Questions and Answers

Which diesel generator set will start when the voltages at the emergency bus bars drop below 0.7VN?

  • 00XKA01
  • 00XKA02
  • Neither generator set will start
  • Both generator sets will start (correct)

Which voltage transformers are used to sense undervoltages at the emergency bus bars?

  • 00XKA01 and 00XKA02
  • 00BBC and 00BBD (correct)
  • 00XKA01 and 00BBC
  • 00BBD and 00XKA02

What is the method of control for the pre-selected diesel generator set?

  • Programmable logic controller (PLC) (correct)
  • Neutral grounding switch (NGS)
  • Emergency bus bars
  • Automatic changeover switch

What happens if one of the diesel generator sets fails to start?

<p>The pre-selection automatically changes to the other generator set (D)</p> Signup and view all the answers

When will the second diesel generator set shutdown automatically after starting?

<p>If it fails to synchronize within 3 minutes (A)</p> Signup and view all the answers

What is the minimum voltage level at which the diesel generator sets will start?

<p>0.7VN (B)</p> Signup and view all the answers

How are the diesel generator sets connected to the 6.6kV busbar?

<p>Through their diesel generator circuit breaker (A)</p> Signup and view all the answers

What will happen if the second BSDG fails to start?

<p>The other DG will be connected to the 6.6kV busbar (B)</p> Signup and view all the answers

When will the second BSDG shutdown automatically if not synchronized?

<p>Within 3 minutes after start (C)</p> Signup and view all the answers

What is the condition for considering the Emergency Power Supply to be in operation?

<p>Voltage &gt;min for more than 5 seconds (D)</p> Signup and view all the answers