Under UDCPR, in which areas can TDR be utilized?

  • Only municipal land
  • Buildable reservations, congested/non-congested areas (correct)
  • Forest land
  • Only restricted zones

Which formula is used to calculate TDR utilization?

  • $X = Y × ASR + \text{Plot area}$
  • $X = \frac{Rg}{Rr} × Y$ (correct)
  • $X = Rg + Rr$
  • $X = Y × \frac{Rr}{Rg}$

In the TDR utilization formula, what does ‘Rg’ stand for?

  • Road grade value
  • Rate of generator in kg
  • ASR rate of generating plot (correct)
  • Redevelopment guidelines

If Rg = ₹3000/sq.m., Rr = ₹6000/sq.m., and Y = 1200 sq.m., how much TDR can be used?

<p>600 sq.m. (C)</p> Signup and view all the answers

What is the minimum percentage of Slum/URT/Amenity TDR required in total TDR loading?

<p>30% (C)</p> Signup and view all the answers

What is the maximum percentage of Slum/URT/Amenity TDR allowed in total TDR loading?

<p>50% (D)</p> Signup and view all the answers

Which regulation specifies the TDR FSI limits?

<p>6.1, 6.2, 6.3 (C)</p> Signup and view all the answers

TDR can be used in plots affected by reservations. True or False?

<p>True (A)</p> Signup and view all the answers

Are infrastructure improvement charges required for using TDR?

<p>No (C)</p> Signup and view all the answers

If 1000 sq.m. TDR is generated from ₹4000/sq.m. land and used on land of ₹2000/sq.m., how much TDR can be utilized?

<p>2000 sq.m. (C)</p> Signup and view all the answers

Flashcards

TDR Utilization Areas

TDR can be utilized in buildable reservations and both congested and non-congested areas under UDCPR regulations.

TDR Utilization Formula

The formula to calculate TDR utilization is X = (Rg / Rr) × Y, where X is the TDR that can be used.

Meaning of 'Rg'

In the Transfer of Development Rights (TDR) utilization formula, 'Rg' stands for the ASR rate of the generating plot.

TDR Utilization Calculation

If Rg = ₹3000/sq.m., Rr = ₹6000/sq.m., and Y = 1200 sq.m., then X = (3000/6000) * 1200 = 600 sq.m. of TDR can be used.

Signup and view all the flashcards

Minimum Slum/URT/Amenity TDR

A minimum of 30% of Slum/URT/Amenity TDR is required in the total TDR loading.

Signup and view all the flashcards

Maximum Slum/URT/Amenity TDR

The maximum percentage of Slum/URT/Amenity TDR allowed in total TDR loading is 50%.

Signup and view all the flashcards

TDR FSI Limits Regulations

Regulations 6.1, 6.2, and 6.3 give the TDR FSI limits.

Signup and view all the flashcards

TDR Use in Reserved Plots

TDR can be used in plots affected by reservations.

Signup and view all the flashcards

Infrastructure Charges for TDR

Infrastructure improvement charges are not required for using TDR.

Signup and view all the flashcards

TDR Utilization Example

If 1000 sq.m. TDR is generated from ₹4000/sq.m. land and used on land of ₹2000/sq.m., then (4000/2000)*1000 means 2000 sq. m can be utilized.

Signup and view all the flashcards

Study Notes

  • Transfer of Development Rights (TDR) can be utilized in buildable reservations and in congested/non-congested areas as per UDCPR (Unified Development Control and Promotion Regulations).
  • The formula X = (Rg / Rr) × Y is used to calculate TDR utilization.
  • In the TDR utilization formula, 'Rg' stands for ASR (Annual Statement of Rates) rate of the generating plot.
  • If Rg = ₹3000/sq.m., Rr = ₹6000/sq.m., and Y = 1200 sq.m., then 600 sq.m. of TDR can be used.
  • The minimum percentage of Slum/URT/Amenity TDR required in total TDR loading is 30%.
  • The maximum percentage of Slum/URT/Amenity TDR allowed in total TDR loading is 50%.
  • Regulations 6.1, 6.2, and 6.3 dictate the TDR FSI (Floor Space Index) limits.
  • TDR can be used in plots affected by reservations.
  • Infrastructure improvement charges are not required for using TDR.
  • If 1000 sq.m. TDR is generated from ₹4000/sq.m. land and used on land of ₹2000/sq.m., then 2000 sq.m. of TDR can be utilized.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

More Like This

Use Quizgecko on...
Browser
Browser