Podcast
Questions and Answers
What is the total operational track length specifically available at the pre-tippler area?
What is the total operational track length specifically available at the pre-tippler area?
Which type of locomotives constitutes the majority of the owned fleet?
Which type of locomotives constitutes the majority of the owned fleet?
How are trailing movements identified in rail operations?
How are trailing movements identified in rail operations?
What is the number of operational tracks available in the hot metal area?
What is the number of operational tracks available in the hot metal area?
Signup and view all the answers
Which component is not listed as part of track components in rail infrastructure?
Which component is not listed as part of track components in rail infrastructure?
Signup and view all the answers
What is the minimum number of track lines at the slag yard for loading G.Slag?
What is the minimum number of track lines at the slag yard for loading G.Slag?
Signup and view all the answers
How many total operated points are mentioned in the rail operations?
How many total operated points are mentioned in the rail operations?
Signup and view all the answers
Which area is responsible for loading HR coil according to the operational track lines?
Which area is responsible for loading HR coil according to the operational track lines?
Signup and view all the answers
Which of the following materials has the highest average monthly dispatch volume?
Which of the following materials has the highest average monthly dispatch volume?
Signup and view all the answers
What is NOT a part of the process for inward rake placement?
What is NOT a part of the process for inward rake placement?
Signup and view all the answers
Which unloading point is associated with the Manual Siding?
Which unloading point is associated with the Manual Siding?
Signup and view all the answers
How many total level crossings are noted in the provided information?
How many total level crossings are noted in the provided information?
Signup and view all the answers
Which type of slag is specifically referenced as being dispatched?
Which type of slag is specifically referenced as being dispatched?
Signup and view all the answers
What is the purpose of the TSM Loco attachment in the inward rake process?
What is the purpose of the TSM Loco attachment in the inward rake process?
Signup and view all the answers
In the average monthly dispatch, how much DRI (Direct reduced iron) is noted?
In the average monthly dispatch, how much DRI (Direct reduced iron) is noted?
Signup and view all the answers
Which unloading point is associated with the fly ash material?
Which unloading point is associated with the fly ash material?
Signup and view all the answers
What is the primary mode of transport for DRI (Sponge Iron) based on the provided rail and road coefficients?
What is the primary mode of transport for DRI (Sponge Iron) based on the provided rail and road coefficients?
Signup and view all the answers
Which commodity has the lowest road transport coefficient among the listed materials?
Which commodity has the lowest road transport coefficient among the listed materials?
Signup and view all the answers
In terms of supply chain efficiency, which raw material has a balanced transport ratio between rail and road?
In terms of supply chain efficiency, which raw material has a balanced transport ratio between rail and road?
Signup and view all the answers
Which of the following measures would likely enhance inventory control in raw material handling?
Which of the following measures would likely enhance inventory control in raw material handling?
Signup and view all the answers
For which type of lifting is permissions required from JDM, JODA, and CHAIBASA?
For which type of lifting is permissions required from JDM, JODA, and CHAIBASA?
Signup and view all the answers
Which region's logistics include a mix of both rail and road lifting operations?
Which region's logistics include a mix of both rail and road lifting operations?
Signup and view all the answers
What percentage of coal tar is transported by rail based on the given coefficients?
What percentage of coal tar is transported by rail based on the given coefficients?
Signup and view all the answers
What is the total approximate amount of raw materials received per month at TSM?
What is the total approximate amount of raw materials received per month at TSM?
Signup and view all the answers
Study Notes
Raw Material Handling
- Approximately 16 Lacs MT of material is received at Tata Steel's (TSM) plant per month.
- The majority of raw materials are transported by rail (60% for incoming raw material).
- Road transportation accounts for 40% of raw material transportation.
- Finished goods, including steel slabs, have a higher rail transport coefficient (77.3%).
Ore Mines Quarry (OMQ)
- Tata Steel operates mines in Khandabo (TSL-NDH), Joda (TSL-I), Noamund (TSL-), and Katamati (TSL-).
- Material from Khandabo, Joda, and Noamund is transported by rail.
- Katamati material is lifted via rail and road.
Coal and Fluxes
- Coal and fluxes are sourced from West Bokaro, Paradeep, Dhamara, and MCL.
- Paradeep and Dhamara mines are primarily accessed by rail.
- West Bokaro uses a combination of rail and road transport.
Outward Rake Loading Details
- TSM has designated areas for loading various materials, including:
- Hot Metal Shop (HSM)
- Cold Rolling Mill (CRM)
- SMS1 (Steel Melting Shop)
- Slag Yard
Track Layout
- TSM’s total track length is 76.131 TKM.
- The track from MRDL to the railway gate is 7.318 TKM.
- Track from BDPK to the railway gate is 5.231 TKM.
- Track length from the rail gate to wagon tipplers is 25.248 TKM.
- Post tippler yard track is 16.464 TKM.
- Slag yard to HSM is 8.803 TKM.
- The hot metal area track is 10.037 TKM.
Rail Operations Facilities
- TSM operates 20 tracks in the pre-tippler area.
- There are 15 tracks in the post tippler area.
- The hot metal area has three operational track lines.
- HSM loading tracks are 6.
- CRM has 3 tracks.
- The slag yard has 2 track lines.
- SMS1 has track lines for loading coal tar and container rakes.
- TSM operates a total of 183 points.
Owned Locomotives
- TSM owns 11 diesel electric locomotives.
- There are 2 hired "Titan" locomotives.
- There are 18 torpedo ladle cars (TLCs).
Facing and Trailing Movements
- Trailing movement occurs when a rolling stock first travels through the crossing section of a point.
- Facing movement occurs when rolling stocks move the opposite direction from trailing movement.
Materials for Dispatch
- Steel: 4 Lacs MT per month
- Slag: 1.5 Lacs MT per month
- DRI: 30 Thousand MT per month
- Coal Tar: 2400 MT per month
Inward Rake Unloading Points
- TSM uses wagon tipplers, track hoppers, and manual sidings to unload inward rakes.
Railway Level Crossing Gates
- TSM has 24 level crossing gates.
- Gate 1 is near the commercial office, gate 4 is in the post tippler area, and gate 11 is near SMS-2.
- The last gate, 24, is near the slag yard.
- Gates 2 and 3 are near tippler 1, and gates 5 and 6 are in the HSM area.
Process for Inward Rake Placement
- Raw Material Handling Services (RMHS) team receives planned schedules.
- Upon arrival at the rail yard, railway power is detached and pressure released.
- TSM locomotives are deployed to move and position rakes.
- The rakes are positioned at unloading stations as directed by the RMHS team.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Explore the intricacies of raw material handling at Tata Steel, including transportation methods for incoming and outgoing materials. Learn about the key operating mines and the logistics involved in the movement of coal and fluxes. This quiz offers insights into the operational efficiency of TSM's material handling processes.