Questions and Answers

How many total residential units are included in the Union Court Apartments project?

  • 80
  • 111 (correct)
  • 12
  • 57
  • The project includes only townhouse buildings.

    False

    What is the purpose of a Draw Request in a construction project?

    To request payment for work completed.

    The line item that indicates the original contract price is labeled as Line ____.

    <p>1</p> Signup and view all the answers

    What types of parking facilities are included in the project?

    <p>Both detached parking garages and surface parking spaces.</p> Signup and view all the answers

    Change orders can only increase the original contract price.

    <p>False</p> Signup and view all the answers

    What is the AIA G702-703 form used for?

    <p>Application &amp; Certification for Payment.</p> Signup and view all the answers

    The total number of surface parking spaces provided in the project is ____.

    <p>179</p> Signup and view all the answers

    Which of the following is not a part of the typical draw package contents?

    <p>Tax Assessment</p> Signup and view all the answers

    What is the purpose of retainage in a construction contract?

    <p>To hold back a percentage of payment until project completion</p> Signup and view all the answers

    The contract sum to date includes only the original contract price.

    <p>False</p> Signup and view all the answers

    What does line 6 represent in a construction payment application?

    <p>Total Earned Less Retainage</p> Signup and view all the answers

    Retainage is typically a percentage between ______ and ______.

    <p>5%, 10%</p> Signup and view all the answers

    What is subtracted from total earned less retainage to determine current payment due?

    <p>Previous certificates for payment</p> Signup and view all the answers

    Materials that are stored onsite contribute to the total work completed calculation.

    <p>True</p> Signup and view all the answers

    What does line 9 indicate in a construction payment calculation?

    <p>Balance To Finish, Including Retainage</p> Signup and view all the answers

    Line 7 subtracts previous certificates for ______ from the total earned less retainage.

    <p>payment</p> Signup and view all the answers

    When does retainage typically get paid out?

    <p>Once the project reaches a certain completion percentage</p> Signup and view all the answers

    Requisition #13 is associated with the period ending on 04/30/2022.

    <p>True</p> Signup and view all the answers

    What are the two primary components of a project development budget?

    <p>Sources and uses</p> Signup and view all the answers

    The SMT Development Progress screen is used to track __________ during construction.

    <p>progress</p> Signup and view all the answers

    Which type of housing project is the WWHA HOUSING PRESERVATION PORTFOLIO?

    <p>Moderate rehabilitation</p> Signup and view all the answers

    There are 21 buildings involved in the moderate rehab project in Walla Walla, WA.

    <p>True</p> Signup and view all the answers

    What is indicated by '3P Monitor SV' in the context of Union Court projects?

    <p>It is a monitoring system for project reporting.</p> Signup and view all the answers

    The Box Folder Path for Union Court includes areas for __________ and Financials.

    <p>Due Diligence</p> Signup and view all the answers

    What process is involved during the construction phase of Union Court Apartments?

    <p>Monthly reporting</p> Signup and view all the answers

    What is included in the 'contract sum to date' calculation?

    <p>Original contract price plus change orders</p> Signup and view all the answers

    Retainage percentages are typically fixed and do not vary by state.

    <p>False</p> Signup and view all the answers

    What does line 6 in a construction payment application represent?

    <p>Total earned less retainage</p> Signup and view all the answers

    The percentage of payment held until project completion typically falls between ______ and ______.

    <p>5%, 10%</p> Signup and view all the answers

    What is typically subtracted to determine the current payment due?

    <p>Previous payments received</p> Signup and view all the answers

    Materials stored onsite do not contribute to the total work completed.

    <p>False</p> Signup and view all the answers

    What is the purpose of the SMT Development Progress screen?

    <p>Track progress during construction</p> Signup and view all the answers

    The UNION COURT project is associated with only one requisition number.

    <p>False</p> Signup and view all the answers

    What specific type of construction project is UNION COURT - 79596?

    <p>Residential apartments</p> Signup and view all the answers

    The project WWHA HOUSING PRESERVATION PORTFOLIO involves the moderate rehab of _____ buildings.

    <p>21</p> Signup and view all the answers

    Which of these documents is NOT part of the Box Folder Path for UNION COURT?

    <p>Construction Contracts</p> Signup and view all the answers

    Which building type is not part of the Union Court Apartments project?

    <p>15-Unit Apartment Complex</p> Signup and view all the answers

    The original contract price can change after the contract is signed.

    <p>True</p> Signup and view all the answers

    What is the total number of residential units in the Union Court Apartments project?

    <p>111</p> Signup and view all the answers

    A typical draw package may include a change order log, a lien waiver, and an owner's sworn ______.

    <p>statement</p> Signup and view all the answers

    What does Line 2 in a construction payment calculation represent?

    <p>Net change by change orders</p> Signup and view all the answers

    A negative change order indicates work was added to the original contract.

    <p>False</p> Signup and view all the answers

    The total number of surface parking spaces provided in the Union Court project is ______.

    <p>179</p> Signup and view all the answers

    Study Notes

    Session 4: SMT & Box Use and Process During Construction

    • Session focuses on a construction management system (SMT) and box (likely file storage) use, along with project processes during construction.

    Project Timeline

    • Dates listed are for training purposes only.
    • Project: Under Construction → Collect Monitoring Docs
    • Key dates include:
      • PM HANDOFF to AM, NTP
      • CONSTRUCTION COMMENCES
      • PROJECT UNDER CONSTRUCTION
      • COLLECT MONITORING DOCS
      • CRM SITE VISIT
    • Specific dates are shown on a graph (not extracted)

    Union Court Apartments SMT # 79596

    • New construction project with multiple buildings:
      • 80-unit senior apartment building
      • 12-unit townhouses (three buildings)
      • 5 detached parking garages (accommodating 57 vehicles + 179 surface parking spaces)
    • Total of 111 residential units
    • Included parking garage

    Notice to Proceed (NTP)

    • Union Court MF, LLC issued an NTP to Construction Management Associates, Inc.
    • Effective date: March 9, 2021.
    • Estimated construction duration: 20 months.
    • Scheduled substantial completion date: July 29, 2022.
    • Project involved Union Court Apartments and Union Court Townhomes in Kenosha, Wisconsin.
    • Also mentioned a different project, The Vista at Creekside in Pleasant Prairie, Wisconsin, with a different agreement and a substantial completion date of December 31, 2020.

    SMT Construction Checklist screen + Box Upload

    • Screen displays project-related information.
    • System has an update available.
    • Includes various tasks, forms, and checklists.
    • Includes a Notice to Proceed document.

    Typical Draw Package Contents

    • Includes documents like a Draw Request, Requisition (Application & Certification For Payment, using AIA G702-703), Executed Change Orders (with backup documentation), Change Order Log, Lien Waivers, Owner's Sworn Statement, and project cost schedule documents and supporting documentation.
    • Includes soft cost invoices, architect's invoices, interest, legal documents, and other relevant documentation.

    Additional Project Information

    • Documents include AIA Document A101-2017 and G702-703.
    • Project timelines and dates are provided specifically for the Union Court project in various documents.
    • Specific change orders were issued with amounts detailed for each order
    • Project involves multiple buildings, garages, and residential units, likely in Kenosha, WI.
    • Details of specific work, including additional railings, stone placement, privacy dividers, and light pole replacements, are part of change orders.
    • Project information, like conduit, pull boxes, roof drains, lumber costs, and sanitary laterals, are included as part of the change orders.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Test your knowledge on key concepts in construction project management, focusing on the Union Court Apartments project. This quiz covers topics such as draw requests, contract pricing, and construction payment applications. See how well you understand the various components that make up a successful construction project.

    More Like This

    Construction Project Management
    5 questions
    Construction Project Management Roles Quiz
    6 questions
    Construction Project Management Basics
    10 questions
    Construction Project Management
    24 questions

    Construction Project Management

    AuthenticFantasticArt avatar
    AuthenticFantasticArt
    Use Quizgecko on...
    Browser
    Browser