What strategy would you follow if you decided to kill the project altogether due to high potential risks?

  • Mitigation
  • Acceptance
  • Transference
  • Avoidance (correct)

Which strategy would be used if you acknowledged the risk but determined that the project could continue without changes?

  • Transference
  • Mitigation
  • Acceptance (correct)
  • Avoidance

What action represents a response strategy if you hire an insurance company to cover potential financial losses from the project?

  • Transference (correct)
  • Acceptance
  • Mitigation
  • Avoidance

Which risk response strategy would you employ if you implemented additional quality checks in the project to reduce the likelihood of failures?

<p>Mitigation (A)</p> Signup and view all the answers

Signup and view all the answers

Flashcards

Risk Mitigation

A risk response strategy where the project team takes action to reduce the likelihood or impact of a risk.

Risk Acceptance

A risk response strategy where the project team accepts the risk and its potential consequences.

Risk Transference

A risk response strategy where the project team transfers the risk to another party, often through insurance or contracts.

Risk Avoidance

A risk response strategy where the project team takes steps to avoid the risk altogether.

Signup and view all the flashcards

Study Notes

Risk Response Strategy

  • The described scenario demonstrates a mitigation risk response strategy. This is because the project manager is taking steps to reduce the impact of the potential risk (loss of the senior developer) by using a contingency plan.

Contingency Plan

  • A contingency plan is implemented in anticipation of potential risks affecting a project and details how to respond to the possible negative events.

Other Risk Response Scenarios

Scenario 1 (Avoidance):

  • A project is planning to develop a new software product. A crucial external supplier announced substantial price increases for a necessary component. What risk response strategy is being used if the project decides to source the components from an alternative supplier?
    • A
    • B
    • C
    • D

Scenario 2 (Acceptance):

  • A project involves deploying a new IT system. There is a known risk of a 5% chance of data loss due to network disruption. What risk response strategy is used if the project team accepts the potential loss and doesn't implement additional security measures to prevent such disruptions?
    • A
    • B
    • C
    • D

Scenario 3 (Mitigation):

  • A project is developing a new mobile app. To safeguard against potential network problems, the development team creates redundant server infrastructure. What risk response strategy is being demonstrated?
    • A
    • B
    • C
    • D

Scenario 4 (Transference):

  • A construction project involves building a high-rise building. The project identifies a considerable risk associated with adverse weather conditions. What response strategy is being used if the project takes out an insurance policy against potential weather-related damages that may affect the project?
    • A
    • B
    • C
    • D