Which of the following is NOT a characteristic of a project charter?
Which of the following is NOT a characteristic of a project charter?
- It authorizes the project manager to apply resources to project activities
- It identifies and assigns a project manager as early in the project as feasible
- It is signed-off and project is thus authorized by the project manager (correct)
- it is a document that formally authorizes a project
What does a project charter typically outline?
What does a project charter typically outline?
- The project budget and resources
- The project milestones and deadlines
- The project objectives and goals (correct)
- The project risks and issues
Why is it important to identify project stakeholders in a project charter?
Why is it important to identify project stakeholders in a project charter?
- To exclude stakeholders from the project
- To create conflicts among stakeholders
- To assign responsibilities to stakeholders
- To ensure stakeholders are aware of the project (correct)