What is the total number of marks for the exam?

  • 60 marks
  • 120 marks
  • 80 marks
  • 100 marks (correct)

In the current year's exam format, what is the structure of Section A?

  • Essay questions totaling 50 marks
  • Multiple choice questions totaling 20 marks (correct)
  • Practical questions totaling 30 marks
  • All written questions totaling 35 marks

Which of the following is a key feature of the exam?

  • Only single correct answers are allowed
  • All sections are compulsory
  • There are three 40-mark questions in Section B (correct)
  • Section B has equal weight for all questions

What is a disadvantage of the past papers for this module?

<p>They provide no useful insights into current exam styles (C)</p> Signup and view all the answers

What is the total duration of the project?

<p>66 days (C)</p> Signup and view all the answers

What type of data is NOT classified as nominal data?

<p>The number of people on a team (C)</p> Signup and view all the answers

Which of the following activities may be part of the exam content?

<p>Performing critical path analysis (A)</p> Signup and view all the answers

Which path represents the critical path of the project?

<p>A-B-E-F-H-J-K (B)</p> Signup and view all the answers

If task C is delayed by 5 days, what would most likely happen?

<p>The critical path would change. (C)</p> Signup and view all the answers

What is the recommended way to prepare for multiple choice quizzes?

<p>Writing your own questions (C)</p> Signup and view all the answers

Which task directly precedes the API integration task F?

<p>Backend development D (B), Frontend development E (D)</p> Signup and view all the answers

What type of learning format is emphasized for the exam preparation?

<p>Group study (C)</p> Signup and view all the answers

What is the duration of the unit testing task G?

<p>8 days (A)</p> Signup and view all the answers

Which task has no prerequisites?

<p>Requirements elicitation A (B)</p> Signup and view all the answers

How many days does the deployment task J take?

<p>5 days (D)</p> Signup and view all the answers

What would be the earliest start time of the final task K if the project starts on day 1?

<p>61 (C)</p> Signup and view all the answers

What would happen if task D is extended by three days?

<p>The critical path would change. (A)</p> Signup and view all the answers

Which assumption is NOT inherent in critical path analysis?

<p>Delays only occur on critical tasks. (A)</p> Signup and view all the answers

What is one potential issue related to resource allocation noted in critical path analysis?

<p>Resources may not always be available for multiple tasks. (C)</p> Signup and view all the answers

What could potentially harm the reliability of time estimates in a project?

<p>A single day's delay in any task. (D)</p> Signup and view all the answers

Why is flexibility a concern in critical path analysis?

<p>Task durations and orders may change in reality. (C)</p> Signup and view all the answers

Which of the following points concerning critical path analysis could contribute to earning max marks in evaluative tasks?

<p>Providing detailed supporting information for fewer points. (B)</p> Signup and view all the answers

How can overlooking non-critical tasks impact a project?

<p>They can potentially delay the project. (B)</p> Signup and view all the answers

Which resource-related assumption in critical path analysis is often unrealistic?

<p>Resources can always be allocated as needed without delay. (D)</p> Signup and view all the answers

Flashcards

Single Correct Answer Multiple Choice Question

A type of exam question that presents a statement with multiple choices, only one of which is correct. The correct answer is often disguised by plausible incorrect options.

Multiple Correct Answer Multiple Choice Question

A type of exam question that presents a statement with multiple choices, and more than one choice may be correct. The learner must identify all the correct answers.

Critical Path Analysis

A technique used to identify the critical path in a project, which is the sequence of activities that determines the shortest possible completion time for the project.

PERT Analysis (Program Evaluation and Review Technique)

A method for estimating the duration of a project by considering the optimistic, pessimistic, and most likely durations of each activity.

Signup and view all the flashcards

Gantt Chart

A visual representation of a project schedule that displays the tasks to be completed, their duration, and their dependencies.

Signup and view all the flashcards

Agile Development

A method for organizing and managing projects, focusing on short iterations of work called sprints, and embracing change as a positive factor.

Signup and view all the flashcards

Nominal Data

Data that can be categorized into distinct groups, but these groups do not have any inherent order.

Signup and view all the flashcards

Defects per SLOC (Lines of Code)

A metric used to measure the number of defects found in a software program per thousand lines of code. It helps in estimating the quality of software.

Signup and view all the flashcards

Activity Network

In project management, an activity network is a visual representation of the project's tasks, their dependencies, and their durations.

Signup and view all the flashcards

Critical Path

The critical path is the longest sequence of tasks in an activity network, and it determines the shortest possible project duration.

Signup and view all the flashcards

Float/Slack

Float, or slack, is the amount of time a task can be delayed without affecting the overall project duration.

Signup and view all the flashcards

Earliest Start Time (EST)

The earliest start time (EST) is the earliest point at which a task can begin, considering its prerequisites.

Signup and view all the flashcards

Latest Start Time (LST)

The latest start time (LST) is the latest point at which a task can begin without delaying the project.

Signup and view all the flashcards

Earliest Finish Time (EFT)

The earliest finish time (EFT) is the earliest point at which a task can be completed, considering its prerequisites and duration.

Signup and view all the flashcards

Latest Finish Time (LFT)

The latest finish time (LFT) is the latest point at which a task can be completed without delaying the project.

Signup and view all the flashcards

Delaying a Task on the Critical Path

A delay in a task on the critical path directly impacts the overall project duration, making it longer.

Signup and view all the flashcards

Critical Path Sensitivity

Changing the duration of a task on the critical path can affect the overall project duration.

Signup and view all the flashcards

Resource Availability Assumption

In critical path analysis, it's assumed that all resources are available whenever needed.

Signup and view all the flashcards

Time Estimate Accuracy

Critical path analysis relies on accurate time estimates for each task. If these estimates are inaccurate, the analysis might be misleading.

Signup and view all the flashcards

Ignoring Non-Critical Tasks

Critical path analysis focuses on the longest path in a project, potentially neglecting tasks outside the critical path that could impact the project's timeline if delayed.

Signup and view all the flashcards

Flexibility in Project Execution

Critical path analysis assumes a fixed sequence of tasks and durations. In reality, projects can be dynamic, with changes in task order or durations.

Signup and view all the flashcards

Benefits of Critical Path Analysis

The benefit of using critical path analysis is that it allows for the identification of the most important tasks in a project. This allows for a focused effort on these tasks and allows better control of the project schedule.

Signup and view all the flashcards

Oversimplification in Critical Path Analysis

A common problem in critical path analysis is that it can be overly simplified and may not account for all possible factors that could affect the project's schedule.

Signup and view all the flashcards

Minimum Project Completion Time

Critical path analysis can be used to identify the minimum time needed to complete a project and gives a comprehensive understanding of the crucial tasks.

Signup and view all the flashcards

Study Notes

CS3SPM Assessment Material

  • The exam format differs from previous years.
  • Section A (compulsory) is now 20 marks of multiple choice, rather than 35 marks written.
  • Section B has three 40-mark questions, students can answer two.
  • The exam is 100 marks and 2 hours long.

Multiple Choice Questions

  • Expect single-correct-answer and multiple-correct-answer questions.
  • Example of a multiple-correct-answer question: nominal data examples.

Agile Development Characteristics

  • Agile development characteristics:
    • Work is organized into sprints.
    • Each phase is thoroughly documented.
    • Change is viewed positively.
    • Teams of any size can work in an agile way.

Nominal Data Example

  • Examples of nominal data:
    • Number of people on a team
    • Language used on a project
    • Defects/SLOC
    • Project duration as a percentage of another project's duration
    • Phase of the current project

Critical Path Analysis Example

  • A table shows tasks, prerequisites, and durations for a project.
  • Instructions to create a network diagram, calculate project duration, and define critical path.
  • Instructions identifying delays in tasks, impacting the critical path.
  • Question on the limitations of critical path analysis.

Formulae for the Exam

  • Formulae for PERT analysis provided.
    • Expected activity duration (Delphi average).
    • Activity variance.
    • Z-score calculation.
  • Formulae for measurements and estimations (effort, size, cost).
    • Effort from size, and EpS (effort per size).
    • Effort from size and SpE.
    • Cost from size and CpS.
    • Cost from effort and CpE.
  • Students will have a calculator permitted.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Agile Development Principles
10 questions
Agile Methods in System Development
14 questions
Agile Development Basics
24 questions

Agile Development Basics

AudibleSatellite1453 avatar
AudibleSatellite1453
Agile Development Principles Quiz
24 questions
Use Quizgecko on...
Browser
Browser