Optical Fiber Communication Systems

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

According to the guidelines for the use of OFC, what type of cable is typically used?

  • 12/24 Fiber OFC with 4 quad jelly filled quad cable
  • 36/60 Fiber OFC with 8 quad jelly filled quad cable
  • 48/72 Fiber OFC with 10 quad jelly filled quad cable
  • 24/48 Fiber OFC with 6 quad jelly filled quad cable (correct)

What method is used to lay All OFC according to the guidelines?

  • Suspended aerially between poles
  • Laid in PVC pipe using a pulling method
  • Directly buried in the ground
  • Laid in HDPE pipe using a blowing method (correct)

For what type of network is the IP-MPLS network installed?

  • Medium haul only
  • Both short haul and long haul (correct)
  • Long haul only
  • Short haul only

What is the specified depth for a cable pit near an OFC room?

<p>1.25 meters (A)</p> Signup and view all the answers

How many RCC pipes are provided separately for OFC and quad cable?

<p>Two RCC pipes of 100mm diameter each (B)</p> Signup and view all the answers

Up to what length should the pipes be laid away from the cable pit?

<p>Up to 2 meter length (D)</p> Signup and view all the answers

In the procedure for '5 km charts', what length of the route should be covered by the charts?

<p>Covers a length of 5 km of the route (C)</p> Signup and view all the answers

What is the minimum distance to be maintained between ONE masts and the cable for OFC?

<p>A minimum distance of 5.75 mtr (B)</p> Signup and view all the answers

Within a yard, what minimum distance from a ONE mast must be maintained with HDPE pipe?

<p>1 meter (A)</p> Signup and view all the answers

How much tapping is provided for emergency control circuits?

<p>1 km to 1.2 km tapping (C)</p> Signup and view all the answers

What additional length is included for track crossing, apart from the actual measurement and contour allowance?

<p>2.5 meters loop on each side (C)</p> Signup and view all the answers

According to the guidelines, what should the bending radius under tension be for armoured OFC during pulling?

<p>Always be greater than 30 times the diameter of the OFC (C)</p> Signup and view all the answers

What is the maximum pulling speed during the laying of cable by winch?

<p>Max 15 mtr/min (C)</p> Signup and view all the answers

What is the recommended temperature range for pouring bitumen compound into steel troughs to secure optic fiber cables?

<p>Should be accurately measured to ensure that the pouring temperature is not more than 140°C (D)</p> Signup and view all the answers

What is the purpose of conducting a Duct Integrity Test (DIT) before blowing OFC cable?

<p>To determine the suitability of the duct for cable installation through jetting (D)</p> Signup and view all the answers

Flashcards

24/48 Fiber OFC

Fiber optic cables with 6 quad jelly-filled quad cables

OFC Cable Installation

A method where OFC cables are installed in HDPE pipes using blowing techniques

IP-MPLS Network

A network suitable for both short and long-distance data transmission

Cable Pit Depth

A pit near the OFC room with a depth of 1.25 meters

Signup and view all the flashcards

Separate Cable Pipes

Two separate pipes, each with a 100mm diameter, used for OFC and quad cables

Signup and view all the flashcards

Pipes for Cable Entry

Pipes laid up to 2 meters away from the cable pit with a suitable slope for smooth cable entry

Signup and view all the flashcards

Route Plan of OFC

Detailed survey and planning for the route of the OFC cable

Signup and view all the flashcards

"5 km charts"

Charts prepared in 5 km segments, with a scale of 10 cm = 1 km

Signup and view all the flashcards

OFC Clearance

Minimum distance to maintain between ONE masts and the OFC cable is 5.75 meters

Signup and view all the flashcards

Yard Clearance

A minimum clearance of 1 meter from ONE mast when in a yard, using HDPE pipe

Signup and view all the flashcards

Emergency Tapping

Providing tapping points every 1 to 1.2 km for emergency control circuits

Signup and view all the flashcards

Track Crossing Loop

Additional length included for track crossings, including a 2.5 meters loop on each side

Signup and view all the flashcards

Bridge/Culvert Length

Additional 10-meter length included for approaches/crossings of bridges and culverts on each side

Signup and view all the flashcards

Joint Cable Loop

At every joint, maintain a loop of 10 meters cable on either side

Signup and view all the flashcards

OFC bend radius

Bend radius should be at least 20 times the cable diameter to prevent damage

Signup and view all the flashcards

Study Notes

  • Optical Fiber Communication Systems are covered

Section I: OFC Usage Guidelines

  • Use 24/48 fiber OFC with 6 quad jelly-filled quad cable
  • All OFC should be laid in HDPE pipe via the blowing method
  • Install an IP-MPLS network for both short and long haul distances

Section II

  • Cable pits near OFC rooms should be 1.25 meters deep
  • Two RCC pipes, each 100mm in diameter, are needed separately for OFC and quad cable
  • Pipes should extend up to 2 meters from the cable pit, outside with a suitable slope; cable entry into the cable must be as smooth as possible

Section III: Route Plan

  • Detailed surveying is needed to finalize the OFC route plan

Procedures (for "5 km charts")

  • "5 km charts covering a 5 km length of the route should be prepared (Scale: 10 cm = 1 km)

  • Start the cable route from the control office using a 30-meter steel tape

  • Maintain a minimum distance of 5.75 meters between ONE masts and the cable for OFC

  • Maintain Imtr from ONE masts in yards using HDPE pipes

  • Use 1 km to 1.2 km tapping for the emergency control circuit

Cable Length (for OFC System)

  • Route length is determined as per actual measurement plus a contour allowance of 2.5%
  • Extra length for track crossing is required, including 2.5 meters loop on each side
  • 10 meters extra length is required on approaches/crossing the bridges and culverts on each side
  • Maintain 5 meters of cable on either side of a major steel bridge
  • Maintain 2.5 meters of cables on short bridges
  • Keep a loop of 10 meters at every joint on either side
  • A loop of 10 meters should be kept in the cable pit

Section VIII: Work Flow Diagram

  • Preparation of Materials, Tools & Equipment → Digging → Trenching → Laying of HDPE Duct → Sieved Earth Filling → Backfilling & Protective Covers (if any) → DIT (Duct Integrity Test) → Blowing of Cable → Completion

  • A Caterpillar tractor can be used for laying cable along the cable route, using an adjustable ripper, allowing a typical preparation of 1.20 meter depth

  • DIT should be carried out once laying is completed, per block section (8-10 km)

Paying Out Cable

  • Under tension during a pull, the OFC bend radius is always at least 20 times the cable's diameter
  • For armored OFC, the bending radius under tension during pulling should always be greater than 30 times the OFC's diameter

Laying Cable by Winch

  • Pulling Tension: (1.1 times w) kg
  • Bending Radius = 30 times D
  • Pulling Speed: Max, 15 mtr./min.
  • 10 to 15 meters of OFC should be kept in the next pit

Section IX: Cable Protection

  • The chapter or section covers arrangements to prevent damage to the cable and to protect staff

Protection of Cables Crossing Bridges/Culverts

  • Separate troughs should be used for laying 6 quad cable and OFC
  • For smaller culverts/bridges, HDD should be adopted, with DWC pipe protection, ensuring the cable is minimum 2 mtrs below the bed of culverts/bridges.
  • At major culverts & bridges use steel troughing, GI pipe, box/pipe, or channels
  • Use bitumen to prevent theft

Measures Against Theft of Steel Troughs

  • To prevent theft of optic fiber cable steel troughs filled with OFC, apply a bitumen compound to IS specification, supervised by a senior supervisor
  • Bitumen should be poured when the temperature is 18°C or less
  • Accurately measure and ensure the pouring temperature of the bitumen compound is not more than 140°C
  • Fill the bitumen compound up to a height of approximately 60mm

Arrangement for Laying Fiber Optic Cable Across Girder Bridges

  • For girder bridges up to a span length of 12 meters, use GI pipe
  • For girder bridges of span length more than 12 meters, use steel trough
  • Always use a separate trough for laying 6 quad cable
  • Bricks are provided in cable trenching

Protection Arrangement on Cable Route

  • B-class bricks must be placed after covering the cable duct
  • Cable markers indicating route changes should be provided every 50 meters on the cable route
  • Joint indicators shall be provided at all joints
  • Standard stone and RCC type cable and joint markers must be provided

Cable Crossing Tracks and Level Crossing Gates

  • Lay the cable in RCC/DWC ducts, maintaining the same depth as normal routes
  • For cable road crossings, RCC/DWC ducts should be laid on the road for at least 2 meters from either side
  • Depth at any track crossing should not be less than 1.2 meters with RCC/DWC duct
  • Ensure the cable's bend radius is not less than 600mm when crossing a track
  • When trenchless HDD is adopted, the minimum depth should be 1.2 meter/120 cm, * 120 cm for OFC and 100 cm for quad cable
  • Use GI pipe in rocky areas, culverts, girder bridges, and PSC girder bridges; always keep 5 meters of cable at the ends
  • OFC cables must be run through Class B GI pipes of 80 mm diameter, also for funnels

Back Filling of Trenches

  • Maintain at least 120 mm from the surface of the last cable
  • A PVC warning tape should be continuously laid at a depth of 500mm
  • In case of labor shortage, make a video recording of the cable and its trench

Section X: Jointing and Termination

  • Two techniques for jointing OFC: Mechanical splice and Fusion splice

  • Mechanical splice aligns the axis of the two fibers and physically holds them together

  • Mechanical splicing may only be used to temporarily splice fibers

  • Fusion splicing applies localized heating (e.g., electric arc/flame) at the interface between butted, pre-aligned fiber ends, causing them soften and fuse together

  • Only use the fusion splicing technique now

Steps Involved in Jointing Cables

  • Prepare the Cable for jointing
  • Strip/cut the Cable
  • Prepare cable and joint closure for splicing
  • Strip and clean fibers
  • Organize fibers and finish joint
  • Seal joint closure
  • Place the joint it a pit

Preparation of Cable for Jointing

  • During installation, coil a minimum of 10 meters of cable at each end in the jointing pit to provide slack for jointing

  • The pit must have sufficient length of the wall that the joint is mounted.

  • Subtract the closure length and add twice the minimum bending radius of the cable

  • A pit length of 1 meter is sufficient for most cables and joint closures

Stripping/Cutting the Cable

  • Strip the cable's outer and inner sheath, staggering each sheath approximately 10mm from the one below

Stripping and Cleaning of Fiber

  • Before splicing, strip each fiber's primary protective coating up to 50mm, using a fiber stripper
  • After stripping, clean the fiber as close as possible to a perfect 90° face.

Splicing of the Fiber

  • Ensure that it is fully automatic with microprocessor splicing machine

Fusion Splicing of Fiber

  • Dip the clean bare fiber in ethyl alcohol from the ultrasonic cleaner, and switch for 5 to 10 seconds

  • Then placing it a "v" groove of the splicing machine, ensure that there is I mm gap between

  • Then heat shrink the insulator

  • Precision alignment is also required for better connectivity

Mechanical Splicing of the Fiber

  • Align the fiber in vi groove
  • Using Index matched adhesive can help to seal the fibre ends

Other Factors Notes

  • End to End tests
  • 1310 nm = 0.40 db/km
  • 1550nm = 0.25 db/km

For RCC Cable Route Marker

  • All sides above ground to be painted in RED

For OFC Joint

  • All sides above ground to be painted GREEN

For QUAD Joint:

  • All sides above ground to be painted YELLOW

Duct Integrity Test (DIT)

  • Carry out DIT before OFC cable blowing
  • Determine that it is suitable for fitting
  • Cable is set to a pressure of 10 Bar
  • Leakage or a puncture can lead to failure in pressure testing
  • Air should flow freely and have no discontinuities
  • The test should also use a shuttle and Sponge twice the size of inner duct, passed with pressurized air.

The DIT test steps are

  • Ensure no discontinuities by using pressurized air
  • Ensure the duct inside the diameter of 150mm
  • Conduct five bar pressure for 30 minutes, drop no more than 0.5 Bar

Shuttle Test

  • A Diameter of 80% passed, diameter and the length should be recorded

Sponge Test

  • Ensure to clean the surface of the area

Pressure Loss Test

  • Measure pressure is 5 bar during loss

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Welding 170 OFC and OFW Flashcards
30 questions
OFC Laying: Guidelines and Best Practices
38 questions
Use Quizgecko on...
Browser
Browser