Materials Engineering Responsibilities and Standards
10 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is not required in conducting nuclear density test?

  • The operator must wear thick clothes (correct)
  • The operator must be licensed
  • Units must be delivered in approved cases
  • Radiation exposure limits must be specified
  • Which of the following is not the responsibility of a materials engineer?

  • Recording the concreting activity in the materials logbook
  • Setting schedule for delivery of materials (correct)
  • Getting samples for testing
  • Analyzing test results
  • Where should the contractor's Materials Engineer directly report?

  • DPWH Project Engineer
  • DPWH Materials Engineer
  • Contractors Project Engineer (correct)
  • All of the above
  • Which of the following documents is prepared by a Materials Engineer?

    <p>Materials Logbook</p> Signup and view all the answers

    During construction of a road project, if all the materials to be used are tested for quality, inspection is no longer required.

    <p>False</p> Signup and view all the answers

    Sample should be taken and sent to the regional offices or any private testing laboratories accredited by DPWH for testing, with a

    <p>Sample card</p> Signup and view all the answers

    As a Materials Engineer, what will you do with major honey-combed area that is considered as defective work?

    <p>Removed and replaced at the expensed of the contractor</p> Signup and view all the answers

    If the strength of control specimen does not meet the requirements and not feasible to obtain cores due to structural consideration, as a Materials Engineer what will be your decision?

    <p>Payment will be made at an adjusted price</p> Signup and view all the answers

    A program of quality control works to be complied by the contractor which is prepared by DPWH:

    <p>Quality Control Program</p> Signup and view all the answers

    What is the average deficiency in thickness of core specimen per lot where no payment is recommended on the project?

    <p>More than 25mm</p> Signup and view all the answers

    Study Notes

    Nuclear Density Test Requirements

    • Operator must be licensed
    • Radiation exposure limits must be specified
    • Units must be delivered in approved cases

    Materials Engineer Responsibilities

    • Getting samples for testing
    • Analyzing test results
    • Recording concreting activities in the materials logbook
    • Reporting directly to DPWH Project Engineer
    • Preparing materials logbooks

    Compaction of Embankment

    • 80% compaction is below the required 100%
    • Adjust water content
    • Use rollers with higher compactive efforts

    Materials Engineer Job Duties

    • Submitting samples for testing
    • Preparing design mixes
    • Checking job mix formulas
    • Surveying and measuring line and grade (optional)

    Material Testing and Quality Control

    • Sample testing at regional offices or private labs accredited by DPWH
    • Quality control is still needed if all materials are tested for quality

    Defective Work (Honeycomb)

    • Defective areas must be removed and replaced at contractor's expense

    Control Specimen Strength

    • If strength does not meet requirements, and cores are not feasible, payment is adjusted

    Bridge Project Piling

    • Piling length is determined using test piling

    Concrete Acceptance Criteria

    • Acceptance/rejection of construction materials is based on materials test reports

    Monthly Materials Status Report

    • Submitted to DPWH by the 25th day of the month

    Subgrade Preparation

    • Compaction of soil topping, cut fills and materials in embankments, and treatment of unsuitable materials

    Concrete Acceptance

    • Adequate average concrete cores strength is 85% of specified f'c, with no single core below 75%

    Asphalt Pavement Testing

    • Completed asphalt pavements with excessive voids are usually caused by inadequate rolling at temperatures that are too low, too much course aggregate , too little binder, too much fine aggregate

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    ME Practical Problems PDF

    Description

    This quiz covers essential responsibilities and requirements for materials engineers, including testing procedures, compaction standards, and quality control measures. Learn about key duties such as sample analysis and logbook maintenance, as well as standards set by DPWH. Perfect for those in the construction and engineering fields.

    More Like This

    Use Quizgecko on...
    Browser
    Browser