Podcast
Questions and Answers
What is the schedule variance for the project described?
What is the schedule variance for the project described?
What do a CPI value of 1.25 and an SPI value of 1.33 for a project indicate?
What do a CPI value of 1.25 and an SPI value of 1.33 for a project indicate?
Which aspects of a project may be influenced by a budget cut due to economic downturn?
Which aspects of a project may be influenced by a budget cut due to economic downturn?
If an influential stakeholder requests to complete the project earlier than planned, which two parameters are most likely to be affected by this change?
If an influential stakeholder requests to complete the project earlier than planned, which two parameters are most likely to be affected by this change?
Signup and view all the answers
Assume that a project manager wants to compress the schedule. Which technique could they utilize to achieve this goal effectively?
Assume that a project manager wants to compress the schedule. Which technique could they utilize to achieve this goal effectively?
Signup and view all the answers
What does a negative schedule variance (SV) indicate?
What does a negative schedule variance (SV) indicate?
Signup and view all the answers
How is the Schedule Performance Index (SPI) calculated?
How is the Schedule Performance Index (SPI) calculated?
Signup and view all the answers
What does a Schedule Performance Index (SPI) of 0.75 imply?
What does a Schedule Performance Index (SPI) of 0.75 imply?
Signup and view all the answers
Why is the Schedule Performance Index (SPI) important in project management?
Why is the Schedule Performance Index (SPI) important in project management?
Signup and view all the answers
How can a project manager use the graphical representation of performance variables over time?
How can a project manager use the graphical representation of performance variables over time?
Signup and view all the answers
Which of the following is true about the Triple Constraint in project management?
Which of the following is true about the Triple Constraint in project management?
Signup and view all the answers
What does the term 'schedule' refer to in project management?
What does the term 'schedule' refer to in project management?
Signup and view all the answers
In a situation where a project is behind schedule with no extra resources available, what must change according to the Triple Constraint?
In a situation where a project is behind schedule with no extra resources available, what must change according to the Triple Constraint?
Signup and view all the answers
Which of the following parameters are fundamental in Earned Value Management (EVM)?
Which of the following parameters are fundamental in Earned Value Management (EVM)?
Signup and view all the answers
What approach can a project manager take to meet a deadline approaching within a week when the project is behind schedule?
What approach can a project manager take to meet a deadline approaching within a week when the project is behind schedule?
Signup and view all the answers
How does the 'time is money' principle relate to the relationship between cost and schedule?
How does the 'time is money' principle relate to the relationship between cost and schedule?
Signup and view all the answers
Which parameter might need to change if a project manager wants to meet a deadline but does not have extra resources available?
Which parameter might need to change if a project manager wants to meet a deadline but does not have extra resources available?
Signup and view all the answers
What does the Triple Constraint indicate about making changes in project management?
What does the Triple Constraint indicate about making changes in project management?
Signup and view all the answers
In the context of a project, what does the term 'triple constraint' refer to?
In the context of a project, what does the term 'triple constraint' refer to?
Signup and view all the answers
Which project management objective does the Earned Value Technique (EVT) help in monitoring?
Which project management objective does the Earned Value Technique (EVT) help in monitoring?
Signup and view all the answers
In project management, contingency reserves are primarily used for what purpose?
In project management, contingency reserves are primarily used for what purpose?
Signup and view all the answers
Which type of estimation is less time-consuming but also less accurate than parametric and bottom-up estimation?
Which type of estimation is less time-consuming but also less accurate than parametric and bottom-up estimation?
Signup and view all the answers
What formula is used for Cost Performance Analysis in project management?
What formula is used for Cost Performance Analysis in project management?
Signup and view all the answers
What formula is used for Schedule Performance Analysis in project management?
What formula is used for Schedule Performance Analysis in project management?
Signup and view all the answers
When putting contingency reserves into project plans, which of the following statements about contingency reserves is NOT true?
When putting contingency reserves into project plans, which of the following statements about contingency reserves is NOT true?
Signup and view all the answers
What is the purpose of controlling costs in project management?
What is the purpose of controlling costs in project management?
Signup and view all the answers
Which document describes how the cost will be monitored and controlled in a project?
Which document describes how the cost will be monitored and controlled in a project?
Signup and view all the answers
What is the purpose of the cost performance baseline in project management?
What is the purpose of the cost performance baseline in project management?
Signup and view all the answers
Why must any change to the budget be approved before implementation?
Why must any change to the budget be approved before implementation?
Signup and view all the answers
What are the input items to the Control Cost process in project management?
What are the input items to the Control Cost process in project management?
Signup and view all the answers
What is planned value (PV) in project management?
What is planned value (PV) in project management?
Signup and view all the answers
How is planned value (PV) calculated in project management?
How is planned value (PV) calculated in project management?
Signup and view all the answers
What does PV represent in project management?
What does PV represent in project management?
Signup and view all the answers
Which formula is used to calculate the planned value for a project?
Which formula is used to calculate the planned value for a project?
Signup and view all the answers
What does schedule variance (SV) measure in project management?
What does schedule variance (SV) measure in project management?
Signup and view all the answers
Why is it important to calculate planned value (PV) in project management?
Why is it important to calculate planned value (PV) in project management?
Signup and view all the answers
How does planned value relate to budget at completion (BAC) in project management?
How does planned value relate to budget at completion (BAC) in project management?
Signup and view all the answers
What is the main purpose of calculating schedule variance (SV) in project management?
What is the main purpose of calculating schedule variance (SV) in project management?
Signup and view all the answers
From the provided text, what does Planned Value represent in terms of cost?
From the provided text, what does Planned Value represent in terms of cost?
Signup and view all the answers
Variance analysis is not a technique used to assess the magnitude of variation in the value of a variable from the baseline.
Variance analysis is not a technique used to assess the magnitude of variation in the value of a variable from the baseline.
Signup and view all the answers
The earned value technique (EVT) is commonly used to measure only the scope and schedule performance of a project.
The earned value technique (EVT) is commonly used to measure only the scope and schedule performance of a project.
Signup and view all the answers
In earned value management (EVM), the budgeted cost of work scheduled is compared with the actual cost of work performed.
In earned value management (EVM), the budgeted cost of work scheduled is compared with the actual cost of work performed.
Signup and view all the answers
The project cost and project schedule are unrelated to each other according to earned value management principles.
The project cost and project schedule are unrelated to each other according to earned value management principles.
Signup and view all the answers
Variance analysis is primarily focused on assessing deviations in project parameters such as quality and risk.
Variance analysis is primarily focused on assessing deviations in project parameters such as quality and risk.
Signup and view all the answers
Schedule Variance (SV) is calculated as EV minus PV in Earned Value Management.
Schedule Variance (SV) is calculated as EV minus PV in Earned Value Management.
Signup and view all the answers
A negative Schedule Variance (SV) indicates that the project is ahead of schedule.
A negative Schedule Variance (SV) indicates that the project is ahead of schedule.
Signup and view all the answers
Schedule Performance Index (SPI) is calculated by dividing EV by PV in Earned Value Management.
Schedule Performance Index (SPI) is calculated by dividing EV by PV in Earned Value Management.
Signup and view all the answers
An SPI value of 0.75 indicates that the project is progressing faster than planned.
An SPI value of 0.75 indicates that the project is progressing faster than planned.
Signup and view all the answers
All performance variables in Earned Value Management, except BAC, are calculated at different points in time as the project progresses.
All performance variables in Earned Value Management, except BAC, are calculated at different points in time as the project progresses.
Signup and view all the answers
Cost variance (CV) is calculated by subtracting the actual cost (AC) from the planned value (PV).
Cost variance (CV) is calculated by subtracting the actual cost (AC) from the planned value (PV).
Signup and view all the answers
The total planned value (PV) of a project is equal to the budget at completion (BAC).
The total planned value (PV) of a project is equal to the budget at completion (BAC).
Signup and view all the answers
The reserves are included in the cost baseline for projects.
The reserves are included in the cost baseline for projects.
Signup and view all the answers
Schedule variance (SV) and the schedule performance index (SPI) are calculated in terms of cost using actual cost (AC).
Schedule variance (SV) and the schedule performance index (SPI) are calculated in terms of cost using actual cost (AC).
Signup and view all the answers
Earned value analysis is primarily based on planned value (PV), earned value (EV), and actual cost (AC).
Earned value analysis is primarily based on planned value (PV), earned value (EV), and actual cost (AC).
Signup and view all the answers
The cost baseline is developed during the process of determining the budget for a project.
The cost baseline is developed during the process of determining the budget for a project.
Signup and view all the answers
In earned value management, the earned value of a project at a certain point indicates the budgeted cost of work performed.
In earned value management, the earned value of a project at a certain point indicates the budgeted cost of work performed.
Signup and view all the answers
If the planned value of a project is higher than the earned value, it indicates a favorable cost variance.
If the planned value of a project is higher than the earned value, it indicates a favorable cost variance.
Signup and view all the answers
Cost variance is calculated by subtracting the earned value from the actual cost of work performed.
Cost variance is calculated by subtracting the earned value from the actual cost of work performed.
Signup and view all the answers
In variance analysis, any deviation in project parameters from the baseline is considered irrelevant to project performance.
In variance analysis, any deviation in project parameters from the baseline is considered irrelevant to project performance.
Signup and view all the answers
The earned value is calculated using the formula EV = BAC × (work completed/total work required)
The earned value is calculated using the formula EV = BAC × (work completed/total work required)
Signup and view all the answers
Actual cost (AC) is the total cost actually incurred until a specific point on the timescale in performing the work for a project.
Actual cost (AC) is the total cost actually incurred until a specific point on the timescale in performing the work for a project.
Signup and view all the answers
Cost variance (CV) is calculated by subtracting the actual cost (AC) from the earned value (EV).
Cost variance (CV) is calculated by subtracting the actual cost (AC) from the earned value (EV).
Signup and view all the answers
The expected value of CV is always negative because we expect the earned value to be less than the actual cost.
The expected value of CV is always negative because we expect the earned value to be less than the actual cost.
Signup and view all the answers
A positive cost variance indicates better cost performance than expected, while a negative cost variance indicates worse cost performance than expected.
A positive cost variance indicates better cost performance than expected, while a negative cost variance indicates worse cost performance than expected.
Signup and view all the answers
The Estimate to Complete (ETC) is calculated as the Budget at Completion (BAC) minus Earned Value (EV).
The Estimate to Complete (ETC) is calculated as the Budget at Completion (BAC) minus Earned Value (EV).
Signup and view all the answers
Cost Performance Index (CPI) is calculated by dividing Earned Value (EV) by Actual Cost (AC).
Cost Performance Index (CPI) is calculated by dividing Earned Value (EV) by Actual Cost (AC).
Signup and view all the answers
Schedule Variance (SV) is calculated as the difference between Earned Value (EV) and Planned Value (PV).
Schedule Variance (SV) is calculated as the difference between Earned Value (EV) and Planned Value (PV).
Signup and view all the answers
Planned Value (PV) is calculated as Budget at Completion (BAC) times Time Passed divided by Total Schedule Time.
Planned Value (PV) is calculated as Budget at Completion (BAC) times Time Passed divided by Total Schedule Time.
Signup and view all the answers
The Cost Variance (CV) is calculated as the Actual Cost (AC) minus Earned Value (EV).
The Cost Variance (CV) is calculated as the Actual Cost (AC) minus Earned Value (EV).
Signup and view all the answers
The Budget at Completion (BAC) represents the total budget authorized for performing the project work.
The Budget at Completion (BAC) represents the total budget authorized for performing the project work.
Signup and view all the answers
Earned Value (EV) indicates the value of the actually performed work in terms of the approved budget for a project or project activity.
Earned Value (EV) indicates the value of the actually performed work in terms of the approved budget for a project or project activity.
Signup and view all the answers
The Budget at Completion (BAC) is also known as the Actual Cost (AC).
The Budget at Completion (BAC) is also known as the Actual Cost (AC).
Signup and view all the answers
Variance analysis primarily focuses on assessing deviations in project parameters such as quality and risk.
Variance analysis primarily focuses on assessing deviations in project parameters such as quality and risk.
Signup and view all the answers
The Performance Measurement Baseline (PMB) includes variables such as BAC, EV, and AC.
The Performance Measurement Baseline (PMB) includes variables such as BAC, EV, and AC.
Signup and view all the answers
Planned Value (PV) represents the total cost of the project work originally estimated in the project management plan.
Planned Value (PV) represents the total cost of the project work originally estimated in the project management plan.
Signup and view all the answers
Budget at Completion (BAC) is calculated differently depending on whether it is for the whole project or just a part of it.
Budget at Completion (BAC) is calculated differently depending on whether it is for the whole project or just a part of it.
Signup and view all the answers
Earned Value (EV) is equivalent to the Budgeted Cost for Work Scheduled (BCWS).
Earned Value (EV) is equivalent to the Budgeted Cost for Work Scheduled (BCWS).
Signup and view all the answers
Cost Performance Analysis focuses on how effectively money is being spent on the project work compared to set expectations.
Cost Performance Analysis focuses on how effectively money is being spent on the project work compared to set expectations.
Signup and view all the answers
The Schedule Performance Index (SPI) is calculated by dividing Earned Value (EV) by Actual Cost (AC).
The Schedule Performance Index (SPI) is calculated by dividing Earned Value (EV) by Actual Cost (AC).
Signup and view all the answers
Study Notes
- Schedule refers to performing work over a specific time period, while cost relates to the money spent for the work on a project during a certain timeframe.
- The relationship between cost and schedule is evident in the understanding that money is required to carry out scheduled activities.
- Planned value (PV), earned value (EV), and actual cost (AC) are fundamental parameters in Earned Value Management (EVM) that need close monitoring and development.
- Scope, schedule, and cost are interlinked in the triple constraint of project management, where changing one aspect affects the others.
- Schedule Variance (SV) is calculated as the difference between EV and PV, indicating if the project is ahead or behind schedule.
- Schedule Performance Index (SPI) measures the efficiency of the project schedule by comparing EV to PV, showing how the project is progressing compared to the planned pace.
- Contingency reserves are used to manage uncertainties in schedule duration and cost, and for addressing project objective overruns to meet stakeholder expectations.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on strategies to prevent cost overruns, manage change requests, and communicate with stakeholders in project cost management. Find out how to keep expenditures within the approved budget limits and ensure timely handling of change requests.