Questions and Answers

What is the minimum percentage of TDR that can be utilized under the Slum Rehabilitation Scheme?

  • 20%
  • 25%
  • 30% (correct)
  • 50%

What percentage does the premium FSI rate represent of the land value mentioned in the Annual Statement of Rates?

  • 35% (correct)
  • 50%
  • 75%
  • 25%

For unauthorized subdivisions of plots up to 0.4 hectares, what is the combined FSI limit?

  • 60%
  • 100%
  • 50%
  • 75% (correct)

What is the maximum road length allowed for TDR utilization in plots with dead-end road access?

<p>100 m (D)</p> Signup and view all the answers

Basic FSI is calculated based on which of the following?

<p>Area remaining after deducting DP road and amenity space (A)</p> Signup and view all the answers

Under which regulation is TDR allowance provision mentioned for plots regularized under the Maharashtra Gunthewari Development Act?

<p>Regulation No. 3.4.1 (A)</p> Signup and view all the answers

What is the required road width for full potential utilization of TDR?

<p>9 m (C)</p> Signup and view all the answers

If a plot is regularized under the Maharashtra Gunthewari Development Act, what is the limit for TDR?

<p>50% (C)</p> Signup and view all the answers

According to municipal regulations, what is the strip width that must be handed over for road widening?

<p>4.5 m (D)</p> Signup and view all the answers

What does the premium FSI rate calculation exclude?

<p>Guidelines under Annual Statement of Rates (B)</p> Signup and view all the answers

What is the maximum permissible FSI for a road width of 18 meters?

<p>3.5 (C)</p> Signup and view all the answers

What premium rate applies to IT parks in a CBD area?

<p>25% (C)</p> Signup and view all the answers

For an IT park in No Development Zone, the additional FSI over basic FSI can be increased up to:

<p>200% (B)</p> Signup and view all the answers

What is the minimum road width required for availing FSI above 100% in any zone?

<p>18 meters (B)</p> Signup and view all the answers

Which type of park is included under the AVGC category?

<p>Animation Parks (A)</p> Signup and view all the answers

What is the maximum FSI permissible on a road with a width of 27 meters?

<p>4 (C)</p> Signup and view all the answers

Which authority can permit additional FSI for IT/ITES units?

<p>Municipal Corporation (A)</p> Signup and view all the answers

In which area does the premium rate rise to 25% for IT parks?

<p>CBD Area (B)</p> Signup and view all the answers

What is the basic FSI for a 12-meter-wide road?

<p>Up to 2 (D)</p> Signup and view all the answers

The term SEZ stands for:

<p>Special Economic Zone (D)</p> Signup and view all the answers

Flashcards

Minimum TDR for Slum Rehabilitation

30% of the Total Development Rights (TDR) can be utilized under the Slum Rehabilitation Scheme.

Premium FSI Rate

The premium FSI rate is 35% of the land value per the Annual Statement of Rates.

Combined FSI for Unauthorized Subdivisions (0.4 ha)

The combined Floor Space Index (FSI) for unauthorized subdivisions up to 0.4 hectares is limited to 75%.

Maximum Road Length for Dead-End TDR

The maximum road length that allows TDR utilization in plots with dead-end road access is 100 meters.

Signup and view all the flashcards

Basic FSI Calculation

Basic FSI is calculated based on the plot area remaining after subtracting Development Plan (DP) roads and amenity spaces.

Signup and view all the flashcards

TDR Allowance for Maharashtra Gunthewari

For plots regularized under the Maharashtra Gunthewari Development Act, TDR allowance is mentioned in Regulation No. 3.4.1.

Signup and view all the flashcards

Road Width for Full TDR Utilization

A road width of 9 meters is required for the full potential utilization of TDR.

Signup and view all the flashcards

TDR Limit for Gunthewari Regularization

The TDR limit for plots regularized under the Maharashtra Gunthewari Development Act is 50%.

Signup and view all the flashcards

Road Widening Strip Width

The strip width a plot owner needs to hand over for road widening is 4.5 meters as per municipal regulations.

Signup and view all the flashcards

Premium FSI Exclusion

The calculation of the premium FSI rate excludes guidelines provided by the Annual Statement of Rates.

Signup and view all the flashcards

FSI on 18 meter road

The maximum Floor Space Index (FSI) allowed on a road with a width of 18 meters is 3.5.

Signup and view all the flashcards

IT Park Premium in CBD

IT parks located in Central Business Districts (CBDs) have a premium FSI rate of 25%.

Signup and view all the flashcards

FSI in No Development Zone

In No Development Zones, IT parks can get an additional FSI up to 200% of the basic FSI.

Signup and view all the flashcards

Road width for FSI > 100%

A minimum road width of 18 meters is necessary to avail FSI exceeding 100% in any zone.

Signup and view all the flashcards

AVGC Park

Animation Parks fall under the category of AVGC (Animation, Visual Effects, Gaming, and Comics).

Signup and view all the flashcards

FSI on 27 meter road

The maximum permissible FSI on a road with a width of 27 meters is 4.

Signup and view all the flashcards

FSI for IT/ITES

Municipal Corporations have the authority to permit additional FSI for IT/ITES units.

Signup and view all the flashcards

25% Premium for IT Park

IT parks in Central Business Districts (CBDs) have a premium FSI rate of 25%.

Signup and view all the flashcards

Basic FSI on 12 meter road

A 12-meter wide road allows a basic FSI of up to 2.

Signup and view all the flashcards

SEZ stands for

SEZ stands for Special Economic Zone, offering special economic policies.

Signup and view all the flashcards

Study Notes

TDR Utilization Regulations

  • Slum Rehabilitation Scheme: Minimum TDR utilization is 30%.
  • Premium FSI: The premium FSI rate is 35% of the land value as mentioned in the Annual Statement of Rates.
  • Unauthorized Subdivisions (0.4 hectares): Combined FSI is limited to 75%.
  • Dead-End Road Access: Maximum road length for TDR utilization is 100 meters.
  • Basic FSI Calculation: Based on the area remaining after deducting Development Plan (DP) road and amenity space.
  • Maharashtra Gunthewari Development Act: TDR allowance is mentioned in Regulation No. 3.4.1.
  • Full TDR Utilization Road Width: A road width of 9 meters is needed.
  • Maharashtra Gunthewari TDR Limit: 50% TDR is allowed for plots regularized under the Maharashtra Gunthewari Development Act.
  • Road Widening Strip Width: 4.5 meters.
  • Premium FSI Exclusion: The calculation excludes guidelines from the Annual Statement of Rates.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Description

Test your knowledge on TDR utilization regulations in Maharashtra. This quiz covers key aspects such as minimum utilization, premium FSI rates, and specific regulations under the Gunthewari Development Act. Perfect for urban planners and real estate professionals!