Podcast
Questions and Answers
Network diagrams require familiarity with network conventions, such as the use of ______ and Nodes.
Network diagrams require familiarity with network conventions, such as the use of ______ and Nodes.
Arrow
There are two conventions for making a network diagram: Activity on Arrow (AOA) and Activity on Node (AON).
There are two conventions for making a network diagram: Activity on Arrow (AOA) and Activity on Node (AON).
AOA, AON
[Blank] are points in time that represent the beginning or end of activities.
[Blank] are points in time that represent the beginning or end of activities.
Events
Activities are dependent on each other and cannot begin until after the completion of all preceding ______.
Activities are dependent on each other and cannot begin until after the completion of all preceding ______.
Signup and view all the answers
The network diagram does not describe time relationships but rather ______ relationships.
The network diagram does not describe time relationships but rather ______ relationships.
Signup and view all the answers
The network diagram is hardly ever done by a single person and should involve input from various ______.
The network diagram is hardly ever done by a single person and should involve input from various ______.
Signup and view all the answers
The fundamental elements of PERT/CPM networking are activity, event, and ______.
The fundamental elements of PERT/CPM networking are activity, event, and ______.
Signup and view all the answers
Study Notes
- Network diagrams require familiarity with network conventions, such as the use of Arrow and Nodes.
- There are two conventions for making a network diagram: Activity on Arrow (AOA) and Activity on Node (AON).
- Events are points in time that represent the beginning or end of activities.
- Activities are dependent on each other and cannot begin until after the completion of all preceding activities.
- The network diagram does not describe time relationships but rather dependency relationships.
- The network diagram is hardly ever done by a single person and should involve input from various stakeholders.
- The fundamental elements of PERT/CPM networking are activity, event, and time.
- Dummy activities may be used in the network to distinguish two or more parallel activities.
- Duration of an activity is the time it takes to finish and is the span of time from the Early Start to its Early Finish or from its Late Start to its Late Finish.
- A path is a sequence of activities that leads from the starting node to the finishing node.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
Test your knowledge on network diagrams and PERT/CPM networking with this quiz! Learn about the conventions, elements, and relationships involved in creating network diagrams, as well as the use of dummy activities and paths. Whether you're studying project management or just interested in learning more about networking, this quiz is a great way to challenge yourself and deepen your understanding.