What is the main objective of Load Flow Analysis under normal conditions?
Assess steady state loading and voltage profile
When conducting load flow studies, what are the two cases that should be considered?
Maximum and minimum plant output
What is one of the conditions for which load flow studies should be conducted?
Normal operation
What type of studies are carried out in Grid Interconnection Studies?
Steady-state studies
What is the purpose of the contingency analysis mentioned in the text?
To assess system compliance with N-1 criteria after plant connection to the Transmission System.
What aspect of the system is considered during the contingency analysis?
All transmission lines and step-up transformers directly connected to the plant.
In sudden voltage variations analysis, what is the limit for voltage change caused by switching a PV plant mentioned in the text?
Not larger than 5% of Umax
Why is it necessary to assess sudden voltage variations as part of grid interconnection studies?
To ensure compliance with Grid Code Requirements.
What is the focus of grid interconnection studies based on the text provided?
Studying how a power plant connects with the grid and analyzing its impact.