Podcast
Questions and Answers
When is a working space of 0.25 m allowed during excavation measurement?
When is a working space of 0.25 m allowed during excavation measurement?
- When the formwork exceeds 1.0m in height regardless of how far below the starting level it is.
- When the formwork does not exceed 0.60m in height and the bottom of the formwork does not exceed 0.60m below the starting level. (correct)
- When the formwork exceeds 0.60m in height and the bottom of the formwork is more than 0.60m below the starting level.
- When the formwork does not exceed 0.60m in height or the bottom of the formwork is less than 0.60m below the starting level.
What is the primary advantage of using bored piling in construction?
What is the primary advantage of using bored piling in construction?
- It produces minimal vibration and lower noise levels, making it suitable for urban environments. (correct)
- It can reach depths of up to 100 meters, deeper than any other piling method.
- It is more cost-effective compared to other piling methods, reducing overall project expenses.
- It requires a smaller construction site footprint, allowing for use in congested areas.
In what unit of measurement is excavation for foundations typically recorded?
In what unit of measurement is excavation for foundations typically recorded?
- m4
- m3 (correct)
- m
- m2
When measuring excavation for foundations, what detail must be stated?
When measuring excavation for foundations, what detail must be stated?
When measuring excavation for foundations, in what increments are successive stages measured?
When measuring excavation for foundations, in what increments are successive stages measured?
How is concrete generally measured in concrete works?
How is concrete generally measured in concrete works?
When measuring concrete works, when should different concrete mixes be measured separately?
When measuring concrete works, when should different concrete mixes be measured separately?
According to the provided text, what determines the extent of formwork measurement?
According to the provided text, what determines the extent of formwork measurement?
According to HKSMM4, which of the following is NOT a major work item covered in the excavation section?
According to HKSMM4, which of the following is NOT a major work item covered in the excavation section?
What is the primary purpose of site clearance as the first construction procedure?
What is the primary purpose of site clearance as the first construction procedure?
According to HKSMM4, what is typically included in excavation work, removing the need for separate measurement?
According to HKSMM4, what is typically included in excavation work, removing the need for separate measurement?
A construction project involves surface excavation to reduce the level of a site. The average depth of the excavation is 0.18m. How is this excavation measured according to HKSMM4?
A construction project involves surface excavation to reduce the level of a site. The average depth of the excavation is 0.18m. How is this excavation measured according to HKSMM4?
A project requires excavation for a building foundation. According to HKSMM4, where can specific measurement guidelines for basement and foundation excavations be found?
A project requires excavation for a building foundation. According to HKSMM4, where can specific measurement guidelines for basement and foundation excavations be found?
According to HKSMM4, what is the implication of the rule stating that excavation includes excavating in any ground encountered?
According to HKSMM4, what is the implication of the rule stating that excavation includes excavating in any ground encountered?
A construction site requires filling to make up levels for a terrace. According to the provided content, which section of HKSMM4 covers this work item?
A construction site requires filling to make up levels for a terrace. According to the provided content, which section of HKSMM4 covers this work item?
Site clearance is identified as the first construction procedure. Which activity is NOT a standard part of site clearance?
Site clearance is identified as the first construction procedure. Which activity is NOT a standard part of site clearance?
When measuring formwork for slabs, which of the following deductions should be made from the overall slab area?
When measuring formwork for slabs, which of the following deductions should be made from the overall slab area?
Formwork to soffits with strutting height exceeding 3.5m is measured:
Formwork to soffits with strutting height exceeding 3.5m is measured:
Regarding formwork at the junction between structural walls and columns, what is the correct measurement practice?
Regarding formwork at the junction between structural walls and columns, what is the correct measurement practice?
Up to what point is formwork measured for the interior sides of columns and walls?
Up to what point is formwork measured for the interior sides of columns and walls?
How is formwork measured on the exterior sides of columns and walls?
How is formwork measured on the exterior sides of columns and walls?
What is the correct approach to measuring formwork for secondary beams that intersect main beams?
What is the correct approach to measuring formwork for secondary beams that intersect main beams?
Which of the following describes 'Left-in formwork'?
Which of the following describes 'Left-in formwork'?
For what purpose is strutting or propping used in formwork?
For what purpose is strutting or propping used in formwork?
When measuring concrete works according to HKSMM4, what should be deducted from the area of a beam?
When measuring concrete works according to HKSMM4, what should be deducted from the area of a beam?
According to the principles outlined for measuring reinforcement, how should reinforcing bars be categorized for separate measurement?
According to the principles outlined for measuring reinforcement, how should reinforcing bars be categorized for separate measurement?
Why is concrete cover considered when calculating the length of reinforcing bars?
Why is concrete cover considered when calculating the length of reinforcing bars?
What is the unit of measurement for fabric reinforcement, according to the guidelines provided?
What is the unit of measurement for fabric reinforcement, according to the guidelines provided?
If you know the length of a reinforcing bar, how do you calculate its weight for measurement purposes?
If you know the length of a reinforcing bar, how do you calculate its weight for measurement purposes?
According to BS4466, what is the formula to calculate the length of a single stirrup (shape code 61), considering 'h' as height, 'w' as width, 'cr' as concrete cover, and 'd' as bar diameter?
According to BS4466, what is the formula to calculate the length of a single stirrup (shape code 61), considering 'h' as height, 'w' as width, 'cr' as concrete cover, and 'd' as bar diameter?
In the context of reinforcing bars in columns, what do the abbreviations 'H', 't', and 'T.A.L.' stand for in the formula L = H – t + T.A.L. for calculating the length of a vertical bar?
In the context of reinforcing bars in columns, what do the abbreviations 'H', 't', and 'T.A.L.' stand for in the formula L = H – t + T.A.L. for calculating the length of a vertical bar?
Why is it essential to use dimension papers while measuring excavation, formwork, and concrete for a strip foundation?
Why is it essential to use dimension papers while measuring excavation, formwork, and concrete for a strip foundation?
In reinforced concrete slabs, what does 'a' represent in the formula N = (a - 2b) / s + 1, used to calculate the number of top bars?
In reinforced concrete slabs, what does 'a' represent in the formula N = (a - 2b) / s + 1, used to calculate the number of top bars?
When calculating the required number of binders in reinforced concrete, what does s
represent in the expression $(H – t_2 – 2a) / s + 1`?
When calculating the required number of binders in reinforced concrete, what does s
represent in the expression $(H – t_2 – 2a) / s + 1`?
What preliminary step is MOST crucial before starting the measurement of rebars according to provided hints?
What preliminary step is MOST crucial before starting the measurement of rebars according to provided hints?
What primarily should an estimator use to group items with similar numbers or calculations according to provided hints?
What primarily should an estimator use to group items with similar numbers or calculations according to provided hints?
When preparing for an oral presentation, what is the recommended practice regarding visual aids?
When preparing for an oral presentation, what is the recommended practice regarding visual aids?
In the formula for calculating the number of binders: N = (H – t2 – 2a) / s + 1
, what does t2
represent?
In the formula for calculating the number of binders: N = (H – t2 – 2a) / s + 1
, what does t2
represent?
What action MUST students take to confirm their participation and contribution to a group project?
What action MUST students take to confirm their participation and contribution to a group project?
Regarding submission deadlines for group project written reports, what are the requirements?
Regarding submission deadlines for group project written reports, what are the requirements?
Flashcards
HKSMM4
HKSMM4
A document providing standard rules for measuring construction work quantities in Hong Kong.
Information in HKSMM4
Information in HKSMM4
- Classification table 2. Measurement rules 3. Supplementary rules.
Site Clearance
Site Clearance
The initial preparation of a construction site, including removing trees, brushes, stumps, and roots.
Excavation
Excavation
Signup and view all the flashcards
Major Work Items in Excavation (HKSMM4)
Major Work Items in Excavation (HKSMM4)
Signup and view all the flashcards
Shallow Excavation Depth
Shallow Excavation Depth
Signup and view all the flashcards
Excavation Risk Assumption
Excavation Risk Assumption
Signup and view all the flashcards
Deep Excavations
Deep Excavations
Signup and view all the flashcards
Working Space (Excavation)
Working Space (Excavation)
Signup and view all the flashcards
Bored Pile
Bored Pile
Signup and view all the flashcards
Excavation Measurement Units
Excavation Measurement Units
Signup and view all the flashcards
Concrete Measurement Units
Concrete Measurement Units
Signup and view all the flashcards
Separate Concrete Mixes
Separate Concrete Mixes
Signup and view all the flashcards
Formwork surface
Formwork surface
Signup and view all the flashcards
Formwork Definition
Formwork Definition
Signup and view all the flashcards
Formwork Measurement Units
Formwork Measurement Units
Signup and view all the flashcards
Fair Faced Formwork
Fair Faced Formwork
Signup and view all the flashcards
Left-in Formwork
Left-in Formwork
Signup and view all the flashcards
Permanent Formwork
Permanent Formwork
Signup and view all the flashcards
Slab Formwork Area
Slab Formwork Area
Signup and view all the flashcards
Strutting/Propping
Strutting/Propping
Signup and view all the flashcards
Formwork Height Measurement
Formwork Height Measurement
Signup and view all the flashcards
Interior Formwork Measurement
Interior Formwork Measurement
Signup and view all the flashcards
Beam Formwork Measurement
Beam Formwork Measurement
Signup and view all the flashcards
Number of Binders Calculation
Number of Binders Calculation
Signup and view all the flashcards
Top Bar Calculation in Slab
Top Bar Calculation in Slab
Signup and view all the flashcards
Take-off list
Take-off list
Signup and view all the flashcards
Blanket Descriptions
Blanket Descriptions
Signup and view all the flashcards
Excavation Measurement
Excavation Measurement
Signup and view all the flashcards
Group project work allocation
Group project work allocation
Signup and view all the flashcards
Presentation Expectation
Presentation Expectation
Signup and view all the flashcards
Beam Soffit Deduction
Beam Soffit Deduction
Signup and view all the flashcards
Wall & Column Area Deduction
Wall & Column Area Deduction
Signup and view all the flashcards
Adjustments for Other Items
Adjustments for Other Items
Signup and view all the flashcards
Reinforcement Measurement
Reinforcement Measurement
Signup and view all the flashcards
Concrete Cover
Concrete Cover
Signup and view all the flashcards
Units for Reinforcement
Units for Reinforcement
Signup and view all the flashcards
Rebar Weight Calculation
Rebar Weight Calculation
Signup and view all the flashcards
Stirrup Length Formula
Stirrup Length Formula
Signup and view all the flashcards
Study Notes
- The presentation covers SEHS3290, Measurement, Documentation and Estimating.
- The lecture focuses on the Measurement of Excavation and Concrete Works.
- Dr. Joseph Chan is the presenter.
Contents Overview
- Introduction to the format of HKSMM4.
- Measurement of excavation.
- Measurement of foundations.
- The presentation includes an in-class exercise.
- Measurement of concrete works.
Introduction to the Format of HKSMM4
- The lecture references HKSMM4 as its basis.
- HKSMM4 provides information in the form of:
- Classification table
- Measurement rules
- Supplementary rules
General Principles of Measurement
- Bills of Quantities (BoQ) should accurately represent the work with clear descriptions of materials and workmanship.
- Supplementary information defining tolerances, methods, or sequences must be included in the descriptions or elsewhere to clarify the work's nature.
- This Standard Method of Measurement provides uniform units of measurement.
- Discretion is expected in special cases but should remain clear to the estimator.
- More detailed information can be provided for improved accuracy.
- Deviations and qualifications to the standard method shall be stated in the BoQ preambles or item descriptions.
- Measurement methods should apply to both the preparation of BoQ before work and the measurement of finished work.
- Linear measurements are taken to the nearest whole meter.
- If the unit of billing is the metre, quantities are billed to the nearest whole unit; fractions less than half are disregarded.
- Kilograms are billed to the nearest whole unit.
- Dimensions should be given consistently in the sequence of length, width, and height.
Measurement of Excavation
- Site clearance and excavation are part of the first construction procedure.
- Major work items are covered in Section VI of HKSMM4.
- In general, the nature of the soil should be described in the documentation.
- The items covered include site clearance, excavation, earth support, disposal, backfilling, filling, hardcore or granular filling, blinding, and surface treatment.
Site Clearance
- Site must be cleared before construction work begins by removing trees and brushes.
- Stumps and roots must be removed resulting in a level ground surface.
- HKSMM4 P.45 lists to items to be included.
- Refer to Figure 12.1 in the notes for measurement of tree girth.
Excavation
- According to HKSMM4 P. 46, VI (a).C.3 excavation includes excavation in any ground encountered.
- Contractors take on the risk excavating in any encountered ground including rocks.
- The rule applies to surface, trench, and basement excavation work.
- For surface excavation and over site excavation to reduced level, the average depth is less than or equal to 0.20m, measured in square meters.
- Over site excavation to reduced level is more than 0.2m deep.
Excavation for Basements and Foundations
- Refer to VI(a).3.4-3.7 for excavation rules for basements, trenches below basement level, foundations, etc.
- Measurement is done in cubic meters.
- State the commencing level.
- Measure in successive stages of 1.50m.
Working Space
- VI(a)..M2 states that working space needs to be included according to the following.
- Allow 0.25 m working space if formwork does not exceed 0.60m high and the bottom of the formwork does not exceed 0.60m below the starting excavation level.
Measurement of Foundation
- Foundations usually use replacement nature bored piles formed in-situ, using a non-percussion approach.
- Bored piles cast-in-place concrete on the construction site.
- A bored piling machine casts the piles using designed drilling tools, buckets and grabs, to remove soil and rock.
- Drilling can reach depths of 50 meters.
- Reinforcement bar put into bore hole; concrete poured into the bore hole.
- The method produces less vibration and noise.
- Bored piling is often used in construction as a foundation, especially for bridges and tall buildings.
Measurement of Concrete Works
- Refer to Section VII(a).1 Concrete Works.
- Concrete is generally measured in cubic meters, unless otherwise stated.
- Different concrete mixes should be measured separately (e.g., Grade 45/20).
- Formwork is measured to the surface of the finished structure that requires support during casting; refer to VII(d).M1.
Concrete Types and Components
- Reinforced in situ concrete and plain in situ concrete.
- Watertight reinforced concrete.
- Concrete in casing to structural steelwork.
- Precast concrete.
- Prestressed in situ concrete and precast prestressed concrete.
- Lightweight concrete.
- Gun applied reinforced concrete, measured in square meters.
- Common components: Blinding layers, small bases for fencing posts, beds, surface channels, foundations, column bases, pile caps, suspended slabs and roofs , strings, filling, walls, columns, piers, and staircases.
Concrete in Slab and Beam
- Slab dimensions measured across beams and columns
Concrete Walls
- Concrete walls are measured between columns or projections and up to the soffits of beams and slabs.
- If the width of a column is four times greater than its thickness, it is classified as a wall
Measurement of Formwork
- Section VII(d).1 governs formwork.
- Measurement is in square meters unless specified otherwise
- Includes formwork that produces a fair faced finish.
- Left-in, permanent to both faces, and permanent to one face only formwork.
- Includes formwork to different components of the buildings.
- For Soffits refer to Section VII(d) 2-3 and the following steps.
- Measure overall slab area.
- Deduct area of beam soffits.
- Deduct wall and column area on the plan.
- Adjust for other items (e.g., deductions for openings).
- Main forms include slab soffits and for landing soffits.
- Wall faces can occur in the vertical, sloping and curved orientation.
- Sides of piers, columns and stanchions can occur in different axis.
Formwork to Slab and Beam Soffits
- Heights of the struts are measured from level of the concrete
- Formwork to the side will include formwork to the beam
- Formwork to the edge will include formwork for edge of the beam
Formwork to Walls and Columns
- No formwork to sides of columns or edges of walls shall be measured for the junction between structural walls and columns.
- Section VII(d).5-6 specifies that it is only be measured to each wall requiring support.
Formwork to Beams
- Section VII(d).7: Measure formwork for the sides and the soffits together.
- Do not add any additional formwork for secondary beams where the the main intersect.
Measurement rule for VII(c) Reinforcement
- Reinforcing bars shall be measured separately according the the following points.
- Different types of steel.
- Different bar sizes.
- Fabric reinforcement to BS4466:1989 or BS8666:2005 clear formulae for different bending shapes.
Unit Weight
- Reinforcement shall be measured in kilograms except for the reinforcement mesh as square meters
- Instead of using the drawings measure the weights
- Take the lengths of the rebars and convert to weights
Reinforcement (Rebar)
- Round, indented, and square bars should be accounted for in measurement.
- Fabric must be flat as per the Engineer and designed according to specification.
- Measure the couplers but not the openings
- Use a detail description with detail of weight
- All proprietary should contain manufacturers reference
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.