Project Cost Management Quiz
18 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What does EV stand for in the context of project management?

  • Earned Value (correct)
  • Estimated Value
  • Estimated Cost
  • Estimated Completion
  • Which formula best represents Estimate At Completion (EAC) in project management?

  • (PV + AC) / 2
  • (BAC / CV) * AC
  • (BAC / CPI) * AC (correct)
  • (BAC - AC) + EV
  • What does PV represent in project management terms?

  • Planned Value (correct)
  • Progressive Value
  • Project Variance
  • Performance Value
  • In project management, what does BAC stand for?

    <p>Budget At Completion</p> Signup and view all the answers

    What is the purpose of Actual Cost (AC) in project management?

    <p>To calculate final project cost</p> Signup and view all the answers

    How is Earned Value calculated in project management?

    <p>(PV * % Complete)</p> Signup and view all the answers

    In Earned Value Management (EVM), what does AC represent?

    <p>Actual Cost</p> Signup and view all the answers

    What does CPI (Cost Performance Index) indicate in Earned Value Management (EVM)?

    <p>The project is under budget</p> Signup and view all the answers

    If a project's EAC (Estimate At Completion) is higher than the BAC (Budget At Completion), what does this imply?

    <p>The project is over budget</p> Signup and view all the answers

    What is the relationship between VAC (Variance At Completion) and EAC in Earned Value Management (EVM)?

    <p>VAC = BAC - EAC</p> Signup and view all the answers

    How is Planned Value (PV) calculated in Earned Value Management (EVM)?

    <p>$100 x Number of birdhouses planned to build</p> Signup and view all the answers

    If a project has a CPI of 0.909, what can be inferred about its performance?

    <p>Over budget and behind schedule</p> Signup and view all the answers

    What does Planned Value (PV) represent in Earned Value Management methodology?

    <p>The budgeted cost of the work scheduled to be done</p> Signup and view all the answers

    In Earned Value Management, what does a Planned Value (PV) of $950.00 as of day 3 indicate?

    <p>The project is ahead of schedule</p> Signup and view all the answers

    How is Planned Value (PV) calculated in Earned Value Management?

    <p>PV = BAC * % Complete</p> Signup and view all the answers

    Which formula correctly represents the relationship between Planned Value (PV), Earned Value (EV), and Actual Cost (AC) in Earned Value Management?

    <p>EV = PV + AC</p> Signup and view all the answers

    If a project has a Planned Value (PV) of $1000 and Actual Cost (AC) of $1200, what does this suggest about the project performance?

    <p>The project is over budget</p> Signup and view all the answers

    Which term in Earned Value Management signifies the total budget allocated for the project?

    <p>Budget at Completion (BAC)</p> Signup and view all the answers

    Study Notes

    Earned Value Management (EVM)

    • EVM is a method to measure project performance by comparing the value of work accomplished to the actual cost incurred.

    Budgeted Cost of Work Scheduled (BCWS)

    • BCWS is the budgeted cost for the work planned to be completed by a specific point in time.

    Earned Value (EV)

    • EV is the estimated value of the work accomplished as of today.

    Actual Cost (AC)

    • AC is the actual cost incurred for the work accomplished as of today.

    Estimate at Completion (EAC)

    • EAC is the anticipated total cost of the project at completion.
    • EAC is how much you expect the project to cost when it is complete.

    Estimate to Complete (ETC)

    • ETC is the outstanding amount of money needed to complete the remaining work on the project.
    • ETC is how much more money you expect to spend to complete the project.

    Cost Variance (CV)

    • CV is the difference between what you have planned to spend on the project and what you've actually spent so far.
    • CV = EV – AC
    • Negative CV indicates over budget, while positive CV indicates under budget.

    Schedule Variance (SV)

    • SV is the difference between the planned schedule and the actual schedule.
    • SV = EV – PV
    • Negative SV indicates behind schedule, while positive SV indicates ahead of schedule.

    Variance at Completion (VAC)

    • VAC is how much over or under budget the project will be at the end of the project.
    • VAC = BAC – EAC

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Test your knowledge on project cost management concepts such as budgeted cost, actual cost, and estimated cost at completion. Practice questions related to EAC calculations and budgeted cost of work scheduled.

    More Like This

    Use Quizgecko on...
    Browser
    Browser