Podcast
Questions and Answers
What is a primary strategic goal when evaluating the time-cost trade-off in project management?
What is a primary strategic goal when evaluating the time-cost trade-off in project management?
- Maximizing the amount of direct project costs, regardless of indirect costs.
- Identifying a plan that minimizes the total amount of direct and indirect project costs. (correct)
- Focusing solely on reducing the project completion time, even if it increases overall costs.
- Prioritizing activities on the critical path without considering cost implications.
What is the MOST important consideration when deciding which activities to crash in a project schedule?
What is the MOST important consideration when deciding which activities to crash in a project schedule?
- Crashing non-critical path activities to avoid impacting the project's completion date.
- Crashing activities with the highest cost first to minimize overall project duration.
- Crashing activities on the critical path with the lowest cost, as long as crashing costs do not exceed the benefits. (correct)
- Crashing all activities equally to distribute the impact of time reduction across the project.
Which of the following considerations is CRUCIAL when determining if shortening an activity on two or more critical paths is economically justifiable?
Which of the following considerations is CRUCIAL when determining if shortening an activity on two or more critical paths is economically justifiable?
- Whether resources are available to shorten the activity without delaying other tasks.
- Whether the total cost of crashing the joint activity is greater than the total cost of crashing individual activities on each path.
- Whether shortening the joint activity will impact activities not on the critical path.
- Whether the crashing cost for a joint activity is less than the sum of crashing one activity on each separate path. (correct)
How could benefits from crashing activities be realized?
How could benefits from crashing activities be realized?
In project crashing, under what condition should the crashing of activities cease?
In project crashing, under what condition should the crashing of activities cease?
Which of the following is NOT a direct influence to shorten project construction time?
Which of the following is NOT a direct influence to shorten project construction time?
What considerations should be made from an economic perspective, when determining which activities should be crashed first?
What considerations should be made from an economic perspective, when determining which activities should be crashed first?
A project manager is deciding whether to crash a project to meet a contractual deadline and avoid penalties that would severely impact profit margins. Considering the provided factors influencing the urgent desire to shorten project construction time, what MOST accurately reflects the project manager's primary motivation?
A project manager is deciding whether to crash a project to meet a contractual deadline and avoid penalties that would severely impact profit margins. Considering the provided factors influencing the urgent desire to shorten project construction time, what MOST accurately reflects the project manager's primary motivation?
In what order are critical path activities ranked during the crashing process?
In what order are critical path activities ranked during the crashing process?
What kind of activities are potential candidates for crashing?
What kind of activities are potential candidates for crashing?
Flashcards
Crashing
Crashing
Shortening project activity times by injecting additional resources to meet deadlines, incentives, or free up resources.
Goal of Time-Cost Trade-off
Goal of Time-Cost Trade-off
Direct costs increase, indirect costs decrease; finding the right balance minimizes total project costs.
Crashing Informations
Crashing Informations
Regular & crash time/cost estimates for each activity; activities on the critical path
Crashing Focus
Crashing Focus
Signup and view all the flashcards
Crashing priority
Crashing priority
Signup and view all the flashcards
Crashing procedure steps
Crashing procedure steps
Signup and view all the flashcards
Simultaneous Shortening
Simultaneous Shortening
Signup and view all the flashcards
Objective of Crashing
Objective of Crashing
Signup and view all the flashcards
Study Notes
Reducing Time and Cost
- Shortening project construction time is influenced by avoiding penalties, monetary incentives, freeing resources, and reducing indirect costs.
- Indirect costs include facilities, equipment, supervision, labor, and personnel.
- Managers can shorten project time via additional funds, personnel, efficient equipment, and relaxed work specifications.
- Evaluating the time cost-trade-off helps identify a plan that minimizes direct and indirect project costs, aiding rational decision-making on activities to crash and to what extent crashing is possible.
- Information needed includes regular/crash time estimates, regular/crash cost estimates, and a list of activities on the critical path.
- Activities on the critical path are potential candidates for crashing.
- Shortening non-critical activities will not affect the total project duration
Crashing Project Activities
- Activities should be crashed according to crashing costs, starting with the lowest cost.
- Crashing should continue as long as the crash cost is less than the benefits received.
- Crashing activities reduces indirect costs and increases direct costs.
- The optimum amount of crashing minimizes the sum of these costs.
- Benefits might be incentive payments or savings in project costs.
Procedure in Crashing Project Time
- First, estimate regular and crash time and costs for each activity.
- Determine the length of all paths and their float time.
- Identify activities on the critical path.
- Crash critical activities in order of increasing costs if crashing costs do not exceed benefits
- Two or more paths may become critical, requiring simultaneous shortening of paths.
- It can be more economical to shorten an activity on two or more critical paths if the joint crashing cost is less than crashing separate activities.
Illustration of Crashing Project Time
- With an indirect cost of Php10,000, develop an optimum time-cost plan.
- Path Length Calculation: Path 1-2-5-6 (A-B-F) = 8 + 12 + 4 = 24 days; Path 1-3-4-5-6 (C-D-E-F) = 7 + 6 + 9 + 4 = 26 days.
- The critical path is 1-3-4-5-6 at 26 days.
- Critical path activities ranked by crashing cost are C (Php2,000, 1 day), E (Php4,500, 2 days), B and D (Php6,000, 2 & 4 days), F (Php7,000, 2 days).
- Start shortening one day at a time, checking which path is critical after each reduction.
- Shortening activity C by one day (Php2,000) reduces the critical path to 25 days.
- Shortening activity E by one day (Php4,500) makes path (C-D-E-F) 24 days.
- Both paths are now critical at 24 days, requiring each path to be shortened.
- Shortening F shortens both paths but is most expensive.
- Shorten activity B (Php 6,000) and activity E (Php 4,500) for Php 10,500 total, making the project duration 23 days.
- No further improvement is feasible as costs exceed the daily project cost (Php 10,000).
Illustration 2: Optimum Crashing Plan
- For a project with indirect costs of Php 10,000 per week, determine an optimum crashing plan and graph total costs.
- Path Durations: A, B (22 weeks), C, D (17 weeks), E, F (21 weeks).
- Critical Path: A, B (22 weeks).
- Path A, B activities ranked by crashing costs are B (Php 3,000 1st week) and A (Php 8,000).
- Shorten activity B (lower crashing cost) to reduce indirect costs: Php 10,000 - 3,000 = Php 7,000 net savings.
Illustration 3: Crashing Activities and Paths
- With Activity B shortened, paths A, B and E, F have equal lengths of 21 weeks, both becoming critical paths.
- Rank activities by crashing costs on both critical paths: B (Php 4,000), A (Php 8,000) on A-B and E (Php 5,000), F (Php 2,000) on E-F.
- Crash B on activity A-B and F on activity E-F: 10,000 - 4,000 = Php 6,000 net savings and 10,000 - 6,000 = Php 4,000.
- Verify paths: with one crash week on both paths, A-B and E-F would be 20 weeks compared to the 17 weeks of path C-D
- Paths: Re-rank activities on the critical paths
- Additional Crashing :Crash B on path A-B and E on path E-F.
- Subtraction Savings: Total savings = Php 1,000
Project Duration
- No further improvements are possible since activity A would mean Php 8,000 and acitivity E means 5,000 for a Php 13,000 total
- Activity A + E exceeds the Php 10,000 potential savings in indirect costs to improve 1 week
- Crashing Sequence: Summarize the project with respective lengths of weeks and activity costs
- Optimum costs in project length can be seen by comparing the project cost chart
Illustration 4:
- Question: Can project be done in 18 weeks for less than Php 75,100
- The Normal Time Critical Path B-D-F-I equals 33 weeks, with a direct cost of Php 44,000.
- Calculate Path lengths : Determine various path lengths and identify critical path, listed as A,C,F,I ; B,E,H ; B,D,F,J ; B,E,G,I
- Determine a critical path which is B, D, F, I with 33 weeks
- Prioritize critical path activities to see if crashing any activities with the lowest costs would bring savings
Crashing Savings
- Calculate paths B, D, F, I and reduce the savings
- D is the lest expensive to crash at at cost of Php 500
- Next, crash/reduce activit B to its minimum and subtract to see crashed activity
- Lastly, take the savings after multiplyiing cost/week * weeks to see crashed savings
- After savings are calculated, crash the activity costs to see if the net savings is in accordance for the overall project
Network Path Results
- Reduce critical project, follow this order to reduce costs in respective manners
Relaxing the Path
- First, analyze the costs remaining to reduce
- Next, find weeks to uncrash and perform the total cost and weeks saved
- Perform with lowest cost and go up
- Next, calculate project results after relaxing non-critical path activities
- This allows the team to calculate new savings and cost parameters
Uncrashing Cost
- In Crashing Cost, start crashing on least expensive activities, while in cost reductions, focus on the most expensive activities being worked on.
- When activity F is relaxed, activity A ,C, F, & I can have an optimum time.
- Calculate the new optimum
Optimizing Path Savings
- Determine activities that have no been uncrushed to see what is a bottleneck
- Activity E and G are not on the critical path
- Reduce Activity E and G costs to gain additional work recovery
- Calculate final costs and optimum savings
Optimum costs
- There is always direct costs and indirect costs within a project with the team performs activities for both.
- Total Savings: The team works to optimize and reduce costs during tasks and find alternatives.
Project cost comparison
- 18-20 weeks: Between 18 weeks or 20 weeks, only direct and indirect costs are counted
- 20 to 33 weeks: If project goes over the 20 weeks duration for the overall project then the utility is calculated
- Indirect costs: utility expenditures and operations bond (the like)
- Utility Costs: bonuses or penalties for performing a project quick or late.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.