Podcast
Questions and Answers
Prior to conducting a soundness test on a domestic hot water system, what preliminary step is crucial?
Prior to conducting a soundness test on a domestic hot water system, what preliminary step is crucial?
- Ensuring the system is completely dry
- Performing a visual inspection to check all joints (correct)
- Applying jointing compound to all connections
- Insulating all exposed pipework
During the soundness testing of rigid pipework (copper and steel), after filling the system, how long should the system stand for temperature stabilization?
During the soundness testing of rigid pipework (copper and steel), after filling the system, how long should the system stand for temperature stabilization?
- 2 hours
- 1 hour
- 30 minutes (correct)
- 15 minutes
What is the recommended pressure level for testing rigid pipework if the system's working pressure is 3 bar?
What is the recommended pressure level for testing rigid pipework if the system's working pressure is 3 bar?
- 3.0 bar
- 6.0 bar
- 4.0 bar
- 4.5 bar (correct)
What is the procedure after increasing the pressure to 1.5 times the working pressure for testing the soundness of plastic pipe (polybutylene)?
What is the procedure after increasing the pressure to 1.5 times the working pressure for testing the soundness of plastic pipe (polybutylene)?
During the flushing and disinfection process, which standard is followed when adding disinfectant to the system?
During the flushing and disinfection process, which standard is followed when adding disinfectant to the system?
What is the objective of flushing and disinfecting a new hot water system?
What is the objective of flushing and disinfecting a new hot water system?
What is the final step in the flushing and disinfection process?
What is the final step in the flushing and disinfection process?
What parameters are typically measured during the commissioning procedure of a hot water system?
What parameters are typically measured during the commissioning procedure of a hot water system?
What should be checked to ensure correct operation of blending valves during commissioning?
What should be checked to ensure correct operation of blending valves during commissioning?
What is a crucial step to take with valves during the commissioning procedure?
What is a crucial step to take with valves during the commissioning procedure?
After completing a new hot water system installation, what documentation must be handed over to the customer?
After completing a new hot water system installation, what documentation must be handed over to the customer?
Which of the following is a key step during the decommissioning of a hot water system for maintenance?
Which of the following is a key step during the decommissioning of a hot water system for maintenance?
What safety measure should be taken regarding the heat source when decommissioning a hot water system?
What safety measure should be taken regarding the heat source when decommissioning a hot water system?
Why should open ends be capped during the decommissioning of a hot water system?
Why should open ends be capped during the decommissioning of a hot water system?
When temporarily decommissioning a hot water system for component replacement, what procedure regarding draining is most important?
When temporarily decommissioning a hot water system for component replacement, what procedure regarding draining is most important?
What is the correct procedure for temporary decommissioning?
What is the correct procedure for temporary decommissioning?
Which of the following items may necessitate temporary decommissioning?
Which of the following items may necessitate temporary decommissioning?
Under what circumstances would permanent decommissioning of a domestic hot water system be appropriate?
Under what circumstances would permanent decommissioning of a domestic hot water system be appropriate?
During permanent decommissioning, after the customer has been informed and the system is isolated, what action should be taken regarding the pipework?
During permanent decommissioning, after the customer has been informed and the system is isolated, what action should be taken regarding the pipework?
Which of the following steps is essential to include in the permanent decommissions process?
Which of the following steps is essential to include in the permanent decommissions process?
Flashcards
What is Soundness Testing?
What is Soundness Testing?
A test to ensure the integrity of pipework joints.
What is the First Step Before Soundness Testing?
What is the First Step Before Soundness Testing?
Before starting a soundness test, visually check all joints to ensure they are properly made.
First Steps in Soundness Testing (Rigid Pipe)
First Steps in Soundness Testing (Rigid Pipe)
- Slowly fill the system with water.
- Walk around the system to check for leaks.
- Leave to stand for 30 minutes (temperature stabilization).
- Attach the hydraulic test bucket.
Soundness Testing - Rigid Pipe
Soundness Testing - Rigid Pipe
Signup and view all the flashcards
Soundness testing plastic pipe
Soundness testing plastic pipe
Signup and view all the flashcards
What is Flushing?
What is Flushing?
Signup and view all the flashcards
What is Disinfecting?
What is Disinfecting?
Signup and view all the flashcards
Commissioning procedure steps?
Commissioning procedure steps?
Signup and view all the flashcards
What is Hot Water System Decommissioning?
What is Hot Water System Decommissioning?
Signup and view all the flashcards
When is Temporary Decommissioning Needed?
When is Temporary Decommissioning Needed?
Signup and view all the flashcards
Steps in Temporary Decommissioning?
Steps in Temporary Decommissioning?
Signup and view all the flashcards
Permanent Decommissioning
Permanent Decommissioning
Signup and view all the flashcards
Steps in Permanent Decommissioning
Steps in Permanent Decommissioning
Signup and view all the flashcards
Components needing periodic maintenance?
Components needing periodic maintenance?
Signup and view all the flashcards
Why is Visual Inspection Important?
Why is Visual Inspection Important?
Signup and view all the flashcards
Study Notes
- Key requirements for testing and decommissioning domestic hot water systems
Requirements of Testing, Commissioning and Decommissioning
- Testing procedures for ridged pipework and plastic pipework are essential.
- Flushing and disinfecting ensures water is wholesome.
- Commissioning and decommissioning procedures, both temporary and permanent are required.
Soundness Testing
- Before testing, visually inspect all joints to make sure they are correctly assembled.
- Look for open ends, soldered joints, tight compression joints and secure clips.
- Soundness tests for rigid pipes and plastic pipes differ.
Soundness Testing: Procedure
- Visual inspection.
- Setting up equipment.
- Testing period.
- Final check.
- Complete documentation.
Soundness Testing: Rigid Pipe (Copper and Steel)
- Slowly fill the system with water.
- Walk around the system checking for leaks.
- Leave the system for 30 minutes for temperature stabilization.
- Attach the hydraulic test bucket.
- Pump the system up to 1.5 times the working pressure; a system working at 3 bar should be tested at 4.5 bar.
- Leave for one hour.
- Check for any pressure drop; none is allowed.
- Rectify and re-test if necessary.
Soundness Testing: Plastic Pipe (Polybutylene)
- Slowly fill the system with water.
- Walk around the system and check for leaks.
- Pump system to 1 bar; check for loss of pressure after 45 minutes.
- Increase pressure to 1.5 times the working pressure for 15 minutes.
- Check for pressure loss.
- Reduce pressure to one-third for a further 45 minutes, then check for pressure loss.
- Main point is to avoid damaging the plastic pipe or O rings.
Flushing and Disinfecting
- New systems or pipework sections must be flushed to remove debris.
- Pipes must be prepared to carry safe, wholesome water.
- Refill the system with water, then drain it from the lowest point.
- Re-fill the system.
- Open the kitchen tap and allow water to run until it is clear of debris or discoloration.
- Repeat for all other outlets in the property.
- Add disinfectant, either sodium hypochlorite solution or chlorine, to the system for 1 hour.
- Follow standard BS EN 806.
Flushing and Disinfecting Continued
- Chlorine levels must be tested at each outlet as per BS EN 806.
- Drain the system.
- Flush the system through from each outlet until no chlorine is present.
Commissioning
- Flow rate pressure must be measured using appropriate tools, such as a weir cup or pressure gauge.
- Flush to remove dirt and debris as per BS EN 806.
- Open all draw-off points, making sure they open and shut off.
- Open and close all valves to ensure operation, and ensure valves are labeled.
- Ensure correct thermostat and blending valve temperature settings and inform the customer.
- Ensure correct temperature at draw-off points and record.
- Check the overall operation of the system, then complete documentation.
- The customer should be shown all settings and valves; must also receive manufacturer's instructions; benchmark and warranty certificates.
Decommissioning
- Decommissioning a hot water system for maintenance and component replacement is a critical task.
- Key steps include informing the customer, identifying components and safely isolating the heat source.
- A warning notice must be placed on the heat source and fuses removed.
- The system must be drained to a safe location with open ends capped and no dead legs left.
Temporary Decommissioning
- Temporary decommissioning occurs when a component or appliance needs replacement.
- Customer must be informed.
- The system must be safely isolated and labeled.
- A hose pipe must be connected to a suitable drain point and discharged to a below-ground drain.
- The part is then replaced, and the system is refilled and tested.
- Common items requiring temporary decommissioning include hot water cylinders, cold water storage cisterns, boilers, showers, valves, appliances, and terminal fittings.
Permanent Decommissioning
- Permanent decommissioning occurs when an old system is replaced or a building is prepared for demolition.
- Customer must be informed.
- The system must be safely isolated and labeled.
- A hose pipe must be connected to a suitable drain point and discharged to a below-ground drain.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.