Podcast
Questions and Answers
A and B can complete a task in 15 and 10 days respectively. If they collaborate for 4 days, what fraction of the task remains incomplete?
A and B can complete a task in 15 and 10 days respectively. If they collaborate for 4 days, what fraction of the task remains incomplete?
- 1/4
- 1/2
- 2/5
- 1/3 (correct)
A can complete a task alone in 4 hours. B and C together can complete it in 3 hours, while A and C together take 2 hours. How many hours would B take to complete the task alone?
A can complete a task alone in 4 hours. B and C together can complete it in 3 hours, while A and C together take 2 hours. How many hours would B take to complete the task alone?
- 24 hours
- 8 hours
- 12 hours (correct)
- 6 hours
A is 150% more efficient than B. If B alone completes a task in 20 days, how many days will A take to complete the same task?
A is 150% more efficient than B. If B alone completes a task in 20 days, how many days will A take to complete the same task?
- 5 days
- 10 days
- 12 days
- 8 days (correct)
A can complete a task in 15 days, while B can complete it in 10 days. They agree to a contract of RS 30,000 for the task. What is A's share, assuming payment is proportional to work done?
A can complete a task in 15 days, while B can complete it in 10 days. They agree to a contract of RS 30,000 for the task. What is A's share, assuming payment is proportional to work done?
A takes 6 days less than B to complete a task. Working together, A and B can complete the same task in 4 days. How many days will B alone take to complete the task?
A takes 6 days less than B to complete a task. Working together, A and B can complete the same task in 4 days. How many days will B alone take to complete the task?
A, B, and C have efficiencies in the ratio of 2:3:5. A alone can complete a task in 50 days. If A works for 15 days, how long will it take A and B working together to complete the remaining work?
A, B, and C have efficiencies in the ratio of 2:3:5. A alone can complete a task in 50 days. If A works for 15 days, how long will it take A and B working together to complete the remaining work?
If efficiency is doubled, how is the time to complete a specific amount of work affected?
If efficiency is doubled, how is the time to complete a specific amount of work affected?
A and B working separately can do a piece of work in 18 days. What portion of the work they can do together in 1 day?
A and B working separately can do a piece of work in 18 days. What portion of the work they can do together in 1 day?
A, B and C can complete a task in 20, 30 and 60 days respectively. How long will A and C take to do the task together?
A, B and C can complete a task in 20, 30 and 60 days respectively. How long will A and C take to do the task together?
A can complete a task in 6 days and B in 9 days. If they work together, how long will they take to complete it?
A can complete a task in 6 days and B in 9 days. If they work together, how long will they take to complete it?
Flashcards
Work Formula
Work Formula
Work is the product of efficiency and time.
Efficiency Definition
Efficiency Definition
Efficiency is the amount of work someone does in a unit of time.
Inverse Proportionality Formula
Inverse Proportionality Formula
When two quantities vary inversely, the ratio of their initial values equals the inverse ratio of their final values.
Steps to Solve Time and Work Problems
Steps to Solve Time and Work Problems
Signup and view all the flashcards
Efficiency Percentage
Efficiency Percentage
Signup and view all the flashcards
Wage Share Principle
Wage Share Principle
Signup and view all the flashcards
Study Notes
- Work = Efficiency * Time.
- Efficiency represents the amount of work done by an individual in a single day.
- Efficiency is determined by the formula: Work / Time.
- Time is calculated as: Work / Efficiency.
- Efficiency and Time are inversely proportional.
- For inversely proportional quantities, use: E1/E2 = T2/T1.
- Focus on finding efficiency to solve time and work problems.
Approach to solving problems:
- Prioritize finding the efficiency of each worker or group.
- If A takes 4 days and B takes 3 days to complete a task:
- Determine the total work by finding the least common multiple (LCM) of 4 and 3.
- Calculate A's one-day work by dividing the total work by A's time.
- Calculate B's one-day work by dividing the total work by B's time.
Example problem 1
- A can complete work in 6 days, B can complete it in 9 days.
- If A and B work together, how long will it take to complete the work?
- A's time = 6 days.
- B's time = 9 days.
- Total work = LCM(6, 9) = 18 units.
- A's one-day work (efficiency) = 18/6 = 3 units.
- B's one-day work (efficiency) = 18/9 = 2 units.
- A + B's combined one-day work = 3 + 2 = 5 units.
- Time for A & B together = Total work / combined efficiency = 18/5 = 3.6 days.
Example problem 2
- A, B, and C can complete a piece of work in 20, 30, and 60 days respectively.
- How long will A and C take to complete the work together?
- A's time = 20 days, B's time = 30 days, C's time = 60 days.
- Total work = LCM(20, 30, 60) = 60 units.
- A's efficiency = 60/20 = 3 units/day.
- B's efficiency = 60/30 = 2 units/day.
- C's efficiency = 60/60 = 1 unit/day.
- A and C working together:
- A+C efficiency = 3+1 = 4 units/day.
- Time to complete = 60/4 = 15 days.
Example problem 3
- A and B can complete a piece of work in 15 and 10 days respectively.
- They work together for 4 days. What fraction of the work is left incomplete?
- A's time = 15 days, B's time = 10 days.
- Total work = LCM(15, 10) = 30 units.
- A's efficiency = 30/15 = 2 units/day.
- B's efficiency = 30/10 = 3 units/day.
- A+B efficiency = 2+3 = 5 units/day.
- Work done in 4 days = 5 * 4 = 20 units.
- Work left = 30 - 20 = 10 units.
- Fraction of work left = 10/30 = 1/3.
Example problem 4
- A can finish a piece of work in 18 days, and B can also do it in 18 days. How much of the work can they finish together in one day?
- A's time = 18 days, B's time = 18 days.
- Total work = 18 units (LCM).
- A's efficiency = 18/18 = 1 unit/day.
- B's efficiency = 18/18 = 1 unit/day.
- Combined efficiency = 1+1 = 2 units/day.
- Work done together in one day is 2 out of 18 = 2/18 = 1/9.
Example problem 5
- A and B can do a piece of work in 12 days, B and C in 16 days, and A and C in 24 days. How much time will A, B, and C take to do the work together?
- A+B time = 12, B+C time = 16, C+A time = 24.
- Total work = LCM(12, 16, 24) = 48 units.
- Efficiency: A+B=4, B+C=3, C+A=2.
- Adding all efficiencies: 2(A+B+C)=9, so A+B+C=4.5.
- Time for A, B, C working together = 48/4.5 = 10.67 days.
- To find the time for C alone:
- C = (A+B+C) - (A+B) = 4.5 - 4 = 0.5 Efficiency
- C Time = 48 / 0.5 = 96 days
Example problem 6
- A can complete a piece of work in 4 hours. B and C can do it in 3 hours, and A and C can do it in 2 hours. How long will it take for B alone to complete the work?
- A: 4 hours, B+C: 3 hours, A+C: 2 hours
- Total Work = LCM (4, 3, 2) = 12
- Efficiencies: A = 3, B+C = 4, A+C = 6
- C = (A+C) - A = 6 - 3 = 3
- B = (B+C) - C = 4 - 3 = 1
- B Time = 12 / 1 = 12 hours
Example problem 7
- A can complete a piece of work in 6 days, while B takes 12 days to complete the same work. If they work together, what portion of the work has A completed.
- A finishes in 6 days, B finishes in 12 days.
- Total work = LCM(6, 12) = 12.
- A's efficiency = 2, B's efficiency = 1.
- A and B working together finish in 4 days (12 / (2 + 1)).
- Portion of work done by A = 8/12 = 2/3.
Example problem 8
- A is 150% more efficient than B, and B alone completes the work in 20 days. How long will it take A to do the same work?
- A = 2.5B
- Work = Efficiency * Time
- 20 = B Time
- T = W / E
- 100 / 250 = 0.4 * 20 = 8
- Time that A takes = 8 days.
Example problem 9
- A can complete work in 15 days, and B can complete it in 10 days. They have a contract worth RS 30,000. What is A's share. Note that the share ratio is dependent on efficiency share.
- A can complete work in 15 days, B can complete in 10 days.
- Total Work = LCM(15, 10) = 30.
- A's efficiency = 2, B's efficiency = 3.
- A/(A + B) = 2 / 5 = 0.4
- Share of A = 0.4 * 30000 = 12000
Example problem 10
- A takes 6 days less than B to complete a work. A and B together take 4 days. How many days does B alone take?
- Let B alone = X, A = X-6.
- A and B together take 4 days
- Eq is X^2-14x+24=0
- Need Quad Eq
- B == 12
Example problem 11
- The efficiencies of A, B, and C are in the ratio 2:3:5. A alone takes 50 days to complete the work. If A works for 15 days, how long will A and B take to complete the remaining work?
- Total Work -- -A = 2. 50 = 1--Share
- A, B, C: 2:3:5
- Efficiency = 10
- Rem = 75 left. and A+B=5 --Rem
- A and together ==15
Example problem 12
- Six Times BE
- More BE
- B: 32 A: time
- BE = 1
- M = 32 A Share Total
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.