Questions and Answers
What does GP3 require regarding the balance of risk/reward allocation?
Under the Red Book, which responsibility is retained by the Employer?
Which condition does not comply with GP3?
What is required from the Employer prior to the Base Date?
Signup and view all the answers
What obligation does the Contractor have regarding the Engineer's data requirements?
Signup and view all the answers
Which of the following statements reflects a misconception about the Contractor's responsibilities?
Signup and view all the answers
How does GP3 relate to GP1?
Signup and view all the answers
Which situation exemplifies a proper application of GP3?
Signup and view all the answers
Which of the following scenarios illustrates a violation of GP3's principles?
Signup and view all the answers
In the context of GP3, what is the importance of the Employer's obligations?
Signup and view all the answers
What aspect of the Contractor's design responsibilities under the Red Book reflects compliance with GP3?
Signup and view all the answers
Which of the following best describes a condition that complies with GP3 regarding the Contractor's commercialization?
Signup and view all the answers
What is one key requirement for the Employer prior to the Contractor submitting a detailed time programme?
Signup and view all the answers
Which responsibility cannot be displaced according to GP3 regulations?
Signup and view all the answers
Identifying which of these obligations violates the principles of GP3 is crucial.
Signup and view all the answers
How does GP3 maintain a fair risk/reward allocation when the Contractor interprets site data?
Signup and view all the answers
Study Notes
GP3: Particular Conditions and Risk/Reward Balance
- GP3 states that particular conditions of contract should not alter the balance of risk and reward allocated in the General Conditions (GCs).
- GP3 is closely linked to GP1, which emphasizes the importance of a fair and balanced allocation of risk and reward.
-
Examples of complying with GP3:
- Requiring the contractor to design minor parts of the works under a Red or Pink Book contract.
- The employer providing the contractor with relevant data on sub-surface and hydrological conditions before the base date.
- The employer providing storage facilities for the contractor outside the site.
- The contractor providing the engineer with a detailed time programme in a specified format as a precondition for receiving an interim payment certificate.
-
Examples of conditions that do not comply with GP3:
- Requiring the contractor to design the majority of the works under a Red or Pink Book contract.
- The contractor assuming the risk of unforeseeable physical conditions under a Red, Pink, or Yellow Book.
- The contractor not being held responsible for the work carried out by its subcontractors.
- Omitting the contractor's right to compensation for delays or costs incurred due to the employer's failure to provide access to the site.
- GP3 reinforces the importance of ensuring that particular conditions maintain a fair and balanced approach to risk and reward allocation as established in the General Conditions.
GP3: Particular Conditions
- Definition: Particular Conditions must not alter the balance of risk/reward allocation established by the General Conditions (GCs).
- Relationship with GP1: GP3 is directly linked to GP1 because significant changes to roles, duties, obligations, and rights under the GCs inevitably affect the fair and balanced risk/reward allocation.
Examples of Proper Application of GP3
- Contractor Designing Minor Parts: Requiring the contractor to handle minor design aspects under a Red or Pink Book contract is acceptable. This maintains the Employer's primary design responsibility and liability.
-
Employer Providing Sub-surface and Hydrological Data: The Employer is obligated to provide pre-Base Date data on site conditions to the Contractor.
- The Employer remains responsible for the correctness and completeness of this data.
- The Contractor is accountable for interpreting this data correctly.
- Employer Providing Storage Facilities: The Employer agreeing to provide off-site storage for the Contractor is in line with GP3.
- Contractor Providing Time Program Data: Requiring the Contractor to submit a detailed and resourced time program in a specified format before receiving Interim Payment Certificates aligns with GP3.
Examples of Conditions that Violate GP3
- Contractor Designing Majority of Works: Placing the primary responsibility and liability for design on the Contractor under Red or Pink Book contracts contradicts GP3.
- Contractor Assuming Risk of Unforeseeable Conditions: Making the Contractor responsible for risks associated with unforeseeable physical conditions under Red, Pink, or Yellow Books is a GP3 violation.
- No Liability for Subcontractor Work: Excluding the Contractor from responsibility or liability for its Subcontractors' actions breaks the risk/reward balance of GP3.
- Omitting Compensation for Access Delays: Leaving out the Contractor's rights to compensation for delays or costs arising from the Employer's failure to provide timely access to the site is a violation of GP3. This refers to Red, Yellow, or Silver Book Sub-Clause 2.1.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
This quiz focuses on GP3, which highlights that specific contract conditions must not disrupt the intended risk and reward balance established in the General Conditions. It provides examples of compliant and non-compliant practices related to contractor responsibilities and employer provisions. Test your understanding of these principles.