30 Questions
Which of the following is NOT a new role created because of BIM implementation?
Data Analyst
What is the responsibility of the System Integrator in the context of BIM implementation?
Managing the integration of systems across the design-construction supply chain
What impact does BIM implementation have on human resources and training?
Requires reorganization of processes
Which of the following is NOT mentioned as an operational system impacted by BIM implementation?
Financial management
What are two new roles mentioned in the passage that are foundational to BIM implementation?
Systems Integrator and BIM Manager
Which of the following is NOT a category of training and office support mentioned in the text?
Continuing education
What is the purpose of conducting audits during and following the implementation of the BIM learning process?
To identify areas for improvement in performance
According to the text, what is the first step in the process of developing an education program?
Evaluating the firm's strategic plan
What is the role of a project manager in the development of a training program?
To assign staff members to different projects
According to the text, when is a training program most effective?
When conducted in parallel with current need
Which of the following is NOT a connectivity option for data exchange in a distributed project team?
Wide area network (WAN)
What are the advantages of cloud-based networking and services according to the CPMB?
Agility, cost, access, reliability, and scalability
Which of the following is NOT a characteristic of organizational culture?
Technology
What is the challenge for an organization operating in a dynamic and complex context?
Adapting the firm's culture
Which concepts reinforce boundaries and separation in the design-construction sector?
Regulation, discipline knowledge, and liability risk management
According to the text, what are the responsibilities of the System Integrator in a BIM environment?
All of the above
What is the role of the BIM Manager in a project?
Enforcing policies controlling viewing, editing, merging, and releases of the master model
What skills should be considered when recruiting design team members for a collaborative BIM environment?
All of the above
What is the purpose of a BIM training program?
All of the above
What does the development phase of a BIM training program involve?
All of the above
Which of the following is the primary purpose of a BIM Execution Plan (BxP)?
To act as a planning and management tool for BIM-enabled projects
According to the text, what is the relationship between the IBC Contract Appendix and the BIM Execution Plan (BxP)?
The IBC Contract Appendix has a direct relationship to the BxP
When should a BxP be updated?
All of the above
Who typically takes the lead on developing the BxP?
The architect
What is the primary purpose of BIM use in the context of project goals?
To reduce RFIs and changes during construction
Which of the following is a financial consideration when selecting software?
The availability of annual subscription options
According to Moore's Law, how often does computing power double?
Every two years
What is openBIM?
A universal approach to collaborative design based on open standards
What drives the functionality of a hardware system?
The processing capacity
What is a key consideration for communications and collaborative technology platforms?
The bandwidth of the communication infrastructure
Take this quiz to test your knowledge on software licensing options. Learn about the differences between subscription and perpetual licenses and understand the financial considerations involved in selecting a software suite.