According to the order of precedence of documents, which takes the highest priority in a contract agreement?

Letter of Award/Acceptance(LOA)

In case of any contradiction in a contract agreement, which document holds the second highest precedence?

Special Conditions of Contract

Which document holds the third highest precedence in a contract agreement, after the Letter of Award/Acceptance(LOA) and Bill(s) of Quantities?

Indian Railways Standard General Conditions of Contract

Which document holds the fourth highest precedence in a contract agreement, after the Letter of Award/Acceptance(LOA), Bill(s) of Quantities, and Special Conditions of Contract?

Technical Specifications as given in tender documents

Which document holds the fifth highest precedence in a contract agreement, after the Letter of Award/Acceptance(LOA), Bill(s) of Quantities, Special Conditions of Contract, and Technical Specifications?

Drawings

Test your knowledge of railway contract agreements with this quiz. Challenge yourself to understand the order of precedence of documents, conditions of tender/contract, specifications, drawings, and other key aspects as per the GFR 2017.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free

More Quizzes Like This

Indian Railways GCC Quiz
5 questions

Indian Railways GCC Quiz

ReverentForethought avatar
ReverentForethought
Railway Safety Terminology Quiz
6 questions
Use Quizgecko on...
Browser
Browser