🎧 New: AI-Generated Podcasts Turn your study notes into engaging audio conversations. Learn more

IT Upgrade Project: Work Breakdown Structure Meeting
3 Questions
1 Views

IT Upgrade Project: Work Breakdown Structure Meeting

Created by
@ImpressedAqua

Podcast Beta

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What did the initial scope statement for the project primarily define?

  • Rough cost and schedule estimates
  • Hardware, software, and network requirements (correct)
  • Project charter and WBS
  • Signatures of key stakeholders
  • What was included in the project charter for the IT upgrade project?

  • Detailed inventory of current hardware, networks, and software
  • Security features for each desktop or laptop computer
  • Signatures of all employees for their IT assets
  • Rough cost and schedule estimates for the project (correct)
  • Why did Kim need to create a detailed inventory of all the current hardware, networks, and software?

  • To avoid scope creep in the project
  • To estimate rough cost and schedule for the project
  • To perform the upgrades for all employees’ IT assets (correct)
  • To develop a project charter and initial scope statement
  • Use Quizgecko on...
    Browser
    Browser