Podcast
Questions and Answers
What is not required in conducting nuclear density test?
What is not required in conducting nuclear density test?
- The operator must wear thick clothes (correct)
- The operator must be licensed
- Units must be delivered in approved cases
- Radiation exposure limits must be specified
Which of the following is not the responsibility of a materials engineer?
Which of the following is not the responsibility of a materials engineer?
- Recording the concreting activity in the materials logbook
- Setting schedule for delivery of materials (correct)
- Getting samples for testing
- Analyzing test results
Where should the contractor's Materials Engineer directly report?
Where should the contractor's Materials Engineer directly report?
- DPWH Project Engineer
- DPWH Materials Engineer
- Contractors Project Engineer (correct)
- All of the above
Which of the following documents is prepared by a Materials Engineer?
Which of the following documents is prepared by a Materials Engineer?
During construction of a road project, if all the materials to be used are tested for quality, inspection is no longer required.
During construction of a road project, if all the materials to be used are tested for quality, inspection is no longer required.
Sample should be taken and sent to the regional offices or any private testing laboratories accredited by DPWH for testing, with a
Sample should be taken and sent to the regional offices or any private testing laboratories accredited by DPWH for testing, with a
As a Materials Engineer, what will you do with major honey-combed area that is considered as defective work?
As a Materials Engineer, what will you do with major honey-combed area that is considered as defective work?
If the strength of control specimen does not meet the requirements and not feasible to obtain cores due to structural consideration, as a Materials Engineer what will be your decision?
If the strength of control specimen does not meet the requirements and not feasible to obtain cores due to structural consideration, as a Materials Engineer what will be your decision?
A program of quality control works to be complied by the contractor which is prepared by DPWH:
A program of quality control works to be complied by the contractor which is prepared by DPWH:
What is the average deficiency in thickness of core specimen per lot where no payment is recommended on the project?
What is the average deficiency in thickness of core specimen per lot where no payment is recommended on the project?
Flashcards
What is test piling?
What is test piling?
A test used to determine the casting length of regular piles in bridge projects.
What is a Quality Control Program?
What is a Quality Control Program?
A document prepared by the DPWH outlining the quality control procedures that contractors must follow for a project.
What is the basis for accepting or rejecting construction materials?
What is the basis for accepting or rejecting construction materials?
This report is key to determining the acceptance or rejection of any construction material.
When is the monthly materials status report submitted to DPWH?
When is the monthly materials status report submitted to DPWH?
Signup and view all the flashcards
What is subgrade preparation?
What is subgrade preparation?
Signup and view all the flashcards
What are the core strength requirements for concrete acceptance?
What are the core strength requirements for concrete acceptance?
Signup and view all the flashcards
How long before approval should the contractor submit the job-mix formula?
How long before approval should the contractor submit the job-mix formula?
Signup and view all the flashcards
What causes too many voids in a completed asphalt pavement, except one?
What causes too many voids in a completed asphalt pavement, except one?
Signup and view all the flashcards
What does a negative G.I. value indicate about soil performance?
What does a negative G.I. value indicate about soil performance?
Signup and view all the flashcards
What happens when concrete control specimens fail and cores cannot be obtained?
What happens when concrete control specimens fail and cores cannot be obtained?
Signup and view all the flashcards
What is the main cause of scaling in newly constructed concrete pavement?
What is the main cause of scaling in newly constructed concrete pavement?
Signup and view all the flashcards
What is the correct way to sample aggregate base course in the laboratory if a splitter is not available?
What is the correct way to sample aggregate base course in the laboratory if a splitter is not available?
Signup and view all the flashcards
What tests are needed for quality determination of concrete course aggregate samples?
What tests are needed for quality determination of concrete course aggregate samples?
Signup and view all the flashcards
What is a common requirement when using manufactured fine aggregates?
What is a common requirement when using manufactured fine aggregates?
Signup and view all the flashcards
What is the required time for opening PCCP construction to traffic?
What is the required time for opening PCCP construction to traffic?
Signup and view all the flashcards
How should compaction be performed after spreading bituminous mix?
How should compaction be performed after spreading bituminous mix?
Signup and view all the flashcards
What document is sufficient for material acceptance for small steel bar projects?
What document is sufficient for material acceptance for small steel bar projects?
Signup and view all the flashcards
How long should concrete curing be performed?
How long should concrete curing be performed?
Signup and view all the flashcards
Is it true that one RCPC must be submitted for quality testing for every 50 RCPC?
Is it true that one RCPC must be submitted for quality testing for every 50 RCPC?
Signup and view all the flashcards
What is the average deficiency in core specimen thickness per lot that results in no payment?
What is the average deficiency in core specimen thickness per lot that results in no payment?
Signup and view all the flashcards
What type of Portland Cement is generally recommended for concreting?
What type of Portland Cement is generally recommended for concreting?
Signup and view all the flashcards
What happens when the average thickness per lot is deficient by 7mm?
What happens when the average thickness per lot is deficient by 7mm?
Signup and view all the flashcards
Is it true that the higher the PI value of the soil, the weaker its performance?
Is it true that the higher the PI value of the soil, the weaker its performance?
Signup and view all the flashcards
What should you do if you suspect materials delivered are different from those previously tested and passed?
What should you do if you suspect materials delivered are different from those previously tested and passed?
Signup and view all the flashcards
When should compaction be performed to attain the required density?
When should compaction be performed to attain the required density?
Signup and view all the flashcards
Which test is primarily conducted for building projects with three stories and above?
Which test is primarily conducted for building projects with three stories and above?
Signup and view all the flashcards
What is sampling in construction?
What is sampling in construction?
Signup and view all the flashcards
What types of tests are conducted in the field for road construction?
What types of tests are conducted in the field for road construction?
Signup and view all the flashcards
How many borings are required for large building projects?
How many borings are required for large building projects?
Signup and view all the flashcards
What is Quality Control work in construction?
What is Quality Control work in construction?
Signup and view all the flashcards
What is a Monthly Materials Report?
What is a Monthly Materials Report?
Signup and view all the flashcards
Which of the following is not the responsibility of the Materials Engineer?
Which of the following is not the responsibility of the Materials Engineer?
Signup and view all the flashcards
How is pavement curing done?
How is pavement curing done?
Signup and view all the flashcards
How do you know a sample placed in an oven is oven-dried?
How do you know a sample placed in an oven is oven-dried?
Signup and view all the flashcards
Where is the proper location to sample aggregates in a stockpile?
Where is the proper location to sample aggregates in a stockpile?
Signup and view all the flashcards
How should concrete cylinder samples be delivered to the laboratory?
How should concrete cylinder samples be delivered to the laboratory?
Signup and view all the flashcards
How is a slump test for concrete prepared?
How is a slump test for concrete prepared?
Signup and view all the flashcards
What kind of sample is commonly used for building projects?
What kind of sample is commonly used for building projects?
Signup and view all the flashcards
Who brings the sample for materials testing to a DPWH accredited laboratory?
Who brings the sample for materials testing to a DPWH accredited laboratory?
Signup and view all the flashcards
When should sampling and testing begin for fine and coarse aggregates?
When should sampling and testing begin for fine and coarse aggregates?
Signup and view all the flashcards
What is the best test to assess the quality of manufactured RCPC?
What is the best test to assess the quality of manufactured RCPC?
Signup and view all the flashcards
What should a Materials Engineer do if ordered asphalt is much colder than the job mix temperature?
What should a Materials Engineer do if ordered asphalt is much colder than the job mix temperature?
Signup and view all the flashcards
What happens when concrete testing results show a 15% deficiency?
What happens when concrete testing results show a 15% deficiency?
Signup and view all the flashcards
What is the conclusion if three cement specimens are tested, two pass but one fails by more than 20%?
What is the conclusion if three cement specimens are tested, two pass but one fails by more than 20%?
Signup and view all the flashcards
Why is an emulsifying agent added to emulsified asphalt?
Why is an emulsifying agent added to emulsified asphalt?
Signup and view all the flashcards
What is the main purpose of concrete curing?
What is the main purpose of concrete curing?
Signup and view all the flashcards
What should a Materials Engineer recommend if aggregates base materials pass all tests except for their grading?
What should a Materials Engineer recommend if aggregates base materials pass all tests except for their grading?
Signup and view all the flashcards
Study Notes
Nuclear Density Test Requirements
- Operator must be licensed
- Radiation exposure limits must be specified
- Units must be delivered in approved cases
Materials Engineer Responsibilities
- Getting samples for testing
- Analyzing test results
- Recording concreting activities in the materials logbook
- Reporting directly to DPWH Project Engineer
- Preparing materials logbooks
Compaction of Embankment
- 80% compaction is below the required 100%
- Adjust water content
- Use rollers with higher compactive efforts
Materials Engineer Job Duties
- Submitting samples for testing
- Preparing design mixes
- Checking job mix formulas
- Surveying and measuring line and grade (optional)
Material Testing and Quality Control
- Sample testing at regional offices or private labs accredited by DPWH
- Quality control is still needed if all materials are tested for quality
Defective Work (Honeycomb)
- Defective areas must be removed and replaced at contractor's expense
Control Specimen Strength
- If strength does not meet requirements, and cores are not feasible, payment is adjusted
Bridge Project Piling
- Piling length is determined using test piling
Concrete Acceptance Criteria
- Acceptance/rejection of construction materials is based on materials test reports
Monthly Materials Status Report
- Submitted to DPWH by the 25th day of the month
Subgrade Preparation
- Compaction of soil topping, cut fills and materials in embankments, and treatment of unsuitable materials
Concrete Acceptance
- Adequate average concrete cores strength is 85% of specified f'c, with no single core below 75%
Asphalt Pavement Testing
- Completed asphalt pavements with excessive voids are usually caused by inadequate rolling at temperatures that are too low, too much course aggregate , too little binder, too much fine aggregate
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers essential responsibilities and requirements for materials engineers, including testing procedures, compaction standards, and quality control measures. Learn about key duties such as sample analysis and logbook maintenance, as well as standards set by DPWH. Perfect for those in the construction and engineering fields.