Risk Informed Completion Time Program Guidelines
16 Questions
2 Views

Risk Informed Completion Time Program Guidelines

Created by
@EntertainingDifferential

Questions and Answers

What must be established to use nominal CC factor probability in the RICT calculation?

  • Assurance of a complete system shutdown
  • Low confidence in the presence of redundant components
  • High confidence in the absence of CC failure mechanisms (correct)
  • Verification of all Technical Specifications
  • What is a consequence of failing to account for the increased possibility of CC failure?

  • Successful completion of a Risk Informed Completion Time
  • Exceeding the Technical Specifications Front Stop (correct)
  • Improvement in redundant system reliability
  • Reduction in initiating event frequencies
  • Which method is NOT mentioned for addressing increased CC failure possibility in RICT calculations?

  • Modifying conditioning probabilities for components
  • Adjusting the RICT calculation numerically
  • Implementing additional individualized redundancy (correct)
  • Using RMAs targeting functional success
  • What is required when a component fails in relation to CC failure probability?

    <p>Increased CC failure probability for remaining components</p> Signup and view all the answers

    What type of condition prompts an exit from a RICT entry?

    <p>A TS loss of function requirement</p> Signup and view all the answers

    In the context of the RICT calculation, what does RMA stand for?

    <p>Risk Mitigation Actions</p> Signup and view all the answers

    According to the content, the RICT calculation requires documentation of RMAs for what purpose?

    <p>Review by the Regulatory Commission</p> Signup and view all the answers

    What is implied if a PRA functionality determination shows that LCO cannot be restored?

    <p>Failure or misalignment of operable trains exists</p> Signup and view all the answers

    What is the maximum duration allowed for a Risk Informed Completion Time (RICT)?

    <p>30 days</p> Signup and view all the answers

    In which operational modes can a RICT be utilized?

    <p>MODE 1 and 2</p> Signup and view all the answers

    When a RICT is being used, what must be considered for any plant configuration change?

    <p>The effect on the RICT must be assessed</p> Signup and view all the answers

    What must happen for a planned change in configuration while a RICT is in use?

    <p>The revised RICT must be determined prior to the change</p> Signup and view all the answers

    Under which condition is the use of a RICT not permitted?

    <p>For voluntary entry into a configuration that results in a loss of a safety function</p> Signup and view all the answers

    When can a RICT be utilized for emergent conditions regarding specified safety function loss?

    <p>If one or more trains are considered ‘PRA Functional’</p> Signup and view all the answers

    What must be true about structures, systems, and components (SSC) for them to be involved in the PRA Functionality determination?

    <p>They must be the same SSCs relied upon for Technical Specifications safety functions</p> Signup and view all the answers

    What is the maximum allowed duration for a RICT under emergent conditions representing a loss of a specified safety function?

    <p>24 hours</p> Signup and view all the answers

    Study Notes

    Risk Informed Completion Time Program

    • The Risk Informed Completion Time (RICT) Program establishes controls for calculating RICT in accordance with NEI-06-09 guidelines.
    • The maximum duration for a RICT is set at 30 days.
    • RICT can only be utilized when the plant is in MODE 1 and 2.
    • Any configuration changes impacting RICT must be assessed under the Configuration Risk Management Program.
      • Revised RICT must be established for planned changes prior to implementation.
      • For emergent conditions, revised RICT must be determined within:
        • Required Action Completion Time, or
        • 12 hours after the configuration change, whichever is shorter.
      • Changes reducing plant risk do not necessitate a revised RICT.
    • RICT is not allowed for voluntary configuration changes that inhibit specified safety functions or render all required system trains inoperable.
    • RICT is permissible for emergent situations causing loss of safety function if trains are deemed “PRA Functional” as defined in NEI 06-09, with a maximum duration of 24 hours.
    • Additional constraints for “PRA Functional” criteria:
      • Structures, systems, and components (SSC) considered PRA Functional must match those relied upon in Technical Specifications.
      • Design basis success criteria must be satisfied for accidents when applying RICT during loss of function.
    • Assessment of common cause (CC) failure potential is mandatory upon entering a RICT due to emergent conditions.
      • If high confidence exists that CC mechanisms do not affect redundant components, nominal CC factor probability can be used for RICT calculation.
      • If confidence is low, RICT must adjust for the increased likelihood of CC failure.
    • Two methods for addressing increased CC failure probability:
      • Adjust RICT calculation to account for CC failure probability as per RG 1.177 guidance.
      • Implement Risk Mitigation Actions (RMA) not credited in the current RICT calculation, targeting the success of redundant SSCs.
    • Documentation of all RMAs must be available for review by the NRC.
    • A RICT entry must be rejected or exited if a PRA Functionality determination indicates that restoring LCO cannot be achieved without compromising functional success criteria.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz covers the essential aspects of the Risk Informed Completion Time Program, focusing on the controls and guidelines as per NEI-06-09. It includes critical rules about the application of RICT, specifically its duration and conditions for use in different operational modes. Test your understanding of these risk management strategies.

    More Quizzes Like This

    Risk Management Overview
    13 questions
    Entrepreneurship and Risk Management
    10 questions
    Composite Risk Management Flashcards
    19 questions
    Use Quizgecko on...
    Browser
    Browser