and uniform curvature cannot be obtained.
- Where provision of such diamonds cannot be avoided, the approach curves of these diamonds should be laid without cant for a distance of at least 20 metres on either side of the diamond crossings.
- The cant should be uniformly run-out at the rate specified in Para 405 beyond 20 metres.
Extra Clearance on Curves
- On curves, additional lateral clearances, in excess of the fixed dimensions, should be provided as laid down in the Schedule of Dimensions.
- Clearances should be provided between adjacent tracks and between curved track and fixed structure.
Compensation for Curvature on Gradient
- Compensation for curvature should be given in all cases where the existing gradient when added to the curve compensation exceeds the ruling gradient.
Realignment of Curves
- The basic principles of string lining are as follows:
- The chord length being identical, the sum total of the existing versines should be equal to the sum total of the proposed versines.
- The slew in any direction at a station affects the versine values at the adjacent stations by half the amount in the opposite direction, when the track is not disturbed at the adjacent stations.
- The second summation of versine difference between proposed versine and existing versine represents half the slew at any station.
- At the first and at the last station, the slews should be zero.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the up-gradation of speeds on turnouts and loops to 30 km/h, including the length of section, works, and speed permits. It's essential for train operation and infrastructure management.