Construction Project Management Chapter 6: Mobilization and Scheduling

MatureBauhaus avatar
MatureBauhaus
·
·
Download

Start Quiz

Study Flashcards

10 Questions

What are some of the temporary services and facilities needed for a construction project's work site?

Temporary services and facilities such as temporary power, water, toilets, storage, and security.

What is the purpose of developing a detailed plan and schedule for a construction project?

To assist with deploying personnel and equipment, procuring materials and supplies, and planning cash flows.

What activities does mobilization encompass in construction project management?

Activities between the award of the construction contract and the beginning of construction work in the field.

What is the significance of organizing the work site in construction project management?

To allow the work to proceed efficiently and effectively.

What does the term 'mobilization' refer to in the context of construction project management?

It encompasses activities between the award of the construction contract and the beginning of construction work in the field.

What is the term 'buyout' in the context of construction project mobilization?

Procuring the materials and equipment that will be installed in the project and arranging subcontracts.

What is the purpose of the project S-curve in construction projects?

To show the cumulative costs across the duration of the project.

What does cost control in construction project management involve?

Influencing factors that create change to the cost baseline, monitoring cost performance, and ensuring that all appropriate changes are recorded accurately.

What is Earned Value Management (EVM) in construction project management?

A project performance measurement technique that integrates scope, time, and cost data.

What does the term 'site layout plan' encompass in construction project management?

It includes jobsite space allocation, jobsite access, material handling, worker transportation, temporary facilities, and jobsite security.

Test your knowledge about the activities that take place between the award of the construction contract and the beginning of construction work, as well as programming and scheduling in construction project management.