Piping and Instrumentation Diagram (P&ID) Quiz
33 Questions
67 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which diagram includes more detail, the P&ID or the PFD?

  • The P&ID (correct)
  • The PFD
  • Both diagrams have the same level of detail
  • Neither diagram includes any detail

What does the P&ID show the details of?

  • The exact orientation of equipment
  • The order of occurrence of equipment
  • The physical locations of equipment
  • The general piping orientation (correct)

What is the purpose of P&IDs in the operation, repair, and modification of the plant?

  • To provide a concise format for how a system should function (correct)
  • To provide information on the order of occurrence of equipment
  • To draw the diagrams to scale
  • To show the exact physical locations of equipment

Which instrument is used to sense the tank level in the control loop described in Figure 7?

<p>Level Indicator (LI) (A)</p> Signup and view all the answers

What type of control system is indicated by the control lines in Figure 7?

<p>Pneumatic (A)</p> Signup and view all the answers

What instrument records the tank level in the control loop described in Figure 7?

<p>Level Recorder (LR) (C)</p> Signup and view all the answers

What type of signal does the level controller send to the diaphragm-operated level control valve in Figure 7?

<p>Pneumatic (B)</p> Signup and view all the answers

Which of the following is NOT typically shown on a P&ID diagram?

<p>Instrumentation (D)</p> Signup and view all the answers

What is the purpose of a P&ID diagram during the design and pre-construction phases?

<p>To develop cost estimates and bid proposals (C)</p> Signup and view all the answers

What do P&IDs provide to field construction and inspection personnel during construction?

<p>A reference for proper equipment location (C)</p> Signup and view all the answers

What do P&IDs serve as for plant operating and engineering staff after construction?

<p>Operational and training reference (B)</p> Signup and view all the answers

Which instrument is used to sense the tank level in the control loop described in Figure 7?

<p>Level Indicator (D)</p> Signup and view all the answers

What type of control system is indicated by the control lines in Figure 7?

<p>Pneumatic (A)</p> Signup and view all the answers

What instrument records the tank level in the control loop described in Figure 7?

<p>Level Recorder (C)</p> Signup and view all the answers

What type of signal does the level controller send to the diaphragm-operated level control valve in Figure 7?

<p>Pneumatic signal (D)</p> Signup and view all the answers

Which diagram provides more detail, the P&ID or the PFD?

<p>The P&amp;ID (A)</p> Signup and view all the answers

What information does the P&ID show about equipment orientation?

<p>General piping orientation (C)</p> Signup and view all the answers

What is the purpose of P&IDs in the operation, repair, and modification of the plant?

<p>To provide a concise format for how a system should function (C)</p> Signup and view all the answers

Which of the following is typically shown on a P&ID diagram?

<p>All of the above (D)</p> Signup and view all the answers

What is the purpose of a P&ID diagram during the design and pre-construction phases?

<p>To define the scope of a project (D)</p> Signup and view all the answers

What do P&IDs provide to field construction and inspection personnel during construction?

<p>Reference for proper location and interrelation of components (C)</p> Signup and view all the answers

What do P&IDs serve as for plant operating and engineering staff after construction?

<p>Operational and training reference (D)</p> Signup and view all the answers

Which diagram provides more detail, the P&ID or the PFD?

<p>The P&amp;ID (C)</p> Signup and view all the answers

What information does the P&ID show about equipment orientation?

<p>The order of occurrence of equipment (D)</p> Signup and view all the answers

What do P&IDs serve as for plant operating and engineering staff after construction?

<p>A reference for system functionality (D)</p> Signup and view all the answers

Which instrument in the control loop described in Figure 7 records the tank level?

<p>Level Indicator (B)</p> Signup and view all the answers

What type of signal does the level controller send to the diaphragm-operated level control valve in Figure 7?

<p>Pneumatic (C)</p> Signup and view all the answers

Which diagram includes more detail, the P&ID or the PFD?

<p>P&amp;ID (A)</p> Signup and view all the answers

What type of control system is indicated by the control lines in Figure 7?

<p>Pneumatic control system (A)</p> Signup and view all the answers

Which of the following is NOT typically shown on a P&ID diagram?

<p>Instrumentation symbols (D)</p> Signup and view all the answers

What do P&IDs serve as for plant operating and engineering staff after construction?

<p>A training manual (D)</p> Signup and view all the answers

What is the purpose of a P&ID diagram during the design and pre-construction phases?

<p>To develop cost estimates and bid proposals (D)</p> Signup and view all the answers

What type of signal does the level controller send to the diaphragm-operated level control valve in Figure 7?

<p>Level signal (C)</p> Signup and view all the answers

Flashcards

P&ID (Piping and Instrumentation Diagram)

A detailed diagram that shows the piping and instrumentation of a process system.

PFD (Process Flow Diagram)

A simplified diagram that focuses on the overall flow of materials in a process.

What does the P&ID show about equipment orientation?

The P&ID shows the general orientation of piping and equipment.

What is the purpose of P&IDs in the operation, repair, and modification of the plant?

P&IDs provide a concise representation of a system's functionality for operation, repair, and modification.

Signup and view all the flashcards

What is the purpose of a P&ID diagram during the design and pre-construction phases?

P&IDs are used to define the scope of a project, develop cost estimates, and create bid proposals.

Signup and view all the flashcards

What do P&IDs provide to field construction and inspection personnel during construction?

P&IDs provide guidance for the correct location and interrelation of components during construction.

Signup and view all the flashcards

What do P&IDs serve as for plant operating and engineering staff after construction?

P&IDs serve as a reference for system functionality, operation, and training after construction.

Signup and view all the flashcards

What type of control system is indicated by the control lines in Figure 7?

A pneumatic control system utilizes compressed air to transmit signals.

Signup and view all the flashcards

Which instrument is used to sense the tank level in the control loop described in Figure 7?

The level indicator (LI) senses the tank level in the control loop.

Signup and view all the flashcards

What instrument records the tank level in the control loop described in Figure 7?

The level recorder (LR) records the tank level in the control loop.

Signup and view all the flashcards

What type of signal does the level controller send to the diaphragm-operated level control valve in Figure 7?

The level controller sends a pneumatic signal to the diaphragm-operated level control valve in Figure 7.

Signup and view all the flashcards

Which diagram includes more detail, the P&ID or the PFD?

The P&ID shows more detail than the PFD.

Signup and view all the flashcards

Which of the following is typically shown on a P&ID diagram?

Instrumentation symbols are typically shown on a P&ID diagram.

Signup and view all the flashcards

Study Notes

P&ID vs PFD

  • The P&ID diagram includes more detail than the PFD.

P&ID Details

  • Shows the details of equipment orientation, piping, instrumentation, and control systems.
  • Provides information about equipment orientation.

Purpose of P&IDs

  • In operation, repair, and modification of the plant, P&IDs serve as a guide for operations, maintenance, and engineering staff.
  • During design and pre-construction phases, P&IDs facilitate communication among designers, engineers, and operators.
  • For field construction and inspection personnel during construction, P&IDs provide a detailed guide for installation and inspection.
  • After construction, P&IDs serve as a reference for plant operating and engineering staff.

Control Loop Components

  • In Figure 7, the instrument that senses the tank level is not specified.
  • The level controller sends an electronic signal to the diaphragm-operated level control valve.
  • The instrument that records the tank level is not specified.
  • The control system indicated by the control lines in Figure 7 is a feedback control loop.

P&ID Content

  • Typically includes information about equipment, piping, instrumentation, and control systems.
  • Does not typically show information about civil foundations or building layouts.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

Plant Diagrams and Drawings PDF

Description

Test your knowledge on piping and instrumentation diagrams (P&IDs) with this quiz. Learn about the importance of P&IDs in showing equipment details, piping orientation, and control and instrumentation devices.