What milestone does the Boiler Light-Up of Unit 2 represent?
What milestone does the Boiler Light-Up of Unit 2 represent?
- The synchronization of the unit (correct)
- The completion of unit construction
- The start of commercial operations (correct)
- The signing of multiple contracts
What percentage of the generated energy will be utilized in the state of Bihar?
What percentage of the generated energy will be utilized in the state of Bihar?
- 90%
- 85% (correct)
- 70%
- 100%
Which project is associated with the MoU signed on 21/10/24?
Which project is associated with the MoU signed on 21/10/24?
- Solar panel installation
- Wind energy development
- Thermal power initiative
- Sunni Dam HEP (correct)
What is the total capacity of the hydro projects under construction mentioned?
What is the total capacity of the hydro projects under construction mentioned?
How many states are allocated for the PM Surya Ghar Muft Bijli Yojana?
How many states are allocated for the PM Surya Ghar Muft Bijli Yojana?
What is the total gigawatt capacity that SJVN has floated tenders for in the financial year '24-'25?
What is the total gigawatt capacity that SJVN has floated tenders for in the financial year '24-'25?
Which organization recognized SJVN with an award for excellence in waste management?
Which organization recognized SJVN with an award for excellence in waste management?
What is the primary responsibility of SJVN in terms of rooftop solar systems?
What is the primary responsibility of SJVN in terms of rooftop solar systems?
What significant status was conferred to SJVN in the second quarter of the financial year '24-'25?
What significant status was conferred to SJVN in the second quarter of the financial year '24-'25?
What capacity does the recently commissioned Omkareshwar solar project have?
What capacity does the recently commissioned Omkareshwar solar project have?
How much revenue annually is the new solar project expected to add to SJVN?
How much revenue annually is the new solar project expected to add to SJVN?
In which state was the Omkareshwar solar project commissioned?
In which state was the Omkareshwar solar project commissioned?
Who presented the overview during the Q2 FY '25 conference call?
Who presented the overview during the Q2 FY '25 conference call?
What is the total installed capacity of SJVN after this recent addition?
What is the total installed capacity of SJVN after this recent addition?
What type of project is the Omkareshwar solar project classified as?
What type of project is the Omkareshwar solar project classified as?
Which organization signed the power sale agreement with SJVN for the solar project?
Which organization signed the power sale agreement with SJVN for the solar project?
What was the incentive income for Q2 in INR?
What was the incentive income for Q2 in INR?
What is the regulated equity amount for the operational project Nathpa Jhakri?
What is the regulated equity amount for the operational project Nathpa Jhakri?
Which factor primarily contributed to the delays in the rail infrastructure?
Which factor primarily contributed to the delays in the rail infrastructure?
What was the incentive income for the last quarter of 2023?
What was the incentive income for the last quarter of 2023?
Who conducted the closing remarks during the conference call?
Who conducted the closing remarks during the conference call?
What is the expected commissioning date for the BBMB project?
What is the expected commissioning date for the BBMB project?
Which aspect of the projects is managed in-house by SJVN Limited?
Which aspect of the projects is managed in-house by SJVN Limited?
What is a likely reason for potential delays in project commissioning as discussed?
What is a likely reason for potential delays in project commissioning as discussed?
How much capacity is mentioned as being allotted for the discussed projects?
How much capacity is mentioned as being allotted for the discussed projects?
What type of contracts is SJVN Limited awarding for the projects?
What type of contracts is SJVN Limited awarding for the projects?
What is mentioned as a potential financial expenditure on the 20-gigawatt projects?
What is mentioned as a potential financial expenditure on the 20-gigawatt projects?
Which project has the least capacity mentioned in the discussion?
Which project has the least capacity mentioned in the discussion?
What is the primary function of SJVN Limited regarding the projects discussed?
What is the primary function of SJVN Limited regarding the projects discussed?
What is one suggested method for improving cost efficiency in projects?
What is one suggested method for improving cost efficiency in projects?
What are the primary tasks involved in O&M according to the content?
What are the primary tasks involved in O&M according to the content?
How can companies potentially reduce O&M costs?
How can companies potentially reduce O&M costs?
What financial metrics may be affected by construction costs according to the discussion?
What financial metrics may be affected by construction costs according to the discussion?
What future action is suggested to take advantage of economies of scale?
What future action is suggested to take advantage of economies of scale?
Why might companies prefer to purchase solar modules directly?
Why might companies prefer to purchase solar modules directly?
What is implied about the nature of O&M tasks?
What is implied about the nature of O&M tasks?
What is highlighted as a critical step for reducing project costs?
What is highlighted as a critical step for reducing project costs?
What is the proposed capacity addition for the year '24-'25?
What is the proposed capacity addition for the year '24-'25?
What challenge does the public sector undertaking face compared to private companies like Reliance or Adani?
What challenge does the public sector undertaking face compared to private companies like Reliance or Adani?
Which entity provides oversight and control in public sector decision-making?
Which entity provides oversight and control in public sector decision-making?
What is the planned capacity addition for the year '25-'26?
What is the planned capacity addition for the year '25-'26?
Which of the following is NOT a requirement for starting a new venture in the public sector?
Which of the following is NOT a requirement for starting a new venture in the public sector?
What capacity is planned for addition in '26-'27?
What capacity is planned for addition in '26-'27?
How does public sector undertaking management differ from that of private companies?
How does public sector undertaking management differ from that of private companies?
What is the total planned capacity addition from '25-'26 to '27-'28?
What is the total planned capacity addition from '25-'26 to '27-'28?
Flashcards
Navratna Status
Navratna Status
A prestigious recognition bestowed upon a company by the Department of Public Enterprises, Government of India, signifying its remarkable performance and contribution to the Indian economy.
Omkareshwar Solar Project
Omkareshwar Solar Project
A solar project, operational since 8th August 2024, located in the Omkareshwar Floating Solar Park in Madhya Pradesh, generating 196 million units of electricity per year.
Installed Capacity
Installed Capacity
The total amount of electricity that a company can produce from its operational power plants.
Revenue
Revenue
Signup and view all the flashcards
Conference Call
Conference Call
Signup and view all the flashcards
Quarter
Quarter
Signup and view all the flashcards
Financial Year
Financial Year
Signup and view all the flashcards
Q&A Session
Q&A Session
Signup and view all the flashcards
Boiler Light-Up
Boiler Light-Up
Signup and view all the flashcards
PM Surya Ghar Muft Bijli Yojana
PM Surya Ghar Muft Bijli Yojana
Signup and view all the flashcards
PCWR Summit and Awards
PCWR Summit and Awards
Signup and view all the flashcards
Empanelment of Vendors
Empanelment of Vendors
Signup and view all the flashcards
Outsourcing EPC
Outsourcing EPC
Signup and view all the flashcards
Incentive income
Incentive income
Signup and view all the flashcards
Regulated equity
Regulated equity
Signup and view all the flashcards
Public Sector Undertaking (PSU)
Public Sector Undertaking (PSU)
Signup and view all the flashcards
Contractor on Hire Basis
Contractor on Hire Basis
Signup and view all the flashcards
Manpower Cost
Manpower Cost
Signup and view all the flashcards
Joint Venture
Joint Venture
Signup and view all the flashcards
Proposal Stage
Proposal Stage
Signup and view all the flashcards
CAG (Comptroller and Auditor General of India), CVC (Central Vigilance Commission), and CVI (Central Vigilance Institute)
CAG (Comptroller and Auditor General of India), CVC (Central Vigilance Commission), and CVI (Central Vigilance Institute)
Signup and view all the flashcards
DIPAM (Department of Investment and Public Asset Management)
DIPAM (Department of Investment and Public Asset Management)
Signup and view all the flashcards
NITI Aayog
NITI Aayog
Signup and view all the flashcards
Backward Integration
Backward Integration
Signup and view all the flashcards
Operation and Maintenance (O&M) Cost
Operation and Maintenance (O&M) Cost
Signup and view all the flashcards
EPC (Engineering, Procurement, and Construction) Company
EPC (Engineering, Procurement, and Construction) Company
Signup and view all the flashcards
Return on Capital Employed (ROCE)
Return on Capital Employed (ROCE)
Signup and view all the flashcards
Return on Equity (ROE)
Return on Equity (ROE)
Signup and view all the flashcards
Bargaining
Bargaining
Signup and view all the flashcards
Vertical Integration
Vertical Integration
Signup and view all the flashcards
Study Notes
SJVN Limited Conference Call Transcript
- Date: November 7, 2024
- Topic: Financial results for the period ended September 30, 2024
- Management: Mr. A.K. Singh (Director Finance) and Mr. Soumendra Das (Company Secretary)
- Moderator: Mr. Rupesh Sankhe (Elara Securities Private Limited)
- NSE Symbol: SJVN-EQ
- BSE Scrip Code: 533206
- Meeting held on: Tuesday, November 5, 2024
- Nature of meeting: Group meeting.
- Compliance: Conference call transcript adheres to Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015.
- NSE Guidance Note: Transcript of call complies with NSE/CML/2022/38 (dated July 29, 2022)
Key Highlights of Q2 FY'25
- Navratna Status: SJVN attained Navratna status by the Department of Public Enterprises, Government of India.
- Omkareshwar Solar Project: Commissioned a 90-megawatt solar project in Omkareshwar, Madhya Pradesh, in August 2024, with a capacity to generate 196 million units per annum. This expands SJVN’s overall installed capacity to 2,466.50 million units
- Lower Arun Hydroelectric Project: Cabinet Committee of Economic Affairs approved a INR5,792.36 crore investment for the 669-megawatt hydroelectric project in Nepal.
- Darzo Lui Pumped Storage Project: The Government of Mizoram allocated the 2,400-megawatt Pumped Storage Project to SJVN.
- Nathpa Jhakri Power Project: Achieved record quarterly power generation (3,450.98 million units) surpassing previous quarter's generation record ('21-'22).
- Rampur Hydro Power Station: Achieved highest ever quarterly generation (955.616 million units).
- Buxar Thermal Project: Boiler light-up of Unit 1 completed on October 2nd, 2024, a significant step towards commercial operation expected by January 2025.
- Other projects: Several hydro projects (1,558 MW), thermal projects (1,320 MW), and solar projects (1,958 MW) are under development.
- Overall Investment: Company is targeting 25,000 MW by 2030, and 50,000 MW by 2040.
- Awards & Recognition: Received the Pollution Control, Waste Management and Recycling Excellence Award during the PCWR Summit.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on significant energy projects and initiatives in Bihar, including the Boiler Light-Up of Unit 2 and the PM Surya Ghar Muft Bijli Yojana. This quiz covers various aspects of energy generation, capacity, and organizations involved in the state's development. Challenge yourself with questions about recent projects and their impact on Bihar's energy landscape.