PRINCE2® 7 Foundation Module 1 Quiz
26 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which characteristic of a project underscores that each project will be unique?

  • Temporary nature
  • Involvement of multi-skilled teams (correct)
  • Introduce change
  • Introduction of uncertainty
  • What is the main advantage of using PRINCE2 in an organization?

  • Focuses solely on documentation without considering outcomes
  • Ensures a common language and concepts across projects (correct)
  • Allows for personalized project direction by individual team members
  • Provides a fixed method with no flexibility
  • Which delivery method allows for the product to be available during the project?

  • Agile framework
  • Iterative-incremental approach
  • Hybrid approach
  • Linear-sequential approach (correct)
  • What is a common aspect of Agile methodologies?

    <p>Encourages iterative and incremental delivery (D)</p> Signup and view all the answers

    Which of the following is NOT a stakeholder outside the business mentioned?

    <p>Employees (A)</p> Signup and view all the answers

    What is the primary principle of PRINCE2 that ensures a project has a justifiable reason for its existence throughout its lifecycle?

    <p>Ensure Continued Business Justification (C)</p> Signup and view all the answers

    Which aspect of project management emphasizes that every project is unique?

    <p>Project Context (B)</p> Signup and view all the answers

    How does the 'manage by exception' principle benefit senior management in a PRINCE2 project?

    <p>It allows decisions to be made at the appropriate level. (B)</p> Signup and view all the answers

    In PRINCE2, what is the significance of the principles in relation to project tailoring?

    <p>They provide a framework for adapting the method. (A)</p> Signup and view all the answers

    Which of the following accurately describes supplier stakeholders within a PRINCE2 framework?

    <p>They can be either internal or external to the organization. (C)</p> Signup and view all the answers

    What does the term 'five integrated elements' in PRINCE2 encompass?

    <p>People, Principles, Practices, Processes, and Project Context (C)</p> Signup and view all the answers

    Which principle of PRINCE2 focuses on decision-making at the appropriate level within the organization?

    <p>Manage by Exception (B)</p> Signup and view all the answers

    What is meant by 'tailoring a project' in the context of PRINCE2?

    <p>Applying PRINCE2 principles in a flexible way to fit specific project needs. (D)</p> Signup and view all the answers

    Which of the following is a characteristic of projects as per the PRINCE2 framework?

    <p>Projects always introduce uncertainty. (B)</p> Signup and view all the answers

    What is one of the seven variables that project managers need to control in a PRINCE2 environment?

    <p>Delivery methods (C)</p> Signup and view all the answers

    Which statement best describes the agile approach within PRINCE2?

    <p>It allows for a flexible approach with iterative and incremental delivery. (A)</p> Signup and view all the answers

    Which benefit of PRINCE2 relates to the common language and concepts it provides?

    <p>Improved collaboration across teams (B)</p> Signup and view all the answers

    What is the significance of understanding the project context in PRINCE2?

    <p>It helps tailor the principles, practices, and processes properly. (A)</p> Signup and view all the answers

    What principle emphasizes that the justification for a project must remain valid throughout its lifecycle?

    <p>Ensure continued business justification (C)</p> Signup and view all the answers

    Which of the following elements is NOT one of the five integrated elements in PRINCE2?

    <p>PRINCE2 Techniques (D)</p> Signup and view all the answers

    How does the 'manage by exception' principle operate within a PRINCE2 project?

    <p>It ensures decisions are made by the appropriate level of management. (A)</p> Signup and view all the answers

    What is the purpose of the 'define roles, responsibilities and relationships' principle in PRINCE2?

    <p>To establish clear accountability and enhance communication among project participants. (B)</p> Signup and view all the answers

    Which aspect of project management does PRINCE2 emphasize to highlight the uniqueness of each project?

    <p>The flexibility to adapt the methodology to different projects (C)</p> Signup and view all the answers

    In PRINCE2, what does the tailoring process allow project teams to do?

    <p>Modify the methodology to better fit the specific project context (B)</p> Signup and view all the answers

    The flexibility of PRINCE2 is attributed to which of the following?

    <p>The guidance provided by its principles for project application (C)</p> Signup and view all the answers

    What aspect of project performance is NOT considered in PRINCE2?

    <p>Project financing and budget allocation (A)</p> Signup and view all the answers

    Flashcards

    Stakeholders outside a business

    Groups or individuals (like trade unions, customers, suppliers, communities, interest groups, banks, or media) who are affected by a project.

    Project Context (PRINCE2)

    Part of PRINCE2 that affects how principles, practices, and processes are applied. It needs to be understood by stakeholders for appropriate application.

    Project characteristics

    Projects have unique aspects, uncertainty, involve temporary change, and a multi-skilled team.

    Agile approach (projects)

    A way of working in projects characterized by collaboration, prioritization, iterative/incremental delivery, and time constraints. Examples: Scrum, Kanban.

    Signup and view all the flashcards

    PRINCE2 benefits

    PRINCE2 provides a universal common language and concepts, increases organizational maturity, and is part of an integrated project management method. It's also outcome focused and flexible as a proven approach.

    Signup and view all the flashcards

    Project Justification

    A project must have a valid reason for starting and this reason needs to be maintained throughout the project.

    Signup and view all the flashcards

    Manage by Exception

    Decision making happens at appropriate levels of the organization to free up senior management's time while maintaining control.

    Signup and view all the flashcards

    PRINCE2 Flexibility

    PRINCE2 allows tailoring to specific project needs.

    Signup and view all the flashcards

    Project Uniqueness

    Every project is different, varying in teams, customers, suppliers, location, and timeframe.

    Signup and view all the flashcards

    Stakeholder Types

    Stakeholders can be internal or external to an organization.

    Signup and view all the flashcards

    PRINCE2 Principles

    PRINCE2 principles guide how PRINCE2 fits a project.

    Signup and view all the flashcards

    Integrated Elements in PRINCE2

    PRINCE2 has five integrated elements: people, principles, practices, processes, and project context.

    Signup and view all the flashcards

    Linear-sequential approach

    A project delivery method where steps happen in order, and the finished product is available either during or at the end of the project.

    Signup and view all the flashcards

    Iterative-incremental approach

    A project delivery method where steps are repeated throughout the project, building upon previous work. This is also known as the agile approach.

    Signup and view all the flashcards

    Hybrid approach

    A project delivery method that combines elements of both linear-sequential and iterative-incremental approaches.

    Signup and view all the flashcards

    Agile (in projects)

    A broad concept that emphasizes collaboration, prioritization, iterative and incremental delivery, and timeboxing, allowing teams to work flexibly.

    Signup and view all the flashcards

    Timeboxing

    A technique used in agile projects where tasks are assigned fixed timeframes, forcing focus and prioritization.

    Signup and view all the flashcards

    What defines a project?

    A project is temporary with a specific goal, involves a team, and usually has a budget and deadline.

    Signup and view all the flashcards

    Tailoring in PRINCE2

    Adapting PRINCE2 to fit the specific needs of a project, like its size, complexity, or industry.

    Signup and view all the flashcards

    Project Context

    The surrounding environment of a project, including stakeholders, organization, and delivery methods.

    Signup and view all the flashcards

    Ensure Continued Business Justification

    The project must have a valid reason for starting and this reason must remain valid throughout its life.

    Signup and view all the flashcards

    Study Notes

    Module 1: Introduction to PRINCE2® 7 Foundation

    • Topics Covered:

      • Defining a project and its characteristics
      • PRINCE2 features and benefits
      • Project management
      • Project performance aspects
      • Project context (users, suppliers, business, organizational context)
      • Delivery methods
      • Five integrated elements of PRINCE2
      • PRINCE2 principles, practices, and processes
      • Project context tailoring
      • Example of a project tailoring
      • What makes a good project
    • What is a Project?

      • Needs a justifiable reason for starting, which must remain valid throughout the project lifecycle
      • Every project unique (due to team, customer, supplier, location, or timeframe)
    • Good Project Characteristics:

      • Relevant to organizational goals
      • On budget
      • On time
      • Well-managed
      • Delivers value and benefits
      • Well-planned
      • Meets objectives
      • Meets stakeholder needs
      • Engaged stakeholders
    • PRINCE2 Principles:

      • Ensure continued business justification (throughout the project lifecycle) is essential
    • Project Variables:

      • Benefits
      • Costs
      • Risk
      • Scope
      • Sustainability
      • Quality
      • Time
    • Delivery Approaches:

      • Linear-sequential
      • Iterative-incremental (Agile)
      • Hybrid (combination of linear and iterative approaches)

    Seven Core Principles of PRINCE2

    • Define roles, responsibilities and relationships
    • Ensure continued business justification
    • Focus on products
    • Manage by exception
    • Manage by stages
    • Learn from experience
    • Tailor to suit the project

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Test your understanding of the foundational concepts of PRINCE2® in this quiz. Explore the characteristics of a successful project, the benefits of PRINCE2 features, and the integrated elements that make up this project management methodology. Perfect for anyone preparing for the PRINCE2® 7 Foundation certification.