🎧 New: AI-Generated Podcasts Turn your study notes into engaging audio conversations. Learn more

PERT Estimation Method
10 Questions
0 Views

PERT Estimation Method

Created by
@EasygoingLogic2024

Podcast Beta

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the formula to calculate the Expected Time in PERT three-point estimates?

  • (P + ML) / 2
  • (P + O) / 2
  • (P + 4ML + O) / 6 (correct)
  • (O + ML) / 3
  • What is the assumption made in the Pessimistic time estimate?

  • Major catastrophes will occur
  • Everything that can go wrong, will do, but major catastrophes are excluded (correct)
  • Everything will go as planned
  • The activity will take the minimum time required
  • What is the purpose of the Three-Point Estimate in PERT?

  • To get a weighted average of three different time estimates (correct)
  • To estimate the minimum time required for an activity
  • To estimate the maximum possible time required for an activity
  • To estimate the best time estimation of the accomplishment of an activity
  • What is the Optimistic time estimate in PERT based on?

    <p>The minimum time required to accomplish an activity, assuming things will go better than normally</p> Signup and view all the answers

    What is the formula to calculate the Resource Units per day?

    <p>Work / Resource Quantity</p> Signup and view all the answers

    What is the purpose of the Parametric Estimates?

    <p>To estimate the resource units required for an activity</p> Signup and view all the answers

    What is the assumption made in the Most Likely time estimate?

    <p>Everything goes as expected</p> Signup and view all the answers

    What is the purpose of the Triangular Distribution in PERT?

    <p>To estimate the uncertainty of an activity</p> Signup and view all the answers

    What is the formula to calculate the Duration?

    <p>Work / (Resource Units / day)</p> Signup and view all the answers

    What is the purpose of the Stopwatch Time Study?

    <p>To measure the time required to perform a task</p> Signup and view all the answers

    Study Notes

    Estimating Techniques

    • PERT (Program Evaluation and Review Technique) is a more accurate estimating method than the triangular estimate.
    • PERT three-estimates is the most applied estimating method by project managers.

    Triangular Distribution

    • Calculation: (P + ML + O) / 3
    • P: Pessimistic duration, ML: Most Likely duration, O: Optimistic duration

    Learning Curves

    • The learning effect: Time per repetition decreases as the number of repetitions increases

    Standard Time and Stopwatch Time Study

    • Standard time: The time it should take a fully trained and qualified worker to complete a specific task, working at an efficient, yet sustainable pace.
    • Observed time: The average of recorded times.
    • Normal time: Observed time adjusted for worker performance, calculated by multiplying observed time by a performance rating (NT = OT * PR).
    • Standard time: Normal time multiplied by an allowance factor for personal delays, unavoidable delays, and breaks (ST = NT * AF).

    Stopwatch Time Study

    • Example: Observed time 5 hours, normal time 6 hours, idle time 25%, standard time 7.5 hours (6 * (1 + 0.25)).

    Three-Point Estimate

    • Optimistic time: Minimum time required to accomplish an activity, assuming things will go better than normally.
    • Pessimistic time: Maximum possible time required to accomplish an activity, assuming everything that can go wrong, will do.
    • Most likely time: Best time estimation of the accomplishment of an activity, assuming everything goes as expected.
    • Expected time: Best estimation of the time needed to accomplish an activity, taking into account that complications might appear, calculated using the formula (P + 4ML + O) / 6.

    Parametric Estimates

    • Example: Resource Units/day = WBS Effort Hours / Resource Working Hours/day * % Availability
    • Duration (days) = Work / Resource Units

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz covers the PERT technique, a method used for estimating project tasks, which has been tested across various industries and countries. It also explores the triangular distribution formula used in PERT.

    More Quizzes Like This

    Use Quizgecko on...
    Browser
    Browser