During the design development phase, the mechanical engineer selects equipment for and resolves
During the design development phase, the mechanical engineer selects equipment for and resolves
- Electrical issues related to the building
- Landscape issues related to the building
- Mechanical issues related to the building (correct)
- Structural issues related to the building
What information does the electrical engineer require to carry out the design development documents?
What information does the electrical engineer require to carry out the design development documents?
- Mechanical information
- Electrical information (correct)
- Structural information
- Municipal services and site systems information
What is the role of a landscape architect in the design development stage?
What is the role of a landscape architect in the design development stage?
- To select and resolve mechanical issues
- To provide conceptual thoughts about landscaping aspects (correct)
- To coordinate the activities of the engineering disciplines
- To design lighting layouts
What type of information does the civil engineer require to carry out the design development documents?
What type of information does the civil engineer require to carry out the design development documents?
What is the purpose of energy modeling in the design development phase?
What is the purpose of energy modeling in the design development phase?
Who is responsible for coordinating the activities of the engineering disciplines in the design development stage?
Who is responsible for coordinating the activities of the engineering disciplines in the design development stage?
During which phase of a project should the architect maintain contact with authorities having jurisdiction?
During which phase of a project should the architect maintain contact with authorities having jurisdiction?
When is it typically required for documents submitted for a building permit to be sealed by the architect of record?
When is it typically required for documents submitted for a building permit to be sealed by the architect of record?
What is the purpose of preparing an updated estimate of the construction cost during design development?
What is the purpose of preparing an updated estimate of the construction cost during design development?
What do design development documents describe and 'finalize' for the remaining project efforts?
What do design development documents describe and 'finalize' for the remaining project efforts?
What should the drawings produced at the design development stage provide adequate information for?
What should the drawings produced at the design development stage provide adequate information for?
What does an outline specification in the design development phase describe?
What does an outline specification in the design development phase describe?
During which phase of the design project are detailed technical analysis and the building information modeling (BIM) process often required?
During which phase of the design project are detailed technical analysis and the building information modeling (BIM) process often required?
What is the main focus of the schematic design phase?
What is the main focus of the schematic design phase?
Which phase of the design project is often associated with obtaining planning approvals?
Which phase of the design project is often associated with obtaining planning approvals?
What is the term used to describe the combination of the schematic design and design development phases into a single phase?
What is the term used to describe the combination of the schematic design and design development phases into a single phase?
What has changed the division of effort and scope of deliverables in the early phases of the design project?
What has changed the division of effort and scope of deliverables in the early phases of the design project?
Why is the design development phase sometimes difficult to differentiate from the schematic design phase?
Why is the design development phase sometimes difficult to differentiate from the schematic design phase?
Which stakeholders may have access to the design development report?
Which stakeholders may have access to the design development report?
Which of the following is a purpose of the design development report?
Which of the following is a purpose of the design development report?
Which report provides information about the process of the design project?
Which report provides information about the process of the design project?
What risks to the project may be addressed in the design development report?
What risks to the project may be addressed in the design development report?
What should be included in the design development report's executive summary section?
What should be included in the design development report's executive summary section?
In which phase of the design project should the design development report be provided to the client?
In which phase of the design project should the design development report be provided to the client?
During the design development phase, the architect's role includes investigating various construction materials, products, systems, and manufactured products for incorporation into the future building. What factors should the architect consider when assessing these materials?
During the design development phase, the architect's role includes investigating various construction materials, products, systems, and manufactured products for incorporation into the future building. What factors should the architect consider when assessing these materials?
What is the purpose of developing a statement of work for each phase of the design project with clearly defined deliverables?
What is the purpose of developing a statement of work for each phase of the design project with clearly defined deliverables?
When does the project move into the construction documentation phase?
When does the project move into the construction documentation phase?
What is the architect's responsibility during the design development phase in terms of coordination with the consultant team?
What is the architect's responsibility during the design development phase in terms of coordination with the consultant team?
What does the term 'design' mean when used by architects?
What does the term 'design' mean when used by architects?
Why is it strategic to obtain initial approval of the early concept from the client before proceeding to more specific design details?
Why is it strategic to obtain initial approval of the early concept from the client before proceeding to more specific design details?