Time Boxing in Atern Methodology
12 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the aim of the Kick-off in the Timebox process?

  • Focus on development and testing of timebox products
  • Ensure all dependencies on other teams are understood
  • Conduct a detailed investigation of product details
  • Review the timebox objectives and agree on acceptance criteria (correct)

Who should attend the Kick-off in a Timebox?

  • Only the Business Visionary
  • Only the Technical Co-ordinator
  • All Solution Development Team members, Project Manager, Technical Co-ordinator, and Business Visionary if needed (correct)
  • Only the Project Manager

During the Investigation Iteration, what should the Solution Developers and Business Ambassadors jointly do?

  • Create a detailed product description
  • Focus on creating a high-level prototype
  • Work together on the full set of requirements agreed in the Kick-off (correct)
  • Conduct a detailed risk analysis

What percentage of the total timebox duration is typically allocated to the Kick-off?

<p>$10-20 ext{%}$ (D)</p> Signup and view all the answers

What should be done if detailed agreement on acceptance criteria cannot be reached during the Kick-off?

<p>Defer agreement to the end of the Investigation iteration (B)</p> Signup and view all the answers

What is a key aspect that should be analyzed during the Kick-off in relation to team members' availability?

<p>Ensuring fixed minimum resource levels are committed to delivery (C)</p> Signup and view all the answers

What is the purpose of timeboxing in Atern?

<p>To control the creation of low-level products in an iterative fashion (B)</p> Signup and view all the answers

What are the main stages within a Timebox?

<p>Investigation, Refinement, Consolidation (D)</p> Signup and view all the answers

How does MoSCoW prioritization contribute to Timeboxing?

<p>It defines what must be achieved within the Timebox (D)</p> Signup and view all the answers

What is the purpose of the Kick-off meeting in a Timebox?

<p>To officially start the Timebox (B)</p> Signup and view all the answers

What is the significance of continual re-assessment in Timeboxing?

<p>To confirm the feasibility of completing tasks within the agreed timeframe (A)</p> Signup and view all the answers

How does controlling on-time delivery at low levels help at higher levels?

<p>It guarantees on-time delivery of high-level products (D)</p> Signup and view all the answers

More Like This

Time of Day Flashcards
13 questions

Time of Day Flashcards

GlisteningRadon avatar
GlisteningRadon
Unit 1 Lesson 3 Time Management Quiz
10 questions
FRQ #3 - Time-Space Convergence
4 questions
Use Quizgecko on...
Browser
Browser