Which method involves defining tasks and milestones, linking tasks in sequence, and assigning time estimates for completion?

  • CPM
  • Dependency Network
  • Critical Path
  • PERT (correct)

Which method is a graphical representation of the dependency network for an entire project?

  • PERT (correct)
  • Dependency Network
  • Critical Path
  • CPM

What is the weakness of PERT?

  • The time estimates for completing each task are not precise (correct)
  • It is difficult to assign time estimates for each task
  • The method is not suitable for construction projects
  • The method is too complex to implement

Which method uses arrows or lines to graphically demonstrate the relationships between activities?

<p>CPM (C)</p> Signup and view all the answers

What is the term used to describe the delay capacity in a project scheduling using CPM?

<p>Float (B)</p> Signup and view all the answers

Which of the following is a limitation of the milestone chart method of scheduling?

<p>It does not show relationships between activities. (D)</p> Signup and view all the answers

What is the main advantage of using a Gantt diagram for scheduling?

<p>It is visually clear and easy to use. (D)</p> Signup and view all the answers

Which method of scheduling is commonly used for bidding and simple projects with a linear implementation?

<p>Milestone chart (C)</p> Signup and view all the answers

What is the purpose of project schedules?

<p>To monitor tasks until the project is complete. (A)</p> Signup and view all the answers

What must a project manager consider when selecting a scheduling method?

<p>The scale and complexity of the work. (B)</p> Signup and view all the answers

Which of the following is referred to as float time in the context of project scheduling?

<p>Tasks that can be delayed without affecting the project completion date (A)</p> Signup and view all the answers

In the CPM procedure, what is the purpose of determining critical paths?

<p>To identify tasks that will affect the project completion date if delayed (A)</p> Signup and view all the answers

How can critical tasks be determined for projects with fewer than 100 tasks?

<p>By graphic inspection (D)</p> Signup and view all the answers

What is the purpose of developing a network schedule in project management?

<p>To visualize the sequence and dependencies of project tasks (D)</p> Signup and view all the answers

What does Illustration A-4 in the Canadian Handbook of Practice for Architects show?

<p>The critical tasks for four two-task project examples (B)</p> Signup and view all the answers

Which task cannot begin until task C2 (preliminary design) is partially completed?

<p>Task C3 (C)</p> Signup and view all the answers

What is the length of time required for an activity to be completed assuming all prerequisite tasks have been completed?

<p>Optimum duration (D)</p> Signup and view all the answers

Which task is scheduled to extend 60 days beyond completion of all other tasks?

<p>Task H (D)</p> Signup and view all the answers

What is the purpose of the vertical arrow in the network schedule?

<p>To show that task B cannot begin until task A is completed (D)</p> Signup and view all the answers

What is the additional time required to complete task B in the third example?

<p>11 days (B)</p> Signup and view all the answers

True or false: The methods shown in the examples can be used to develop a network schedule.

<p>True (A)</p> Signup and view all the answers

True or false: The last step in the CPM procedure is to determine the critical paths.

<p>True (A)</p> Signup and view all the answers

True or false: The critical tasks are the ones that will affect the project completion date if any delay occurs.

<p>True (A)</p> Signup and view all the answers

True or false: For projects with fewer than 100 tasks, the critical tasks can be determined by graphic inspection.

<p>True (A)</p> Signup and view all the answers

True or false: Illustration A-4 in the Canadian Handbook of Practice for Architects shows the critical tasks for each of the four two-task project examples.

<p>False (B)</p> Signup and view all the answers