Questions and Answers
What is required for any work on the open line that affects passenger train running?
Approval from the Commissioner of Railway Safety is required.
What type of installations require the sanction of the Commissioner of Railway Safety?
Additions, extensions, or alterations to existing Block, Signalling, and interlocking installations.
Which work does not require the Commissioner of Railway Safety's sanction if it enhances safety?
Provision of telephones at already manned level crossings.
What action must be taken before closing manned level crossing gates?
Signup and view all the answers
What type of schemes requires the approval of the Commissioner of Railway Safety?
Signup and view all the answers
What modification does not require sanction relating to signalling assets?
Signup and view all the answers
Which new installations require the Commissioner's sanction?
Signup and view all the answers
What is the implication of providing electrical and mechanical lifting barriers?
Signup and view all the answers
What must the Engineer in charge submit if there is no prior inspection by the Commissioner of Railway Safety?
Signup and view all the answers
What should the Engineer in charge do before signing the Safety Certificate?
Signup and view all the answers
What determines if the work can be opened for public carriage of passengers?
Signup and view all the answers
After satisfying himself, what is the next action of the Engineer in charge?
Signup and view all the answers
In the case of joint works, who else must sign the message along with the Engineer in charge?
Signup and view all the answers
Who is responsible for countersigning the Safety Certificate?
Signup and view all the answers
What additional documentation must accompany the Safety Certificate?
Signup and view all the answers
What is the role of the Divisional Railway Manager concerning the Safety Certificates?
Signup and view all the answers
What must be referenced in the certificate from the Operating Department?
Signup and view all the answers
Which engineers must receive copies of the Safety Certificates if their departments are involved?
Signup and view all the answers
What conditions classify a rolling stock as 'new'?
Signup and view all the answers
What type of modifications are considered material changes in rolling stock design?
Signup and view all the answers
What should happen if there is a disagreement on whether a modification classifies as new rolling stock?
Signup and view all the answers
Who can sanction the use of new locomotives or rolling stock in Government railways?
Signup and view all the answers
What must railway administrations other than Government railways do to use new locomotives?
Signup and view all the answers
How do minor changes in axle load affect the classification of rolling stock?
Signup and view all the answers
What is meant by 'unsprung mass' in the context of rolling stock?
Signup and view all the answers
Why would a change in the internal equipment layout not classify a rolling stock as new?
Signup and view all the answers
Can a slight alteration in track loading density classify rolling stock as new?
Signup and view all the answers
What is the role of the Research, Design and Standards Organisation in rolling stock modifications?
Signup and view all the answers
What is the primary purpose of the Safety Certificate for S&T Works?
Signup and view all the answers
What should be verified to ensure compliance with signalling and telecommunication installations?
Signup and view all the answers
What details must be included in the Joint Safety Certificate for new locomotives?
Signup and view all the answers
Why is it important to specify speed restrictions on the Joint Safety Certificate?
Signup and view all the answers
What institutions or individuals are involved in signing the Joint Safety Certificate?
Signup and view all the answers
What must the General Manager of the Government railway do ten days before the actual use of locomotive or rolling stock?
Signup and view all the answers
What rule applies to proposals from railway administrations other than the Government railway?
Signup and view all the answers
What is required for introducing a new passenger carrying train above 130 kilometer per hour?
Signup and view all the answers
What additional requirement exists for changing the speed of existing passenger trains?
Signup and view all the answers
What is indicated by GSR 945(E), dated 01.10.2018 regarding the rules?
Signup and view all the answers
Who needs to be informed about the sanction communicated by the General Manager?
Signup and view all the answers
What chapter discusses the procedure for commissioning signalling installations?
Signup and view all the answers
What is the main focus of 9.4.3 in the document?
Signup and view all the answers
What happens if a railway administration wishes to introduce a train above 130 km/h?
Signup and view all the answers
What role does the Central Government play in the introduction of new trains?
Signup and view all the answers
What rules must be referenced before starting work that affects the running line?
Signup and view all the answers
What is required before signaling work affecting train operations can commence?
Signup and view all the answers
How should deviations from approved plans be handled?
Signup and view all the answers
What is the Signal Engineer in charge responsible for before commencing work?
Signup and view all the answers
What information should be included in the circular issued by the Operating Department?
Signup and view all the answers
What must be obtained before any work that affects train running is started?
Signup and view all the answers
Why is timely notification important in the commissioning process?
Signup and view all the answers
What happens to deviations made during the signaling work?
Signup and view all the answers
What are the Opening Documents required by the Commissioner of Railway Safety for new lines or electrification?
Signup and view all the answers
Which specific items related to signalling and interlocking must be submitted to the Commissioner of Railway Safety?
Signup and view all the answers
What condition must be met before a new line can open for passenger traffic or initiate electric traction?
Signup and view all the answers
What should be noted if a new line or electrification affects existing signaling or interlocking?
Signup and view all the answers
What role does the General Manager of Railway have before opening a new line?
Signup and view all the answers
What certificate is required for introducing or extending electric traction?
Signup and view all the answers
How long in advance must the Opening Documents be submitted to the Commissioner of Railway Safety?
Signup and view all the answers
What is the purpose of the list of Questions and Answers submitted to the Commissioner?
Signup and view all the answers
What is required if modifications to existing signalling affect a new line?
Signup and view all the answers
What should the Dy.CSTE do regarding signal failures at the stations?
Signup and view all the answers
What is the purpose of the 'Site Inspection Register'?
Signup and view all the answers
What must be obtained before starting trenching and cable laying work?
Signup and view all the answers
What tests must be conducted before non-interlocking working begins?
Signup and view all the answers
What is required from an executing agency before they offer the installation for joint tests?
Signup and view all the answers
What constitutes a rolling stock as 'new' according to the specified conditions?
Signup and view all the answers
What kind of minor changes in rolling stock do not classify it as 'new'?
Signup and view all the answers
Who has the authority to approve the use of new locomotives on Government railway sections?
Signup and view all the answers
In case of disagreements regarding the classification of modifications, who resolves the issue?
Signup and view all the answers
What is the role of the Research, Design and Standards Organisation in terms of rolling stock modifications?
Signup and view all the answers
What must non-Government railway administrations do to use locomotives already introduced by the Central Government?
Signup and view all the answers
What significant modifications in rolling stock design alter its type and operation?
Signup and view all the answers
How may changes in unsprung mass affect rolling stock classification?
Signup and view all the answers
What happens if modifications to rolling stock are deemed minor in terms of axle load or track loading density?
Signup and view all the answers
What is required for introducing a new rolling stock with modified braking systems?
Signup and view all the answers
What must be ensured regarding signalling and interlocking as specified in Chapter VII?
Signup and view all the answers
In what way can arrangements provided for signalling installations fall short of compliance?
Signup and view all the answers
What action should be taken to verify compliance during signalling and interlocking installations?
Signup and view all the answers
What is the significance of ensuring that signalling interlocking installations meet established rules?
Signup and view all the answers
What could be a potential consequence of failing to fully comply with signalling recommendations?
Signup and view all the answers
Who is responsible for reviewing compliance with signalling and interlocking regulations?
Signup and view all the answers
What specific documentation should accompany the verification of signalling installations?
Signup and view all the answers
Why is it important for the General Manager to communicate sanction for new locomotives in advance?
Signup and view all the answers
What role does the Central Government play in the introduction of new trains?
Signup and view all the answers
How does non-compliance with signalling and interlocking recommendations impact railway operations?
Signup and view all the answers
What legal authorization is necessary before starting any work affecting the running line?
Signup and view all the answers
What is the role of the Operating Department during the commissioning of signalling installations?
Signup and view all the answers
What must the Signal Engineer in charge verify before commencing work?
Signup and view all the answers
How should deviations from approved plans be treated according to the guidelines?
Signup and view all the answers
What specific information should the Operating Department's circular include about the work?
Signup and view all the answers
What happens if the Engineer in charge of signalling work does not follow proper procedures?
Signup and view all the answers
What is required for a new section of a railway to be opened for public traffic?
Signup and view all the answers
What should be done to ensure the accuracy of signalling installation documentation?
Signup and view all the answers
What must the Engineer in charge do after completing the work related to disconnection and traffic block?
Signup and view all the answers
What is the validity period of the PCSTE sanction unless otherwise specified?
Signup and view all the answers
What should be done if the Engineer in charge seeks prior inspection by the Commissioner of Railway Safety?
Signup and view all the answers
What is required for the work to be officially opened for public carriage of passengers?
Signup and view all the answers
What must the Principal Chief Signal & Telecommunication Engineer communicate regarding the work's readiness for inspection?
Signup and view all the answers
What must be written if any required document is not submitted?
Signup and view all the answers
What alternative phrase can be used instead of 'NIL' for working rules sent late?
Signup and view all the answers
How long before the public use of the work must the Engineer notify the Commissioner of Railway Safety for inspection?
Signup and view all the answers
What should be verified to ensure that materials used meet loads during the commissioning process?
Signup and view all the answers
What is the maximum validity period of the sanction accorded for the proposed works?
Signup and view all the answers
What must be included in the documentation for both temporary and permanent works?
Signup and view all the answers
What document is essential to certify that no danger will attend the opening for public carriage of passengers?
Signup and view all the answers
Who is responsible for signing the message regarding safety certification in joint works?
Signup and view all the answers
Which chapter covers the procedure for the commissioning of signalling installations?
Signup and view all the answers
What certification does the Commissioner of Railway Safety require before proceeding to public carriage?
Signup and view all the answers
What document must be kept laminated for maintenance staff reference at the station?
Signup and view all the answers
What is required to hand over at the time of maintenance handover of the station?
Signup and view all the answers
List two types of plans mentioned that are necessary for the completion of signalling installations.
Signup and view all the answers
What is the purpose of a 'Battery history card' in the context of signalling installations?
Signup and view all the answers
Identify the document that serves to certify proper installation as per the specified format.
Signup and view all the answers
What should be included in the 'As Laid' cable route plan?
Signup and view all the answers
What is one of the roles of a Control Table in signalling installations?
Signup and view all the answers
Why is a track circuit bonding plan necessary?
Signup and view all the answers
What action does the Engineer in charge take after verifying the installation?
Signup and view all the answers
What type of records must be maintained for the earthing arrangements?
Signup and view all the answers
Who must sign the application for works executed by the Divisional organization?
Signup and view all the answers
What should accompany the application submitted to the Commissioner of Railway Safety?
Signup and view all the answers
How far in advance should the application for sanction be made before the expected commencement of work?
Signup and view all the answers
What is required if a sanctioned work is not initiated within twelve months?
Signup and view all the answers
What must be done if material deviations from the approved plan are necessary?
Signup and view all the answers
What kind of official should sign the application when the work is executed by an extra Divisional Organisation?
Signup and view all the answers
In the case of joint works, who must co-sign the application along with the Divisional Railway Manager?
Signup and view all the answers
What is the prescribed form for making the application for sanction?
Signup and view all the answers
What action does the Commissioner of Railway Safety take if he decides to inspect the work?
Signup and view all the answers
What will the Commissioner of Railway Safety do in relation to the works for which sanction is granted?
Signup and view all the answers
Study Notes
### Section 2: Obtaining Sanction for Works on Lines Opened to Traffic
-
Works requiring the approval of the Commissioner of Railway Safety (CRS) include:
- Additions, extensions, or alterations to existing block, signaling, and interlocking installations.
- Changes in block, signaling, and interlocking schemes.
- New stations, temporary or permanent.
- Interlocking of level crossings, catch sidings, and slip sidings.
- Closing of manned level crossing gates, after approval from district administration.
-
Works that do NOT require the sanction of the CRS include:
- Provision of telephones at manned level crossings.
- Installation of electrical or mechanical lifting barriers, including emergency interlocking, and sliding booms at interlocked level crossing gates.
- Interlocking existing level crossing gates within interlocked station yards using existing signals.
- Installation of track circuits, axle counters, including dual detection.
- Replacement or modification of signaling assets without changing the yard layout or signal interlocking, either in station yards or at level crossings.
- Replacement of block instruments with approved substitutes, or signal proving through axle counters or track circuits, using existing block instruments.
### Safety Certificate
- The Engineer-in-charge must submit a safety certificate on the prescribed form before commencing work.
- The Engineer-in-charge must test the new works and ensure the installation was carried out correctly.
- The Engineer-in-charge must be fully satisfied that the work can be opened to the public without endangering the safety of the travelling public or railway employees.
- The Engineer-in-charge must then bring the installation into use by sending a message to the Commissioner of Railway Safety.
- If the work involves multiple departments, the Engineer-in-charge of each department must sign the certificate.
Use of New Types of Locomotives or Rolling Stock
- The use of new types of locomotives or rolling stock introduced by the Central Government requires the approval of the General Manager of the Government railway.
- Railway administrations other than Government railways need to obtain approval from the Central Government through the CRS.
- The General Manager must inform the CRS ten days before any new locomotive or rolling stock is put into service.
Introduction of New Passenger Trains or Changes in Speed
- Railway administrations can introduce new passenger trains or change the speed of existing ones following instructions from the Central Government.
- If the speed of a new passenger train or existing passenger train exceeds 130 km/h, the railway administration must get approval from the Central Government through the CRS.
Appendix
- Annexure 9-A5 is a safety certificate for S&T works related to the implementation of electrification.
- Annexure 9-A6 is a Joint Safety Certificate for New types of locomotives or rolling stock.
General Instructions
- Safety: Indian Railway Act, General Rules & Subsidiary rules, Rules for Opening of a Railway, and the Indian Railway Schedule of Dimensions are all used to ensure the safety of passengers
- Authorization: Any work that alters the running line requires legal authorization before starting or using the work
- Notification: Before any work begins or new traffic instructions are brought into use, the Operating Department needs to be notified
- Approved plans: All work must be done according to approved plans, standard drawings and specifications and should conform to provisions in the signalling manual
- Deviations: Any deviations must be approved by the Principal Chief Signal and Telecommunication Engineer
- Engineer Incharge: The Signal Engineer incharge is responsible for ensuring adequate men and materials are available for any work
New Lines & Electrification
-
Application: The General Manager of the Railway must provide a set of documents to the Commissioner of Railway Safety at least one month before a new line is opened to the public
- These documents are collectively called "Opening Documents"
- The documents include:
- Tabulated details
- Index plan and section of Railway
- Drawings of works
- List of questions and answers
- Certificates
- List of infringements of maximum and minimum dimensions
- Diagram of proposed testing train
- Station working rules
-
Signalling Documents: The following documents pertaining to signalling and interlocking are also required:
- Tabulated details (Form No. VIII of Rules for Opening of a Railway)
- Drawings of works, plans of station yard showing gradients, the layout of tracks and signals and interlocking including Locking and Selection tables/Route Control chart
- List of Questions and Answers
- Station working Rules
- Certificate for introducing or extending electric traction, containing details of maximum value of Traction current
- Commissioner of Railway Safety: Final authorization for opening a line for passenger traffic or beginning electric traction is given by the Commissioner of Railway Safety after an inspection
- Existing Signalling: Any work affecting existing signalling or interlocking for a new line or electrification requires prior sanction from the Commissioner of Railway Safety
Rolling Stock
- New Rolling Stock: A rolling stock with different principal dimension or a different bogie design or new designs of braking system or suspension details is considered new
- Minor changes: Any minor changes to equipment design or change of internal equipment layout on the rolling stock or minor change of axle load or minor change of track loading density or minor change in unsprung mass are not considered new rolling stock, unless they are likely to significantly affect weight distribution, center of gravity or riding behavior of the rolling stock
- Material modification: Any changes in the design of the coach which alters the system of operation and control over the rolling stock, like change in the braking system or change in the principle of traction are considered material modifications in the type and design of the rolling stock
Use of New Types of Locomotives or Rolling Stock
- Government railway: The General Manager of a Government railway can approve the use of locomotives or rolling stock that was already introduced on Indian railways by the Central Government
- Other Railways: Private railways need approval from the Central Government through the Commissioner for using any locomotive or rolling stock already introduced on Indian railway by the Central Government
List of Questions & Answers for Opening Documents
- Signalling & Telecommunication: Questions are designed to confirm that all requirements and recommendations regarding signalling and interlocking are met, as well as the catechism for signalling interlocking installations
Work Execution
- Open Line Inspection: Open Line inspectors and Officers should be involved in new/alteration works to identify any deficiencies before the work is completed
- Maintenance staff presence: Open Line maintenance staff should be present when work is done in existing location boxes
- Cable route plan: Cable route plans are required to be approved before beginning any trenching and cable laying
- Power supply equipment: Power supply equipment needs to be approved by the PCSTE/OL
- Cable insulation test: Open line organization is responsible for carrying out power supply audits and functional tests before executing agencies can begin non-interlocking working
- Wiring diagram alterations: Any alteration done by executing agencies to wiring diagrams must be reported to open line officials for further testing
- Testing: Executing agencies are responsible for performing continuity, wire count, breakdown, and functional tests before offering the installation to the open line for joint testing
- Maintenance staff planning: Sr.DSTE is responsible for coordinating maintenance staff positioning with construction/Project organisation or Rly PSUs
Commissioning of Signalling Installations
- Safety is paramount: The text emphasizes the importance of following the rules and regulations laid down by the Indian Railway Act, General Rules, Subsidiary rules, Rules for opening a railway, and Indian Railway Schedule of Dimensions.
- Notification for Work: Before any signalling work affecting train operations is commenced, all concerned departments must be notified through a circular issued by the Operating Department. This includes information regarding the commencement date, duration, working arrangements during the work, and the opening date.
- Strict Adherence to Plans: All work must conform to the approved plans, standard drawings, and specifications, and must comply with the provisions of the Signal Engineering Manual (SEM). Deviations require prior approval from the Principal Chief Signal and Telecommunication Engineer (PCSTE).
- Responsibilities of the Signal Engineer: The Signal Engineer in charge is responsible for ensuring availability of adequate manpower and materials before commencing any work.
-
Applications for Sanction: Applications for carrying out signalling works listed in Para 9.2.1 and 9.2.2 of the SEM are submitted in a specific format (Form 1606/1) and should be accompanied by the Station Working Rules:
- Divisional Organization: Application signed by the Senior Divisional Signal & Telecom Engineer.
- Extra Divisional Organization: Application signed by an officer of the rank of Deputy Chief Signal and Telecommunication Engineer.
- Joint Works: Application signed by officers of the Junior Administrative grade from the departments involved.
-
Sanction Process:
- The application for sanction must be submitted at least 14 days before the expected commencement of the work.
- If a sanctioned work is not started within 12 months, a fresh sanction is required.
- The Commissioner of Railway Safety (CRS) /PCSTE may or may not inspect the work before opening.
- If inspecting, the CRS/PCSTE will communicate the sanction to open the work after inspection.
-
Documents for CRS/PCSTE Sanction:
- Temporary Works: Description of proposed works, temporary work drawings, list of infringements to the Schedule of Dimensions, list of deviations from the SEM and General/Subsidiary Rules, restrictions, traffic working rules, and bridge documents as per Chapter VII of the Rules for the Opening of Railways.
- Permanent Works: The same documents as for temporary works are required.
- Safety Certificate: Upon completion of the work, a safety certificate is signed by the responsible engineer, signifying that all work is completed to the required standards.
-
Documents for Commissioning:
- Approved Station Interlocking Plan (SIP).
- Completion wiring diagrams.
- Control Table, Selection Table, Locking Table, Route Control Chart, and Dog Chart documents.
- Panel diagram/VDU diagrams (for panel or EI installations).
- Sighting Committee certificate.
- Approved and updated 'As Laid' Cable Route plan.
- Cable termination plan/diagrams in relay room, location boxes, and power supply room.
- Wire counts details for Relay Interlocking (RRI).
- Power supply arrangement plan.
- Cable insulation test record.
- Signal infringements at the station.
- Track circuit bonding plan.
- Battery history card, track circuit test card, and earth resistance measurement record.
- Tools, plants, and spares.
- 3 sets of DVDs containing all completion drawings.
- Floor Plans of Relay room, IPS room, Battery room, ASM room, OFC/Telecom cable room, and Maintainer room.
- Earthing Plan of Relay room, IPS room, and Control Panel/VDU ASM’s room.
- Earthing value joint measurements records.
- Technical documents of any new equipment installed.
-
PCSTE Sanction:
- For works not requiring CRS sanction, a PCSTE sanction is obtained in a specific format (Annexure 9-A9).
- The PCSTE may or may not inspect the work, communicating their decision in writing.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on the requirements for obtaining sanction for various railway works. This quiz covers the works that need approval from the Commissioner of Railway Safety and those that do not. Understand the nuances of signaling, interlocking, and station modifications.