Which of the following is the primary focus of 'Line Balancing' in operations management?
Which of the following is the primary focus of 'Line Balancing' in operations management?
- Reducing the amount of raw materials used in production.
- Minimizing the total number of workstations in a production line.
- Ensuring an even distribution of work across workstations to prevent bottlenecks. (correct)
- Maximizing the utilization of the fastest workstation.
How does 'Finite Loading' differ from 'Infinite Loading' in job assignment?
How does 'Finite Loading' differ from 'Infinite Loading' in job assignment?
- Finite loading assigns jobs randomly, while infinite loading follows a predetermined sequence.
- Finite loading is used for short-term scheduling, while infinite loading is used for long-term planning.
- Finite loading assigns jobs to minimize idle time, while infinite loading maximizes resource utilization.
- Finite loading considers the capacity of work centers, while infinite loading does not. (correct)
Which scheduling method is most suitable when prioritizing jobs to minimize machine idle time and overall production time?
Which scheduling method is most suitable when prioritizing jobs to minimize machine idle time and overall production time?
- First Come, First Serve.
- Short Processing Time. (correct)
- Johnson's Rule.
- Earliest Due Date.
What is the primary goal of 'Queuing Analysis' in operations management?
What is the primary goal of 'Queuing Analysis' in operations management?
In the context of scheduling, what does 'ERP' primarily aim to achieve within a business?
In the context of scheduling, what does 'ERP' primarily aim to achieve within a business?
For a project with several dependent tasks, which method is used to determine the shortest possible completion time?
For a project with several dependent tasks, which method is used to determine the shortest possible completion time?
How does 'Backward Scheduling' differ from 'Forward Scheduling'?
How does 'Backward Scheduling' differ from 'Forward Scheduling'?
Which of the following is a key component of 'Material Requirements Planning (MRP)'?
Which of the following is a key component of 'Material Requirements Planning (MRP)'?
What is a primary consideration when applying 'Johnson's Rule'?
What is a primary consideration when applying 'Johnson's Rule'?
What is the main purpose of sequencing?
What is the main purpose of sequencing?
Flashcards
Scheduling Operation
Scheduling Operation
Assigning start dates to batches of individual components and designating work centers for each operation.
First Come, First Serve
First Come, First Serve
Prioritizes jobs based on the order they are received. Effective for single-product operations.
Short Processing Time
Short Processing Time
Prioritizes jobs that take the least time to complete, reducing machine idle time.
Earliest Due Date
Earliest Due Date
Signup and view all the flashcards
Johnson's Rule
Johnson's Rule
Signup and view all the flashcards
Critical Path Method (CPM)
Critical Path Method (CPM)
Signup and view all the flashcards
Material Requirements Planning (MRP)
Material Requirements Planning (MRP)
Signup and view all the flashcards
Infinite Loading
Infinite Loading
Signup and view all the flashcards
Finite Loading
Finite Loading
Signup and view all the flashcards
Sequencing
Sequencing
Signup and view all the flashcards
Study Notes
Scheduling Operation
- Scheduling assigns start dates to individual component batches and designates work centers for each operation.
- Objectives include minimizing time delays, reducing costs, optimizing resource utilization, and ensuring timely product delivery.
- It involves systematic planning and coordination of tasks, resources, and timelines to optimize production efficiency and meet customer demands.
First Come, First Serve
- Jobs are prioritized based on the order of receipt.
- It is more effective for single-product operations than for multiple product operations.
Short Processing Time
- Jobs that take the least time to complete are prioritized.
- This reduces machine idle time and overall production time.
Earliest Due Date
- Jobs are scheduled based on their due dates.
- Suitable for operations with varying deadlines.
Johnson's Rule
- Method to find the best job order in two work centers.
- Aims to reduce completion time and waiting time between work centers.
- Steps include:
- List jobs and their times at each work center.
- Find the job with the shortest time at the first work center and schedule it first.
- Find the job with the shortest time at the second work center and schedule it last.
- Remove the scheduled job from consideration and repeat the process until all jobs are scheduled.
Critical Path Method (CPM)
- Identifies the longest stretch of dependent tasks to determine the shortest time to complete a project.
- Used for analyzing, planning, and scheduling large, complex projects, determining the critical path.
Queuing Analysis
- Manages and optimizes the flow of jobs through a system by analyzing waiting times and resource utilization.
- "Queuing analysis" applies queuing theory to study and optimize waiting lines within a system.
- It Analyzes customer arrival rates, service times, number of servers, and queue discipline to improve operational efficiency and customer service by minimizing wait times and resource utilization
Enterprise Resource Planning (ERP)
- ERP integrates critical business operations into a unified database, streamlining the business environment.
- Manufacturing ERP systems plan, oversee, and support functions within manufacturing enterprises.
Material Requirements Planning (MRP)
- MRP is a technique for resource planning and inventory control.
- MRP systems gather data from customer demand and the bill of materials for specific product, using this information to develop purchasing plans and basic production schedules.
- It is widely used for production planning and scheduling.
Forward Scheduling
- Starts as early as possible.
- If a job is completed early but the customer wants the product on a specific day, the product will be held in inventory, increasing inventory levels.
Backward Scheduling
- Schedules as late as possible.
- It lowers inventory but increases the risk of delays; urgent orders may compromise existing orders.
Line Balancing
- Work is evenly distributed across workstations.
- Aims to avoid bottlenecks and maintain a smooth production flow.
Infinite Loading
- Jobs are assigned to work centers without regard for capacity constraints.
- It helps identify potential bottlenecks.
Finite Loading
- It considers the capacity of each work center.
- Ensures the processing time does not exceed available capacity.
Loading
- Assigns jobs to work centers and machines.
- Determines distribution across resources for efficient capacity utilization.
- Purpose: Focuses on the allocation of jobs to available resources, ensuring effective utilization of work centers and machines without overloading.
- Process: Assigns jobs to work centers and machines based on capacity and availability, using methods like infinite loading or finite loading.
- Impact on Production: Affects the overall distribution of work and can impact the balance of workload across different resources. Proper loading ensures resources are neither idle nor overloaded.
Sequencing
- Establishes the order jobs are processed at each work center.
- Based on priority rules to optimize workflow and minimize idle time and delays.
- Purpose: Determining the order of job processing to minimize setups, reduce waiting times, and improve overall efficiency.
- Process: Use priority rules like Shortest Processing Time (SPT), Earliest Due Date (EDD), or Critical Ratio (CR) to manage job flow.
- Impact on Production: Affects the flow of jobs through the production process. Effective sequencing can reduce idle times, minimize setup times, and improve the overall throughput of the system.
Job Assignments
- Matching the right technician to the right job based on skills, availability, and location.
- Ensures efficient job completion to the highest standard.
Route Planning
- Optimizes routes to minimize travel time and fuel consumption.
- It Uses mapping tools or GPS tracking software to identify the most efficient paths.
Time Management
- Allocates appropriate time slots for each job based on complexity and duration.
- Helps effectively manage the workload and avoid overbooking.
Last Minute Changes
- Handling last-minute changes in customer requirements can disrupt schedules.
- Requires quick adjustments to minimize the impact on service delivery.