What is the purpose of increasing the rate of continuous blowdown and bottom blowoff several days before shutting down the boiler?

  • To reduce the frequency of bottom blowoff
  • To discharge sediment and sludge that may have accumulated in the boiler (correct)
  • To decrease the rate of make-up water
  • To increase the pressure inside the boiler
  • What action should be taken if the flame is unusually smoky, asymmetrical, or impinging on boiler surfaces?

  • Increase the fuel supply to the burner
  • Continue operating the boiler as usual
  • Employ a certified burner service technician to adjust the burner (correct)
  • Reduce the rate of continuous blowdown
  • Which control should be tested during the shutdown procedure to ensure safety?

  • High-pressure steam cut-off
  • Low water cut-off (correct)
  • Temperature control
  • Combination feeder/cut-off control or pump control
  • What is the purpose of transferring load to other operating boilers during a shutdown?

    <p>To test safety interlocks without interrupting production</p> Signup and view all the answers

    Why is it important to adjust the chemical feed rates before shutting down the boiler?

    <p>To accommodate an increase in make-up water</p> Signup and view all the answers

    What is the purpose of observing the flame for irregularity before shutting down a boiler?

    <p>To ensure proper combustion and prevent damage to boiler surfaces</p> Signup and view all the answers

    What should be done with the low water cut-off during a boiler shutdown procedure?

    <p>Tested to ensure proper operation</p> Signup and view all the answers

    What could happen if irregularities in the flame are not addressed before returning a boiler to service?

    <p>Increased risk of damage to boiler surfaces</p> Signup and view all the answers

    What impact does increasing make-up water have on the boiler before shutdown?

    <p>'Dilutes' the chemical content in the boiler water</p> Signup and view all the answers

    Why is it important to test all operating and limit controls during a boiler shutdown procedure?

    <p>To validate proper operation and safety.</p> Signup and view all the answers

    What is the purpose of performing a safety valve pop test during the shutdown of a boiler?

    <p>To check the performance of the safety valves under operating conditions</p> Signup and view all the answers

    What is the purpose of opening the steam drum vent valve during the boiler shutdown?

    <p>To prevent a vacuum from forming in the boiler</p> Signup and view all the answers

    Why is it important to record the results of all limit tests in the log book during a boiler shutdown?

    <p>To comply with safety regulations and procedures</p> Signup and view all the answers

    What is the purpose of using a lockbox and numbered group lockout locks during a boiler lockout?

    <p>To ensure that all electrically operated equipment is de-energized</p> Signup and view all the answers

    What is the purpose of sealing the lockbox with a car seal during a boiler lockout?

    <p>To prevent unauthorized access to the lockbox</p> Signup and view all the answers

    Why do contractors and plant employees place their personal locks on the lockbox during boiler maintenance?

    <p>To indicate their involvement in the maintenance work</p> Signup and view all the answers

    What is the purpose of adding a supervisor or operations lock to the lockbox during a boiler lockout?

    <p>To ensure that the lockout was performed correctly</p> Signup and view all the answers

    Why is it important for a second qualified operator to verify that all lockout points are locked during a group lockout?

    <p>To provide an additional layer of verification for safety</p> Signup and view all the answers

    What is the purpose of isolating the boiler from the main header during a shutdown?

    <p>To ensure safe isolation from steam supply</p> Signup and view all the answers

    Why should workers sign-off that their work is complete before removing personal locks from the lockbox?

    <p>To ensure that no unauthorized work is carried out on the boiler</p> Signup and view all the answers