Contract Costing Method Quiz
10 Questions
1 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the method of Costing used when a job is large and requires considerable time to complete?

  • Process costing
  • Activity-based costing
  • Job costing
  • Contract costing (correct)

What determines the completed contract price in contract costing?

  • Architect certificate (correct)
  • Contractor's estimate
  • Contractee's assumption
  • Market price index

When is the contract price paid to the contractor in contract costing?

  • Based on contractor's estimate
  • Before initiation of work
  • Monthly installments
  • After completion of work (correct)

In contract costing, what kind of account does the contractor prepare for each contract?

<p>Contract account (A)</p> Signup and view all the answers

What does the debit side of the contract account in contract costing record?

<p>Expenses incurred by the contractor (A)</p> Signup and view all the answers

What type of companies typically adopt contract costing?

<p>Building construction companies (B)</p> Signup and view all the answers

What is another term for contract costing?

<p>Terminal costing (B)</p> Signup and view all the answers

How does a contractor determine the profit or loss of a particular job in contract costing?

<p>From the architect certificate (D)</p> Signup and view all the answers

Who pays the contract price to the contractor in contract costing?

<p>Contractee (A)</p> Signup and view all the answers

What is considered as a cost unit in contract costing?

<p>Each contract (D)</p> Signup and view all the answers