Podcast
Questions and Answers
A project manager is leading a high-profile initiative and is pressured by senior executives to present the project as "on track", even though significant budget overruns and delays exist. They believe that reporting truthfully may jeopardize stakeholder confidence. What should the project manager do?
A project manager is leading a high-profile initiative and is pressured by senior executives to present the project as "on track", even though significant budget overruns and delays exist. They believe that reporting truthfully may jeopardize stakeholder confidence. What should the project manager do?
- Report the actual project status transparently, detailing corrective actions to manage concerns. (correct)
- Provide only partial information, emphasizing successes while minimizing challenges.
- Present the project as "on track", since disclosing issues could cause unnecessary panic.
- Adjust status reports to reflect executive expectations, ensuring continued project support.
A project sponsor asks a project manager to delay reporting a data breach to avoid bad press. While no immediate harm has occurred, withholding this information may impact client trust and legal compliance. What should the project manager do?
A project sponsor asks a project manager to delay reporting a data breach to avoid bad press. While no immediate harm has occurred, withholding this information may impact client trust and legal compliance. What should the project manager do?
- Report the breach immediately, ensuring legal and ethical compliance. (correct)
- Delay disclosure until an internal damage assessment is completed.
- Consult with legal counsel but avoid acting without executive approval.
- Follow the sponsor's directive, since no direct harm has been identified.
During vendor selection, a project manager discovers that one supplier is a close friend. Though their company meets requirements, there are other equally qualified candidates. What should the project manager do?
During vendor selection, a project manager discovers that one supplier is a close friend. Though their company meets requirements, there are other equally qualified candidates. What should the project manager do?
- Proceed with the selection but ensure a strict evaluation process is followed.
- Avoid discussing the relationship unless formally questioned.
- Declare the relationship and remove themselves from the selection process. (correct)
- Award the contract to their friend's company, since they meet the qualifications.
A client requests that a project manager falsify project completion percentages to align with their own reporting cycle, even though actual progress is lower. The client argues that this will "buy time" to resolve delays internally. What should the project manager do?
A client requests that a project manager falsify project completion percentages to align with their own reporting cycle, even though actual progress is lower. The client argues that this will "buy time" to resolve delays internally. What should the project manager do?
A junior team member accidentally accesses confidential data beyond their clearance level. The information is not directly related to the project, but keeping it could offer a competitive advantage. What should the project manager do?
A junior team member accidentally accesses confidential data beyond their clearance level. The information is not directly related to the project, but keeping it could offer a competitive advantage. What should the project manager do?
A project manager notices biased hiring practices within the company, where certain candidates are favored based on personal relationships rather than merit. While they are not directly responsible for hiring, they are expected to onboard new team members. What should the project manager do?
A project manager notices biased hiring practices within the company, where certain candidates are favored based on personal relationships rather than merit. While they are not directly responsible for hiring, they are expected to onboard new team members. What should the project manager do?
A senior stakeholder requests that the project manager hire their relative as a consultant, despite the candidate lacking relevant qualifications. Refusing could damage the relationship, but hiring them may set a bad precedent. What should the project manager do?
A senior stakeholder requests that the project manager hire their relative as a consultant, despite the candidate lacking relevant qualifications. Refusing could damage the relationship, but hiring them may set a bad precedent. What should the project manager do?
A project faces budget cuts, and a project manager must decide which costs to reduce. An external consultant suggests inflating certain expense reports to maintain funding. What should the project manager do?
A project faces budget cuts, and a project manager must decide which costs to reduce. An external consultant suggests inflating certain expense reports to maintain funding. What should the project manager do?
A project manager uncovers bribery during vendor negotiations. The supplier has offered personal incentives in exchange for an exclusive contract. What should the project manager do?
A project manager uncovers bribery during vendor negotiations. The supplier has offered personal incentives in exchange for an exclusive contract. What should the project manager do?
A project manager is working internationally and discovers that local business culture accepts "facilitation payments" to speed up approvals. This is technically legal but violates company ethics policies. What should the project manager do?
A project manager is working internationally and discovers that local business culture accepts "facilitation payments" to speed up approvals. This is technically legal but violates company ethics policies. What should the project manager do?
A project manager accidentally receives an internal report outlining a competitor's financial projections. The document was sent in error but could provide a competitive advantage if used for decision-making. What should the project manager do?
A project manager accidentally receives an internal report outlining a competitor's financial projections. The document was sent in error but could provide a competitive advantage if used for decision-making. What should the project manager do?
A senior executive asks the project manager to fast-track approval of a deliverable without conducting the required quality assurance checks. The executive claims that meeting the deadline is more important than minor quality issues. What should the project manager do?
A senior executive asks the project manager to fast-track approval of a deliverable without conducting the required quality assurance checks. The executive claims that meeting the deadline is more important than minor quality issues. What should the project manager do?
A project manager learns that a subcontractor is using unethical labor practices. While the contract is legally binding, continuing with them could damage the company's reputation. What should the project manager do?
A project manager learns that a subcontractor is using unethical labor practices. While the contract is legally binding, continuing with them could damage the company's reputation. What should the project manager do?
A project manager realizes that the team's performance metrics are being manipulated to make the project appear more successful than it actually is. Stakeholders are making critical decisions based on false data. What should the project manager do?
A project manager realizes that the team's performance metrics are being manipulated to make the project appear more successful than it actually is. Stakeholders are making critical decisions based on false data. What should the project manager do?
A project manager notices that a team member has been accessing unauthorized project files containing sensitive client information. The employee claims they did so out of curiosity and did not use the data. What should the project manager do?
A project manager notices that a team member has been accessing unauthorized project files containing sensitive client information. The employee claims they did so out of curiosity and did not use the data. What should the project manager do?
A project manager is offered an all-expenses-paid trip by a vendor bidding for a new contract. The vendor insists that the trip is not tied to any decision-making and is a general networking opportunity. What should the project manager do?
A project manager is offered an all-expenses-paid trip by a vendor bidding for a new contract. The vendor insists that the trip is not tied to any decision-making and is a general networking opportunity. What should the project manager do?
A project team is instructed to use a new software tool that violates data privacy regulations in certain regions. The vendor claims that compliance is not strictly enforced, and most companies ignore it. What should the project manager do?
A project team is instructed to use a new software tool that violates data privacy regulations in certain regions. The vendor claims that compliance is not strictly enforced, and most companies ignore it. What should the project manager do?
A project sponsor suggests delaying payments to suppliers as a tactic to improve the company's quarterly financial statements. While this does not break any contract terms, it could strain supplier relationships. What should the project manager do?
A project sponsor suggests delaying payments to suppliers as a tactic to improve the company's quarterly financial statements. While this does not break any contract terms, it could strain supplier relationships. What should the project manager do?
A project manager discovers that their direct report has been inflating work hours on their timesheets. The employee insists that everyone does it and that it is a company-wide practice. What should the project manager do?
A project manager discovers that their direct report has been inflating work hours on their timesheets. The employee insists that everyone does it and that it is a company-wide practice. What should the project manager do?
A project requires approval from a government agency, and a local intermediary offers to "expedite" the process for a small cash payment. The intermediary claims this is standard practice in that region. What should the project manager do?
A project requires approval from a government agency, and a local intermediary offers to "expedite" the process for a small cash payment. The intermediary claims this is standard practice in that region. What should the project manager do?
A project manager is under pressure to approve an incomplete deliverable to meet a contractual milestone. The client has already made partial payments and is expecting the product on time, but the quality assurance tests have not been completed. What should the project manager do?
A project manager is under pressure to approve an incomplete deliverable to meet a contractual milestone. The client has already made partial payments and is expecting the product on time, but the quality assurance tests have not been completed. What should the project manager do?
A senior executive pressures the project manager to select a specific vendor, despite concerns over their inflated pricing and past ethical violations. The executive argues that this vendor has been a long-term business partner. What should the project manager do?
A senior executive pressures the project manager to select a specific vendor, despite concerns over their inflated pricing and past ethical violations. The executive argues that this vendor has been a long-term business partner. What should the project manager do?
A project manager is asked to modify an employee's performance review to make it more favorable. The request comes from a senior manager who wants to help the employee secure an internal promotion. What should the project manager do?
A project manager is asked to modify an employee's performance review to make it more favorable. The request comes from a senior manager who wants to help the employee secure an internal promotion. What should the project manager do?
A project sponsor offers the project manager a personal financial incentive in exchange for expediting approval of certain project expenses that are outside of budget guidelines. What should the project manager do?
A project sponsor offers the project manager a personal financial incentive in exchange for expediting approval of certain project expenses that are outside of budget guidelines. What should the project manager do?
A project team member is publicly criticizing the company's ethical standards on social media. Their comments do not violate company policy but could damage the organization's reputation. What should the project manager do?
A project team member is publicly criticizing the company's ethical standards on social media. Their comments do not violate company policy but could damage the organization's reputation. What should the project manager do?
A key supplier is struggling with delivery deadlines and offers the project manager a personal incentive to approve an extension without informing the client. What should the project manager do?
A key supplier is struggling with delivery deadlines and offers the project manager a personal incentive to approve an extension without informing the client. What should the project manager do?
A project manager is assigned to lead an initiative in a country where gender discrimination is prevalent. The local business culture expects men to make final project decisions, even though the project manager is a woman. What should the project manager do?
A project manager is assigned to lead an initiative in a country where gender discrimination is prevalent. The local business culture expects men to make final project decisions, even though the project manager is a woman. What should the project manager do?
An external consultant requests access to sensitive project data, claiming it will help them provide better recommendations. However, the consultant does not have the proper security clearance. What should the project manager do?
An external consultant requests access to sensitive project data, claiming it will help them provide better recommendations. However, the consultant does not have the proper security clearance. What should the project manager do?
A project manager notices that one of their team members is being treated unfairly due to their ethnic background. The affected employee has not filed a complaint but appears demotivated. What should the project manager do?
A project manager notices that one of their team members is being treated unfairly due to their ethnic background. The affected employee has not filed a complaint but appears demotivated. What should the project manager do?
A client insists that the project team "repurpose" existing project funds to cover unapproved expenses. The request is minor but violates budget policies. What should the project manager do?
A client insists that the project team "repurpose" existing project funds to cover unapproved expenses. The request is minor but violates budget policies. What should the project manager do?
A project manager overseeing a large-scale IT infrastructure upgrade discovers that the selected vendor has a history of underpaying subcontractors and has faced lawsuits regarding poor labor conditions. While the vendor meets all technical and contractual requirements, continuing the partnership could lead to reputational damage for the company. What should the project manager do?
A project manager overseeing a large-scale IT infrastructure upgrade discovers that the selected vendor has a history of underpaying subcontractors and has faced lawsuits regarding poor labor conditions. While the vendor meets all technical and contractual requirements, continuing the partnership could lead to reputational damage for the company. What should the project manager do?
During a project audit, the project manager notices several minor accounting discrepancies in how vendor payments have been logged. The discrepancies are small enough that they do not impact overall financial accuracy, but failing to report them could set a precedent for overlooking financial mismanagement. What should the project manager do?
During a project audit, the project manager notices several minor accounting discrepancies in how vendor payments have been logged. The discrepancies are small enough that they do not impact overall financial accuracy, but failing to report them could set a precedent for overlooking financial mismanagement. What should the project manager do?
A project team member privately confides in the project manager that their supervisor has been pressuring them to manipulate project reports to make key performance indicators (KPIs) appear more favorable. The employee fears retaliation if they report the issue. What should the project manager do?
A project team member privately confides in the project manager that their supervisor has been pressuring them to manipulate project reports to make key performance indicators (KPIs) appear more favorable. The employee fears retaliation if they report the issue. What should the project manager do?
A government-funded project is required to follow strict diversity hiring policies, but a senior stakeholder insists on hiring an unqualified candidate due to their long-standing relationship with the company. Approving the hire could risk regulatory penalties, but refusing may strain relations with leadership. What should the project manager do?
A government-funded project is required to follow strict diversity hiring policies, but a senior stakeholder insists on hiring an unqualified candidate due to their long-standing relationship with the company. Approving the hire could risk regulatory penalties, but refusing may strain relations with leadership. What should the project manager do?
A project manager is informed that a team member has been using company resources for personal projects during work hours. The employee is a high performer, and disciplinary action could negatively impact project progress. What should the project manager do?
A project manager is informed that a team member has been using company resources for personal projects during work hours. The employee is a high performer, and disciplinary action could negatively impact project progress. What should the project manager do?
A key stakeholder offers the project manager insider information about an upcoming corporate restructuring that could affect project funding. The information is not yet public, but using it could allow the project team to make strategic adjustments in advance. What should the project manager do?
A key stakeholder offers the project manager insider information about an upcoming corporate restructuring that could affect project funding. The information is not yet public, but using it could allow the project team to make strategic adjustments in advance. What should the project manager do?
A project manager is overseeing an international construction project and discovers that local environmental laws are significantly weaker than their home country's standards. The project can legally proceed without additional environmental protections, but doing so could cause significant ecological harm. What should the project manager do?
A project manager is overseeing an international construction project and discovers that local environmental laws are significantly weaker than their home country's standards. The project can legally proceed without additional environmental protections, but doing so could cause significant ecological harm. What should the project manager do?
A project manager's direct report takes credit for another team member's work during a stakeholder meeting. The misrepresentation could increase their chances for promotion, but the actual contributor is too junior to challenge the claim. What should the project manager do?
A project manager's direct report takes credit for another team member's work during a stakeholder meeting. The misrepresentation could increase their chances for promotion, but the actual contributor is too junior to challenge the claim. What should the project manager do?
A project manager is working with a consultant who is also employed by a competitor. There is no clear conflict of interest, but they have access to sensitive project strategies. What should the project manager do?
A project manager is working with a consultant who is also employed by a competitor. There is no clear conflict of interest, but they have access to sensitive project strategies. What should the project manager do?
A project manager is asked to reduce workplace safety measures to lower project costs. While the legal requirements will still be met, the reduced measures increase risk to workers. What should the project manager do?
A project manager is asked to reduce workplace safety measures to lower project costs. While the legal requirements will still be met, the reduced measures increase risk to workers. What should the project manager do?
Flashcards
Transparent Project Reporting
Transparent Project Reporting
Truthfully report the project's actual status, including budget overruns and delays, and detail corrective actions.
Report Data Breach
Report Data Breach
Immediately report the data breach to ensure legal and ethical compliance.
Declare Conflicts of Interest
Declare Conflicts of Interest
Declare the relationship with your friend and remove yourself from the vendor selection process.
Uphold Accurate Reporting
Uphold Accurate Reporting
Signup and view all the flashcards
Report Unauthorized Data Access
Report Unauthorized Data Access
Signup and view all the flashcards
Escalate Hiring Concerns
Escalate Hiring Concerns
Signup and view all the flashcards
Refuse Unqualified Hires
Refuse Unqualified Hires
Signup and view all the flashcards
Ensure Financial Transparency
Ensure Financial Transparency
Signup and view all the flashcards
Report Bribery Attempts
Report Bribery Attempts
Signup and view all the flashcards
Refuse Facilitation Payments
Refuse Facilitation Payments
Signup and view all the flashcards
Return Confidential Documents
Return Confidential Documents
Signup and view all the flashcards
Enforce Quality Checks
Enforce Quality Checks
Signup and view all the flashcards
Investigate Labor Ethics
Investigate Labor Ethics
Signup and view all the flashcards
Report Accurate Performance Metrics
Report Accurate Performance Metrics
Signup and view all the flashcards
Report Unauthorized File Access
Report Unauthorized File Access
Signup and view all the flashcards
Reject vendor gifts
Reject vendor gifts
Signup and view all the flashcards
Reject non-compliant software
Reject non-compliant software
Signup and view all the flashcards
Reject unethical payments
Reject unethical payments
Signup and view all the flashcards
Report unethical hours
Report unethical hours
Signup and view all the flashcards
Reject bribery
Reject bribery
Signup and view all the flashcards
Uphold quality assurance
Uphold quality assurance
Signup and view all the flashcards
Enforce ethics
Enforce ethics
Signup and view all the flashcards
Be accurate
Be accurate
Signup and view all the flashcards
Compliance first
Compliance first
Signup and view all the flashcards
Ethics first
Ethics first
Signup and view all the flashcards
Safety is first
Safety is first
Signup and view all the flashcards
Equal Inclusion
Equal Inclusion
Signup and view all the flashcards
Deny Data Access
Deny Data Access
Signup and view all the flashcards
Address unfair treatment
Address unfair treatment
Signup and view all the flashcards
Financial integrity
Financial integrity
Signup and view all the flashcards
Study Notes
-
A project manager should transparently report the actual project status, detailing corrective actions, even when under pressure from senior executives to present the project as "on track" despite budget overruns and delays, as truthful reporting maintains stakeholder confidence
-
A project manager should immediately report a data breach, despite a project sponsor's request to delay, to ensure legal and ethical compliance and to maintain client trust, even if no immediate harm has occurred
-
A project manager should declare a relationship with a vendor during vendor selection and remove themselves from the selection process, even if the vendor meets the requirements, when other equally qualified candidates exist, to avoid any perception of bias
-
A project manager should refuse a client's request to falsify project completion percentages, even if the client argues it will "buy time" to resolve internal delays, to uphold accurate reporting standards
-
A project manager should report a junior team member's accidental access to confidential data and ensure the data is not used improperly, even if the information is not directly related to the project but could offer a competitive advantage
-
A project manager should escalate concerns to HR, advocating for transparent and fair hiring practices, when noticing biased hiring practices within the company, where candidates are favored based on personal relationships rather than merit even if the project manager is not directly responsible for hiring, but they are expected to onboard new team members
-
A project manager should decline a senior stakeholder's request to hire their relative as a consultant, emphasizing the need for a fair selection process, even if the candidate lacks relevant qualifications and refusing could damage the relationship
-
A project manager should reject an external consultant's suggestion to inflate expense reports when faced with budget cuts, ensuring financial transparency
-
A project manager should report a supplier that is offering personal incentives in exchange for an exclusive contract immediately and disqualify them from consideration when uncovering bribery during vendor negotiations
-
A project manager should adhere to company policies, refusing to make unethical payments, when working internationally and discovers that local business culture accepts "facilitation payments" to speed up approvals, even if it is technically legal but violates company ethics policies
-
A project manager should return an internal report outlining a competitor's financial projections immediately and notify the sender of the mistake, even if the document was accidentally received and could provide a competitive advantage if used for decision-making
-
A project manager should refuse to bypass quality checks, ensuring compliance with project standards, when a senior executive asks to fast-track approval of a deliverable without conducting the required quality assurance checks, even if the executive claims that meeting the deadline is more important than minor quality issues
-
A project manager should investigate a subcontractor's unethical labor practices further and escalate concerns to company leadership, even if the contract is legally binding, because continuing with them could damage the company's reputation
-
A project manager should correct the manipulated data and report accurate metrics immediately when realizing that the team's performance metrics are being manipulated to make the project appear more successful than it actually is because stakeholders are making critical decisions based on false data
-
A project manager should report a team member accessing unauthorized project files containing sensitive client information according to company policy and reinforce data security protocols when noticing that a team member has been accessing unauthorized project files containing sensitive client information.
-
A project manager should decline an all-expenses-paid trip offered by a vendor bidding for a new contract, ensuring procurement decisions remain unbiased, even if the vendor says it is not tied to any decision-making and insists it is a general networking opportunity
-
A project manager should refuse to implement a new software tool until it meets compliance standards when the project team is instructed to use a new software tool that violates data privacy regulations in certain regions, even if the vendor claims that compliance is not strictly enforced
-
A project manager should reject the suggestion, prioritizing ethical financial practices, when a project sponsor suggests delaying payments to suppliers as a tactic to improve the company's quarterly financial statements, even if it does not break any contract terms, because it could strain supplier relationships
-
A project manager should report the falsified timesheets and reinforce integrity expectations when discovering that a direct report has been inflating work hours on their timesheets, even if the employee insists that everyone does it and that it is a company-wide practice
-
A project manager should decline an offer that ensures compliance with anti-bribery laws when a project requires approval from a government agency, and a local intermediary offers to "expedite" the process for a small cash payment, even if the intermediary claims this is standard practice in that region
-
A project manager should refuse to approve an incomplete deliverable until all quality assurance checks are complete when under pressure to approve an incomplete deliverable to meet a contractual milestone, the client has already made partial payments and is expecting the product on time, but the quality assurance tests have not been completed
-
A project manager should insist on a competitive bidding process, ensuring ethical procurement when a senior executive pressures the project manager to select a specific vendor, despite concerns over their inflated pricing and past ethical violations, the executive argues that this vendor has been a long-term business partner
-
A project manager should refuse to modify a review, ensuring performance assessments accurate when a senior manager asks a project manager to modify an employee's performance review to make it more favorable to help the employee secure an internal promotion
-
A project manager should report the bribery attempt to the appropriate compliance authorities when a project sponsor offers the project manager a personal financial incentive in exchange for expediting approval of certain project expenses that are outside of budget guidelines
-
A project manager should have a private discussion with the employee, reinforcing ethical communication expectations when a project team member is publicly criticizing the company's ethical standards on social media. The comments do not violate company policy but could damage the organization's reputation
-
A project manager should reject an offer and report the ethical violation to company leadership when a key supplier is struggling with delivery deadlines and offers the project manager a personal incentive to approve an extension without informing the client
-
A project manager should uphold company diversity and inclusion policies, ensuring decisions are made equitably when assigned to lead an initiative in a country where gender discrimination is prevalent.
-
A project manager should deny access and follow proper security protocols to protect sensitive data when an external consultant requests access to sensitive project data, claiming it will help them provide better recommendations, but the consultant does not have the proper security clearance
-
A project manager should address the situation proactively, reinforcing a culture of inclusivity and fairness, when a project manager notices that one of their team members is being treated unfairly due to their ethnic background, and the affected employee has not filed a complaint but appears demotivated
-
A project manager should reject the request, ensuring financial integrity is maintained when a client insists that the project team "repurpose" existing project funds to cover unapproved expenses, the request is minor but violates budget policies
-
A project manager should escalate the concern to senior leadership, recommending a review of the vendor's ethical track record before continuing when overseeing a large-scale IT infrastructure upgrade and discovers that the selected vendor has a history of underpaying subcontractors and has faced lawsuits regarding poor labor conditions
-
A project manager should report the discrepancies to the finance department, ensuring full transparency and financial accountability when noticing several minor accounting discrepancies in how vendor payments have been logged because failing to report them could set a precedent for overlooking financial mismanagement
-
A project manager should document the concern and escalate it confidentially to HR and compliance teams, ensuring the employee is protected when a project team member privately confides that their supervisor has been pressuring them to manipulate project reports to make key performance indicators (KPIs) appear more favorable, and the employee fears retaliation
-
A project manager should uphold hiring policies and reject the request, ensuring compliance with diversity and fairness regulations when a government-funded project is required to follow strict diversity hiring policies, but a senior stakeholder insists on hiring an unqualified candidate due to their long-standing relationship with the company
-
A project manager should address the issue formally, ensuring company policies are followed while recognizing the employee's contributions when informed that a team member has been using company resources for personal projects during work hours
-
A project manager should refuse to use or share the insider information, ensuring compliance with corporate ethics policies when offered insider information about an upcoming corporate restructuring that could affect project funding
-
A project manager should implement higher environmental standards voluntarily, aligning with ethical corporate practices even if not required by law if overseeing an international construction project and discovers that local environmental laws are significantly weaker than their home country's standards
-
A project manager should clarify the contributions in a professional manner, ensuring credit is given fairly when a direct report takes credit for another team member's work during a stakeholder meeting
-
A project manager should implement stricter confidentiality agreements and monitor access to proprietary information when working with a consultant employed by a competitor, even with no clear conflict of interest
-
A project manager should reject the request and advocate for maintaining safety standards, even if it increases costs, when asked to reduce workplace safety measures to lower project costs, where reduced measures increase risk to workers
-
A project manager should pause development and escalate the issue to both internal ethics committees and regulatory bodies if necessary, ensuring that the potential risk is addressed transparently while leading a research initiative where a subcontractor discovered a potentially dangerous flaw in an early-stage prototype and the client insists on proceeding without disclosure because the project manager is torn between honoring the client's directive and ensuring the flaw is properly evaluated
-
A project manager should insist on a fair hiring process, ensuring that all candidates are evaluated based on merit and competency when a senior manager instructs them to hire a specific individual for a leadership position within the project, despite the candidate lacking key skills
-
A project manager should reject the request and uphold the integrity of the internal review process, even if it slows progress during contract negotiations where the client suggests to "speed up approvals" by bypassing internal review processes because the change may increase risk exposure for the company
-
A project manager should report the compliance violation immediately, ensuring that the issue is investigated and the employee is protected should a junior employee confesses to a project manager that they have falsified safety compliance data by their direct supervisor
-
A project manager should inform stakeholders, assessing alternative suppliers, thus prioritizing long-term project integrity over short-term gains when learning that a key supplier is using substandard materials that technically meet contractual obligations but may reduce product longevity
-
A project manager should reject the request unless it is formally approved, thus ensuring all resource allocations align with project governance standards when a project sponsor privately requests to redirect some project resources to support an unrelated initiative that is politically important to leadership but outside the original project scope
-
A project manager should adopt the strictest regional standards across all locations, ensuring compliance with all applicable laws when a global project involves collecting customer data from multiple regions, and some locations have stricter privacy laws than others, but the client suggests applying the least restrictive standards globally to simplify data handling
-
A project manager should report the issue to the competitor or the platform hosting the document, ensuring ethical integrity is maintained when a team member discovers a competitor's confidential internal document (likely uploaded by mistake) on a public website
-
A project manager should inform stakeholders that the regulatory change requires a revised scope and budget, thus ensuring compliance when a new regulatory change requires adjustments to an ongoing project's scope and budget, but the project sponsor insists on delivering the original scope without additional resources
-
A project manager should refuse to engage in favoritism and enforce a fair, competitive selection process, aligning with company policies when a high-ranking executive pressures the project manager to give preferential treatment to a particular supplier during contract negotiations
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
These scenarios highlight ethical dilemmas faced by project managers. They emphasize the importance of transparency, integrity, and compliance with ethical standards. Truthful reporting builds stakeholder confidence and maintaining client trust.