Risk Assessment and Management
10 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the symbol 'TS' representing in the given equation?

  • Critical path duration
  • Scheduled project duration (correct)
  • Project duration
  • Probability of meeting scheduled duration
  • What is the purpose of Table A7.2?

  • To identify the project duration
  • To determine the critical path duration
  • To find the probability of meeting scheduled duration (correct)
  • To analyze the risk breakdown structure
  • In the equation, what does 'Z' represent?

  • Critical path duration
  • Probability of meeting scheduled duration (correct)
  • Project duration
  • Risk severity
  • What is the purpose of Figure A7.3?

    <p>To illustrate the probability of completing the project before the scheduled time</p> Signup and view all the answers

    What is the relationship between 'TE' and 'TS' in the equation?

    <p>TE is the critical path duration, and TS is the scheduled project duration</p> Signup and view all the answers

    What is the concept behind Figure A7.2?

    <p>Hypothetical network</p> Signup and view all the answers

    What is the main purpose of probability analysis in project management?

    <p>To determine the probability of meeting scheduled duration</p> Signup and view all the answers

    What is the primary application of Table A7.2 in project management?

    <p>Probability analysis</p> Signup and view all the answers

    What is the concept behind Figure A7.2?

    <p>Hypothetical network</p> Signup and view all the answers

    What is the relation between 'Z' and probability in the equation?

    <p>Z is directly proportional to the probability</p> Signup and view all the answers

    Study Notes

    Risk Breakdown Structure (RBS)

    • A risk breakdown structure (RBS) is a hierarchical structure that breaks down risks into categories and subcategories.
    • It is used to identify, categorize, and prioritize risks in a project.

    Risk Assessment

    • Risk assessment involves evaluating the probability and impact of each risk event.
    • Scenario analysis is used to assess the significance of each risk event in terms of probability and impact.
    • A risk assessment form is used to evaluate the severity, probability, and detection difficulty of risk events.
    • The risk severity matrix prioritizes which risks to address.

    Failure Mode and Effects Analysis (FMEA)

    • FMEA extends the risk severity matrix by including ease of detection in the equation: Risk Value = Impact x Probability x Detection.
    • FMEA is used to evaluate the risk of failure of a product or process.

    Risk Response Development

    • The four main strategies for responding to risks are:
      • Mitigating Risk: reducing the likelihood or impact of a risk event.
      • Avoiding Risk: eliminating or avoiding a risk event.
      • Transferring Risk: passing the risk to another party (e.g. through insurance).
      • Escalating Risk: notifying higher management of a risk event.

    Contingency Planning

    • A contingency plan is an alternative plan that will be used if a possible foreseen risk event becomes a reality.
    • Contingency planning involves identifying potential risks and developing alternative plans to mitigate or respond to them.

    PERT and PERT Simulation

    • PERT (Program Evaluation and Review Technique) is a method for planning and controlling projects.
    • PERT assumes each activity duration has a range that statistically follows a beta distribution.
    • PERT uses three time estimates for each activity: optimistic, pessimistic, and most likely.
    • PERT simulation involves computing the probability of meeting different project durations.

    Activity Time Calculations

    • The weighted average activity time is computed using the formula: te = (a + 4m + b) / 6.
    • The variability in the activity time estimates is approximated using the formula: σ^2 = ((b - a) / 6)^2.

    Probability of Completing the Project

    • The probability of completing the project in a specified time can be computed using the formula: Z = (TS - TE) / σ.
    • The Z value is used to determine the probability of meeting the project deadline using statistical tables.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz assesses your understanding of risk assessment techniques, including scenario analysis and risk assessment forms. It covers the evaluation of risk severity, probability, and impact.

    More Like This

    Project Risk Management BBA 231
    30 questions
    Project Risk Management
    20 questions
    Use Quizgecko on...
    Browser
    Browser