Project Planning Essentials Quiz

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson
Download our mobile app to listen on the go
Get App

Questions and Answers

What are the outcomes of the initial project coordination and the project charter?

  • Mission goals, client permission, outside clients, aggregated levels
  • Client specifications, project planning, organizational strategy, budget levels
  • Technical scope, areas of responsibility, delivery dates or budgets, risk management group (correct)
  • Project objectives, launch meetings, senior manager attendance, risk review

What is important for a senior manager to attend in traditional project activity planning?

  • Risk management group
  • Launch meetings (correct)
  • Project objectives
  • Client specifications

When planning for outside clients, what cannot be changed without the client’s permission?

  • Areas of responsibility
  • Specifications (correct)
  • Delivery dates
  • Technical scope

What should not go beyond the most aggregated levels at the initial project coordination stage?

<p>Plans, schedules, and budgets (B)</p> Signup and view all the answers

What should project objectives be tied to in traditional project activity planning?

<p>Overall mission, goals, and organizational strategy (B)</p> Signup and view all the answers

Flashcards are hidden until you start studying

Related Documents

Project Planning PDF

More Like This

Project Planning Essentials Quiz
5 questions
Event Planning Essentials
5 questions

Event Planning Essentials

ConscientiousPrudence2187 avatar
ConscientiousPrudence2187
Use Quizgecko on...
Browser
Browser