Which of the following is the most accurate definition of a project?
Which of the following is the most accurate definition of a project?
- A temporary endeavor undertaken to create a unique product, service or result.
- A complex, nonroutine, one-time effort to create a unique product or service limited by time, budget, and specifications. (correct)
- A unique set of coordinated activities, with a definite starting and finishing point, undertaken by an individual or organization to meet specific objectives within a defined schedule, cost and performance parameters.
- A unique, transient endeavor undertaken to achieve planned objectives.
What are project characteristics?
What are project characteristics?
- Complex, permanent, focused, emergent and uncertain
- Unique, temporary, focused, emergent and uncertain (correct)
- Common, permanent, broad, predictable
- Routine, continuous, flexible, predictable
Which organization defines a project as 'A unique, transient endeavor undertaken to achieve planned objectives'?
Which organization defines a project as 'A unique, transient endeavor undertaken to achieve planned objectives'?
- British Standards Institution (BSI)
- Gray & Larson
- Project Management Institute (PMI)
- Association for Project Management (APM) (correct)
What is the role of project management?
What is the role of project management?
Which of the following is NOT a characteristic of a project?
Which of the following is NOT a characteristic of a project?