Critical Path Analysis and Activity Networks
21 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the main purpose of using dummy activities in an activity network?

  • To indicate the critical path in the network.
  • To make the network more visually appealing.
  • To represent activities that have no duration.
  • To show the dependence of multiple activities on the same task. (correct)
  • What information is represented by the 'Early time' and 'Late time' of a task in an activity network?

  • The earliest and latest time the task can be started without delaying the project. (correct)
  • The time it takes to complete the task and the time it can be delayed.
  • The duration of the task and its associated float time.
  • The earliest and latest time the task can be completed without delaying the project.
  • What does the 'float time' of a task indicate?

  • The time the task can be accelerated to finish earlier.
  • The time it takes to complete the task.
  • The time a task can be delayed before it affects the project completion time. (correct)
  • The time allocated to the task in the project schedule.
  • Which of the following is NOT a step involved in creating an activity network?

    <p>Calculating the total project cost.</p> Signup and view all the answers

    What is the purpose of a Gantt chart in project management?

    <p>To show the schedule of tasks and their durations.</p> Signup and view all the answers

    What is the relationship between the critical path and the project completion time?

    <p>The critical path determines the minimum project completion time.</p> Signup and view all the answers

    What is the significance of the start node and sink node in an activity network?

    <p>They represent the beginning and end of the project, respectively.</p> Signup and view all the answers

    Which of the following statements about critical tasks is TRUE?

    <p>They have a float time of 0.</p> Signup and view all the answers

    What is the purpose of the float time in a Gantt chart?

    <p>To represent the flexibility in scheduling a task</p> Signup and view all the answers

    How should workers be assigned when there are enough available workers?

    <p>Assign a worker to each critical path first</p> Signup and view all the answers

    What happens to the project if there are not enough workers available?

    <p>The project will take longer to complete</p> Signup and view all the answers

    To determine the minimum number of workers required, what calculation is performed?

    <p>Calculate the total number of hours needed and divide by hours available per worker</p> Signup and view all the answers

    Which strategy should be avoided when scheduling a project with insufficient workers?

    <p>Leaving workers idle without tasks</p> Signup and view all the answers

    What does rounding up to the next integer provide in the context of worker assignment?

    <p>A lower bound for the number of workers needed</p> Signup and view all the answers

    Which method should be prioritized when scheduling activities in the presence of insufficient workers?

    <p>Choose the activity with the lowest late time available</p> Signup and view all the answers

    Why must a worker complete an activity once it has started?

    <p>To adhere to the project’s timeline requirements</p> Signup and view all the answers

    In a Gantt chart, what does the dotted section at the end of the bar represent?

    <p>The float time of the task</p> Signup and view all the answers

    What is the assumption about activity completion in the context of worker assignment?

    <p>Each activity is completed by a single worker in the time specified</p> Signup and view all the answers

    When scheduling a project without enough workers, what should you avoid doing?

    <p>Leaving a worker idle when possible</p> Signup and view all the answers

    What is the result of rounding up to the next integer in the context of worker assignment?

    <p>A lower bound for the number of workers needed</p> Signup and view all the answers

    When scheduling activities with insufficient workers, which strategy should be prioritized?

    <p>Assigning workers to activities with the lowest late time</p> Signup and view all the answers

    Study Notes

    Critical Path Analysis

    • Critical Path Analysis is used to plan large projects, identify dependent activities, and determine start and finish times for project parts.

    Precedence Table and Activity Networks

    • A precedence table is the first step in Critical Path Analysis.
    • Activity networks visually represent complex topics with interdependent tasks, similar to a precedence table.
    • Dummy activities are used in activity networks to show multiple activity dependencies.

    Task Timing

    • Each task in a network has an Early time (when it can begin) and a Late time (when it must finish to avoid delaying the project).
    • Early and Late times are calculated by analyzing task durations from start to end and then from end to start.
    • The start node has times of 0, 0, and the sink node has times of t, t.

    Float Time and Critical Tasks

    • Float time is the time a task can be delayed before holding up the project.
    • Tasks with a float time of 0 are critical tasks, which form a critical path from start to finish in the network.
    • There may be multiple critical paths.

    Gantt Charts

    • Gantt charts are bar charts displaying task information, including start time, duration, and float time.

    Scheduling

    • To find the minimum number of workers needed, assume each activity is completed by a single worker in the specified time.
    • Once an activity starts, the same worker must complete it, and once finished, the worker is immediately available for another activity.
    • The lower bound for workers is calculated and rounded up to the next integer.

    Scheduling with Enough Workers

    • Assign a worker to each critical path.
    • Allocate workers to remaining activities in order of lowest Late time.
    • Minimize the number of workers used.

    Scheduling without Enough Workers

    • If there are insufficient workers, the project will take longer.
    • Use the activity network instead of the Gantt chart.
    • Avoid leaving a worker idle whenever possible.
    • Assign the next available activity based on the lowest Late time.

    Critical Path Analysis

    • Critical Path Analysis is used to plan large projects, identify dependent activities, and determine start and finish times for project parts.

    Precedence Table and Activity Networks

    • A precedence table is the first step in Critical Path Analysis.
    • Activity networks visually represent complex topics with interdependent tasks, similar to a precedence table.
    • Dummy activities are used in activity networks to show multiple activity dependencies.

    Task Timing

    • Each task in a network has an Early time (when it can begin) and a Late time (when it must finish to avoid delaying the project).
    • Early and Late times are calculated by analyzing task durations from start to end and then from end to start.
    • The start node has times of 0, 0, and the sink node has times of t, t.

    Float Time and Critical Tasks

    • Float time is the time a task can be delayed before holding up the project.
    • Tasks with a float time of 0 are critical tasks, which form a critical path from start to finish in the network.
    • There may be multiple critical paths.

    Gantt Charts

    • Gantt charts are bar charts displaying task information, including start time, duration, and float time.

    Scheduling

    • To find the minimum number of workers needed, assume each activity is completed by a single worker in the specified time.
    • Once an activity starts, the same worker must complete it, and once finished, the worker is immediately available for another activity.
    • The lower bound for workers is calculated and rounded up to the next integer.

    Scheduling with Enough Workers

    • Assign a worker to each critical path.
    • Allocate workers to remaining activities in order of lowest Late time.
    • Minimize the number of workers used.

    Scheduling without Enough Workers

    • If there are insufficient workers, the project will take longer.
    • Use the activity network instead of the Gantt chart.
    • Avoid leaving a worker idle whenever possible.
    • Assign the next available activity based on the lowest Late time.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Learn about Critical Path Analysis, precedence tables, and activity networks for planning and managing complex projects with interdependent tasks.

    More Like This

    Use Quizgecko on...
    Browser
    Browser