Questions and Answers

Which method involves defining tasks and milestones, linking tasks in sequence, and assigning time estimates for completion?

  • CPM
  • Dependency Network
  • Critical Path
  • PERT (correct)
  • Which method is a graphical representation of the dependency network for an entire project?

  • PERT (correct)
  • Dependency Network
  • Critical Path
  • CPM
  • What is the weakness of PERT?

  • The time estimates for completing each task are not precise (correct)
  • It is difficult to assign time estimates for each task
  • The method is not suitable for construction projects
  • The method is too complex to implement
  • Which method uses arrows or lines to graphically demonstrate the relationships between activities?

    <p>CPM</p> Signup and view all the answers

    What is the term used to describe the delay capacity in a project scheduling using CPM?

    <p>Float</p> Signup and view all the answers

    Which of the following is a limitation of the milestone chart method of scheduling?

    <p>It does not show relationships between activities.</p> Signup and view all the answers

    What is the main advantage of using a Gantt diagram for scheduling?

    <p>It is visually clear and easy to use.</p> Signup and view all the answers

    Which method of scheduling is commonly used for bidding and simple projects with a linear implementation?

    <p>Milestone chart</p> Signup and view all the answers

    What is the purpose of project schedules?

    <p>To monitor tasks until the project is complete.</p> Signup and view all the answers

    What must a project manager consider when selecting a scheduling method?

    <p>The scale and complexity of the work.</p> Signup and view all the answers

    Which of the following is referred to as float time in the context of project scheduling?

    <p>Tasks that can be delayed without affecting the project completion date</p> Signup and view all the answers

    In the CPM procedure, what is the purpose of determining critical paths?

    <p>To identify tasks that will affect the project completion date if delayed</p> Signup and view all the answers

    How can critical tasks be determined for projects with fewer than 100 tasks?

    <p>By graphic inspection</p> Signup and view all the answers

    What is the purpose of developing a network schedule in project management?

    <p>To visualize the sequence and dependencies of project tasks</p> Signup and view all the answers

    What does Illustration A-4 in the Canadian Handbook of Practice for Architects show?

    <p>The critical tasks for four two-task project examples</p> Signup and view all the answers

    Which task cannot begin until task C2 (preliminary design) is partially completed?

    <p>Task C3</p> Signup and view all the answers

    What is the length of time required for an activity to be completed assuming all prerequisite tasks have been completed?

    <p>Optimum duration</p> Signup and view all the answers

    Which task is scheduled to extend 60 days beyond completion of all other tasks?

    <p>Task H</p> Signup and view all the answers

    What is the purpose of the vertical arrow in the network schedule?

    <p>To show that task B cannot begin until task A is completed</p> Signup and view all the answers

    What is the additional time required to complete task B in the third example?

    <p>11 days</p> Signup and view all the answers

    True or false: The methods shown in the examples can be used to develop a network schedule.

    <p>True</p> Signup and view all the answers

    True or false: The last step in the CPM procedure is to determine the critical paths.

    <p>True</p> Signup and view all the answers

    True or false: The critical tasks are the ones that will affect the project completion date if any delay occurs.

    <p>True</p> Signup and view all the answers

    True or false: For projects with fewer than 100 tasks, the critical tasks can be determined by graphic inspection.

    <p>True</p> Signup and view all the answers

    True or false: Illustration A-4 in the Canadian Handbook of Practice for Architects shows the critical tasks for each of the four two-task project examples.

    <p>False</p> Signup and view all the answers