Podcast
Questions and Answers
According to the guidelines for the use of OFC, what type of cable is typically used?
According to the guidelines for the use of OFC, what type of cable is typically used?
- 12/24 Fiber OFC with 4 quad jelly filled quad cable
- 36/60 Fiber OFC with 8 quad jelly filled quad cable
- 48/72 Fiber OFC with 10 quad jelly filled quad cable
- 24/48 Fiber OFC with 6 quad jelly filled quad cable (correct)
What method is used to lay All OFC according to the guidelines?
What method is used to lay All OFC according to the guidelines?
- Suspended aerially between poles
- Laid in PVC pipe using a pulling method
- Directly buried in the ground
- Laid in HDPE pipe using a blowing method (correct)
For what type of network is the IP-MPLS network installed?
For what type of network is the IP-MPLS network installed?
- Medium haul only
- Both short haul and long haul (correct)
- Long haul only
- Short haul only
What is the specified depth for a cable pit near an OFC room?
What is the specified depth for a cable pit near an OFC room?
How many RCC pipes are provided separately for OFC and quad cable?
How many RCC pipes are provided separately for OFC and quad cable?
Up to what length should the pipes be laid away from the cable pit?
Up to what length should the pipes be laid away from the cable pit?
In the procedure for '5 km charts', what length of the route should be covered by the charts?
In the procedure for '5 km charts', what length of the route should be covered by the charts?
What is the minimum distance to be maintained between ONE masts and the cable for OFC?
What is the minimum distance to be maintained between ONE masts and the cable for OFC?
Within a yard, what minimum distance from a ONE mast must be maintained with HDPE pipe?
Within a yard, what minimum distance from a ONE mast must be maintained with HDPE pipe?
How much tapping is provided for emergency control circuits?
How much tapping is provided for emergency control circuits?
What additional length is included for track crossing, apart from the actual measurement and contour allowance?
What additional length is included for track crossing, apart from the actual measurement and contour allowance?
According to the guidelines, what should the bending radius under tension be for armoured OFC during pulling?
According to the guidelines, what should the bending radius under tension be for armoured OFC during pulling?
What is the maximum pulling speed during the laying of cable by winch?
What is the maximum pulling speed during the laying of cable by winch?
What is the recommended temperature range for pouring bitumen compound into steel troughs to secure optic fiber cables?
What is the recommended temperature range for pouring bitumen compound into steel troughs to secure optic fiber cables?
What is the purpose of conducting a Duct Integrity Test (DIT) before blowing OFC cable?
What is the purpose of conducting a Duct Integrity Test (DIT) before blowing OFC cable?
Flashcards
24/48 Fiber OFC
24/48 Fiber OFC
Fiber optic cables with 6 quad jelly-filled quad cables
OFC Cable Installation
OFC Cable Installation
A method where OFC cables are installed in HDPE pipes using blowing techniques
IP-MPLS Network
IP-MPLS Network
A network suitable for both short and long-distance data transmission
Cable Pit Depth
Cable Pit Depth
Signup and view all the flashcards
Separate Cable Pipes
Separate Cable Pipes
Signup and view all the flashcards
Pipes for Cable Entry
Pipes for Cable Entry
Signup and view all the flashcards
Route Plan of OFC
Route Plan of OFC
Signup and view all the flashcards
"5 km charts"
"5 km charts"
Signup and view all the flashcards
OFC Clearance
OFC Clearance
Signup and view all the flashcards
Yard Clearance
Yard Clearance
Signup and view all the flashcards
Emergency Tapping
Emergency Tapping
Signup and view all the flashcards
Track Crossing Loop
Track Crossing Loop
Signup and view all the flashcards
Bridge/Culvert Length
Bridge/Culvert Length
Signup and view all the flashcards
Joint Cable Loop
Joint Cable Loop
Signup and view all the flashcards
OFC bend radius
OFC bend radius
Signup and view all the flashcards
Study Notes
- Optical Fiber Communication Systems are covered
Section I: OFC Usage Guidelines
- Use 24/48 fiber OFC with 6 quad jelly-filled quad cable
- All OFC should be laid in HDPE pipe via the blowing method
- Install an IP-MPLS network for both short and long haul distances
Section II
- Cable pits near OFC rooms should be 1.25 meters deep
- Two RCC pipes, each 100mm in diameter, are needed separately for OFC and quad cable
- Pipes should extend up to 2 meters from the cable pit, outside with a suitable slope; cable entry into the cable must be as smooth as possible
Section III: Route Plan
- Detailed surveying is needed to finalize the OFC route plan
Procedures (for "5 km charts")
-
"5 km charts covering a 5 km length of the route should be prepared (Scale: 10 cm = 1 km)
-
Start the cable route from the control office using a 30-meter steel tape
-
Maintain a minimum distance of 5.75 meters between ONE masts and the cable for OFC
-
Maintain Imtr from ONE masts in yards using HDPE pipes
-
Use 1 km to 1.2 km tapping for the emergency control circuit
Cable Length (for OFC System)
- Route length is determined as per actual measurement plus a contour allowance of 2.5%
- Extra length for track crossing is required, including 2.5 meters loop on each side
- 10 meters extra length is required on approaches/crossing the bridges and culverts on each side
- Maintain 5 meters of cable on either side of a major steel bridge
- Maintain 2.5 meters of cables on short bridges
- Keep a loop of 10 meters at every joint on either side
- A loop of 10 meters should be kept in the cable pit
Section VIII: Work Flow Diagram
-
Preparation of Materials, Tools & Equipment → Digging → Trenching → Laying of HDPE Duct → Sieved Earth Filling → Backfilling & Protective Covers (if any) → DIT (Duct Integrity Test) → Blowing of Cable → Completion
-
A Caterpillar tractor can be used for laying cable along the cable route, using an adjustable ripper, allowing a typical preparation of 1.20 meter depth
-
DIT should be carried out once laying is completed, per block section (8-10 km)
Paying Out Cable
- Under tension during a pull, the OFC bend radius is always at least 20 times the cable's diameter
- For armored OFC, the bending radius under tension during pulling should always be greater than 30 times the OFC's diameter
Laying Cable by Winch
- Pulling Tension: (1.1 times w) kg
- Bending Radius = 30 times D
- Pulling Speed: Max, 15 mtr./min.
- 10 to 15 meters of OFC should be kept in the next pit
Section IX: Cable Protection
- The chapter or section covers arrangements to prevent damage to the cable and to protect staff
Protection of Cables Crossing Bridges/Culverts
- Separate troughs should be used for laying 6 quad cable and OFC
- For smaller culverts/bridges, HDD should be adopted, with DWC pipe protection, ensuring the cable is minimum 2 mtrs below the bed of culverts/bridges.
- At major culverts & bridges use steel troughing, GI pipe, box/pipe, or channels
- Use bitumen to prevent theft
Measures Against Theft of Steel Troughs
- To prevent theft of optic fiber cable steel troughs filled with OFC, apply a bitumen compound to IS specification, supervised by a senior supervisor
- Bitumen should be poured when the temperature is 18°C or less
- Accurately measure and ensure the pouring temperature of the bitumen compound is not more than 140°C
- Fill the bitumen compound up to a height of approximately 60mm
Arrangement for Laying Fiber Optic Cable Across Girder Bridges
- For girder bridges up to a span length of 12 meters, use GI pipe
- For girder bridges of span length more than 12 meters, use steel trough
- Always use a separate trough for laying 6 quad cable
- Bricks are provided in cable trenching
Protection Arrangement on Cable Route
- B-class bricks must be placed after covering the cable duct
- Cable markers indicating route changes should be provided every 50 meters on the cable route
- Joint indicators shall be provided at all joints
- Standard stone and RCC type cable and joint markers must be provided
Cable Crossing Tracks and Level Crossing Gates
- Lay the cable in RCC/DWC ducts, maintaining the same depth as normal routes
- For cable road crossings, RCC/DWC ducts should be laid on the road for at least 2 meters from either side
- Depth at any track crossing should not be less than 1.2 meters with RCC/DWC duct
- Ensure the cable's bend radius is not less than 600mm when crossing a track
- When trenchless HDD is adopted, the minimum depth should be 1.2 meter/120 cm, * 120 cm for OFC and 100 cm for quad cable
- Use GI pipe in rocky areas, culverts, girder bridges, and PSC girder bridges; always keep 5 meters of cable at the ends
- OFC cables must be run through Class B GI pipes of 80 mm diameter, also for funnels
Back Filling of Trenches
- Maintain at least 120 mm from the surface of the last cable
- A PVC warning tape should be continuously laid at a depth of 500mm
- In case of labor shortage, make a video recording of the cable and its trench
Section X: Jointing and Termination
-
Two techniques for jointing OFC: Mechanical splice and Fusion splice
-
Mechanical splice aligns the axis of the two fibers and physically holds them together
-
Mechanical splicing may only be used to temporarily splice fibers
-
Fusion splicing applies localized heating (e.g., electric arc/flame) at the interface between butted, pre-aligned fiber ends, causing them soften and fuse together
-
Only use the fusion splicing technique now
Steps Involved in Jointing Cables
- Prepare the Cable for jointing
- Strip/cut the Cable
- Prepare cable and joint closure for splicing
- Strip and clean fibers
- Organize fibers and finish joint
- Seal joint closure
- Place the joint it a pit
Preparation of Cable for Jointing
-
During installation, coil a minimum of 10 meters of cable at each end in the jointing pit to provide slack for jointing
-
The pit must have sufficient length of the wall that the joint is mounted.
-
Subtract the closure length and add twice the minimum bending radius of the cable
-
A pit length of 1 meter is sufficient for most cables and joint closures
Stripping/Cutting the Cable
- Strip the cable's outer and inner sheath, staggering each sheath approximately 10mm from the one below
Stripping and Cleaning of Fiber
- Before splicing, strip each fiber's primary protective coating up to 50mm, using a fiber stripper
- After stripping, clean the fiber as close as possible to a perfect 90° face.
Splicing of the Fiber
- Ensure that it is fully automatic with microprocessor splicing machine
Fusion Splicing of Fiber
-
Dip the clean bare fiber in ethyl alcohol from the ultrasonic cleaner, and switch for 5 to 10 seconds
-
Then placing it a "v" groove of the splicing machine, ensure that there is I mm gap between
-
Then heat shrink the insulator
-
Precision alignment is also required for better connectivity
Mechanical Splicing of the Fiber
- Align the fiber in vi groove
- Using Index matched adhesive can help to seal the fibre ends
Other Factors Notes
- End to End tests
- 1310 nm = 0.40 db/km
- 1550nm = 0.25 db/km
For RCC Cable Route Marker
- All sides above ground to be painted in RED
For OFC Joint
- All sides above ground to be painted GREEN
For QUAD Joint:
- All sides above ground to be painted YELLOW
Duct Integrity Test (DIT)
- Carry out DIT before OFC cable blowing
- Determine that it is suitable for fitting
- Cable is set to a pressure of 10 Bar
- Leakage or a puncture can lead to failure in pressure testing
- Air should flow freely and have no discontinuities
- The test should also use a shuttle and Sponge twice the size of inner duct, passed with pressurized air.
The DIT test steps are
- Ensure no discontinuities by using pressurized air
- Ensure the duct inside the diameter of 150mm
- Conduct five bar pressure for 30 minutes, drop no more than 0.5 Bar
Shuttle Test
- A Diameter of 80% passed, diameter and the length should be recorded
Sponge Test
- Ensure to clean the surface of the area
Pressure Loss Test
- Measure pressure is 5 bar during loss
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.